January 16, 2025

CT Construction Digest Thursday January 16, 2025

Fishing pier by Connecticut River Bridge in Old Lyme to be removed this spring

Kimberly Drelich

Old Lyme — The fishing pier and boardwalk at Ferry Landing State Park will be removed starting early this spring and will remain absent for the duration of the multi-year, $1.3 billion bridge construction project to replace the Connecticut River Bridge, according to Amtrak.

An improved pier and boardwalk will be installed at the end of the project, which entails building a new railroad bridge between Old Lyme and Old Saybrook and demolishing the existing 1907 bridge, said Amtrak spokesman W. Kyle Anderson.

Trains are anticipated to begin running on the new bridge in 2029, but the overall project, including the demolition of the existing bridge and opening of the new pier and boardwalk, is slated to be completed in 2030 or 2031, he said.

A new fishing pier is being built at Eagle Landing State Park in Haddam, which will provide an alternative fishing spot during construction, he said.

A sign at the entrance to the Old Lyme boardwalk tells people that during the closure, they can fish at the new Haddam fishing pier and at the fishing pier by the Baldwin Bridge in Old Saybrook.

Anderson said the pier and boardwalk need to be removed for the construction of the new bridge and demolition of the existing bridge. He said Amtrak is using some of the park property for construction access, parking and storage. He said the removal of the pier and boardwalk is expected around late March or early April.

The new fishing pier and boardwalk will be located slightly west of the current pier and closer to deeper water, which will improve the experience for anglers, and feature a new observation deck and stairway, Anderson said.

Will Healey, director of communications for the state Department of Energy and Environmental Protection, said the department knows "that anglers, and members of the public enjoy the pier at Ferry Landing State Park for fishing, and to take in the scenic views and outstanding wildlife viewing," and the public still will be able to access Ferry Landing during construction, but parking and shoreline access will be greatly reduced.

Healey said Amtrak's improvements to the 1,000-foot-long fishing pier at Ferry Landing will include extending the pier further out into the river and widening it from 8 to 12 feet wide. The existing pier is supported by wooden piles, but the new pier will be supported by concrete piles with a wooden deck.

Ferry Landing State Park sees about 13,345 angling trips each year, according to data provided by DEEP from the National Oceanic and Atmospheric Administration Fisheries’ Marine Recreational Information Program. The park site is also home to DEEP's marine headquarters.

Construction on the new fishing pier in Eagle Landing began in December, and the new structure is scheduled to open in early spring, Anderson said.

Healey said the failing 100-foot pier in Haddam was originally built as a boat dock for a cruise line and will be rebuilt as a fishing pier with benches, rod holders, and cutting boards. The new Haddam pier should be open to the public before demolition of the Old Lyme pier begins.

New bridge to be taller

A groundbreaking for the Connecticut River Bridge project was held in September. Amtrak CEO Stephen Gardner said at the event that the new bridge will be more reliable and resilient than the existing bridge. It will have a taller span so it will need to open less frequently for boat traffic and will be prepared for rising water levels. Train speeds will be able to increase from 45 mph to 70 mph.

Gardner said there will be about 150 workers on average during construction, reaching a peak of 300 workers.

An access road has been set up on Shore Road, and fencing has been installed in the park.

Old Lyme First Selectwoman Martha Shoemaker said there are people in the community that use the Old Lyme pier as well as people from other communities that fish there and enjoy walking along the river. Shoemaker said a resident recently was concerned about the planned pier closure after the signs went up and asked if the town made the decision, but Shoemaker explained that it was not the town’s decision.

“It’s going to be missed, but it is going to be rebuilt,” she said.

She said she thinks the pier closure will be a loss to the community for the time being, and people will have to decide if either of the alternatives are possibilities for them, as Haddam can be a “bit of a haul” from Old Lyme.

Old Saybrook First Selectman Carl Fortuna, Jr. said he assumes the change will lead to additional anglers in town, and they are more than welcome to use the Baldwin Bridge fishing pier.

Shoemaker said that Old Lyme, which sees an influx of seasonal residents in the summer, so far has not seen too much of a change from the project, though the community might see some changes once beach traffic starts. But, that said, the workers tend to be at the site earlier in the morning.

She said one of the town's hopes is that some of the construction workers will visit local restaurants and stores while in the area.

She added that the bridge replacement project will bring needed improvements.

“It’s greatly needed to make sure everything is safe for train travel, but it is going to take a long time to get done,” she said.


Montville officials urge Lamont to widen Mohegan-Pequot Bridge

Daniel Drainville

Montville — As the state Department of Transportation designs a $32.8 million rehabilitation of the Mohegan-Pequot Bridge, town officials have sent a letter to Gov. Ned Lamont saying the span needs to be wider.

In its letter, the Town Council strongly urged Lamont to consider adding two lanes to the bridge instead of just rehabilitating the two existing ones.

The letter was signed Tuesday by Town Council Chairman Tim May and Mayor Leonard Bunnell, then sent to Lamont, DOT officials and legislators.

The DOT's current plan to rehabilitate the bridge, which is in a design phase and not scheduled to begin construction until 2027, does not include bridge widening, only the replacement, rehabilitation or upgrading of certain components, and painting.

But officials from Montville and Preston, along with local legislators, in meetings with the DOT, have urged that the bridge be widened, and that a bike or pedestrian lane be added.

They have said the DOT should consider major developments underway, scheduled or planned such as housing and tribal projects like the Mohegans' Preston Riverwalk and Foxwoods' Great Wolf Lodge, which they say will substantially increase traffic on the bridge.

During a DOT public information meeting at the end of last year, Bunnell, state Sen. Cathy Osten, D-Sprague, and state Rep. Derrell Wilson, D-Norwich, said project planners had not thoroughly evaluated how development would affect the bridge's needs. They said the widening should be done at the same time as the $32.8 million rehabilitation.

I don't think it's too late to consider that," Bunnell said.

DOT officials indicated they had considered widening the span as part of the project, but it had been a much costlier option. Superstructure replacement, which would allow the widening, would cost about $206 million, while replacing the bridge would cost about $227 million.

DOT spokesperson Josh Morgan said Tuesday that Osten and local officials met again with the DOT on Monday and were told the department will have a consultant look at the existing traffic on the bridge to determine the potential impact of future development in the area.

"In the meantime, the rehabilitation project is critical to ensure the structure remains in a state of good repair until a future solution is identified and executed," Morgan said.

DOT officials have said certain components of the bridge have deteriorated to below acceptable standards.

Bunnell described the letter as "kind of a plea" to Lamont to consider widening the bridge.

"We're really kind of questioning the Department of Transportation, and pushing them to maybe use that money more wisely and seek to get a bigger bridge, added May.

The letter also cites various studies over the years that identified the need and local support for widening the bridge.

Bunnell said the town is trying to persuade Preston, Norwich, Groton and Ledyard officials to also push for widening the bridge.


New Estimates Push Madison Community Center Cost $8 Million Over Budget

Francisco Uranga

MADISON — The committee leading the project to convert the former Academy School building into a community center concluded that keeping the project as it was originally envisioned would require at least $8 million more than the original budget. 

This is more than the amount presented at last week’s public hearing, where the majority of people present expressed their opposition to the project.

First selectwoman Peggy Lyons told the audience last week that the bids received in December were between $5.2 million and $7.6 million over the original budget.

The revised cost of nearly $24 million is 50 percent higher than the budget approved in the 2022 referendum, and also exceeds the $7.6 million the project received in state and federal grants.

Joseph Ballantine, chair of the Academy Community Center Building Committee, explained the updated estimates Tuesday at a Board of Selectman meeting. He said he wanted to show the board the cost of the full project before discussing things to cut.   

“You should note that we are not too far from the amount of the grants that we believe we could do enough changes in scope or get down to meet that,” Ballantine said. “We wanted to start with the full cost of the project before we began to reduce the scope.”

Given the escalating costs of the project, blamed on inflation and certain technical contingencies such as the need to replace the septic system, the selectmen expressed their intention to call for a new referendum on May 6 to increase the budget and maintain the project as it was originally proposed to the community. 

Built in 1921, the Academy School operated until 2004, after which the school board vacated it and handed it over to the town in 2011. Following years of deliberation, town officials held a referendum approving $15.9 million to turn the building into a community center, with the intention of seeking grants to reduce the total borrowing required.

The original project included a gymnasium, commercial kitchen, recital hall, additional parking lots, and town department office space. The work included improvements to the heating and air conditioning systems, roof and window repairs, removal of lead paint and asbestos.

Ballantine told the selectmen that after a detailed review of project costs on Monday, the committee had reduced upgrades to the recital hall, gymnasium and playground and eliminated other items they deemed unnecessary. But these changes weren’t enough to bring down the cost. 

During the meeting, town construction manager Ben Whittaker also recommended increasing the contingency, or the amount of money set aside in case a project unexpectedly becomes more costly during construction. This would push the project cost even higher. 

“What you really don’t want to do is go out to a referendum again and then find out that your bids don’t work,” Whittaker said. “It is painful to go back for more money.”

Lyons asked the committee to put together a list of what items would and would not be included in the project. 

Committee member Joan Walker explained that some of the cuts included the elimination of recital hall sound equipment and the gymnasium bleachers. But Lyons pointed out that the recital hall would not be an auditorium-style theater.

“I just want to make sure there’s no confusion,” Lyons said. “That room was always seen as a multi-functional room that would serve the community, and you could do a small theater on the stage.”

Lyons proposed that at the next board of selectmen’s meeting, a vote be taken to set the date of the new referendum for May 6. She clarified that they would have until April 9 to determine the final amount the town would request for the community center. 

Selectman Al Goldberg asked about the possibility of requesting the current vendors to maintain the bid they have made, which are set to expire March 20. 

But Lyons replied that she did not see a benefit in keeping those bids.

“These bids were way off what the estimates were. The more I think about this, why are we bending over backward to accommodate a bid package that kind of blew our budget?” Lyons said. “We know we’re risking that these could creep up again, but I don’t feel we’ve got great pricing that we’re trying to hold.”