June 29, 2026

CT Construction Digest Monday June 29, 2026

Years-long CT gas pipeline stalled at the finish line. Why the $200M+ project faces a permit dispute

Edmund H. Mahony 

After seven years, $150 million and 31 of 34 miles already under ground, the state has halted a pipeline project designed to provide a more dependable natural gas supply to the booming southeastern Connecticut economy.

The reason for what could become years of delay is a decision by the Department of Energy and Environmental Protection requiring a comprehensive environmental review of parts of a mile or so of what remains to be completed of Eversource’s southeastern Connecticut gas resiliency project.

The environmental impact evaluation is limited to a plan to install gas pipeline on a little more than a mile of Eversource electric rights of way that cross the rugged granite ledges of two state parks on either side of the river where the towns of Middletown, East Hampton and Haddam meet.

To the west, the right of way crosses about 100 feet of a narrow strip of Penn Central rail line that is now Connecticut Valley Railroad State Park. On the east, about a mile of pipe would run across the south end of Hurd State Park, part of which was donated to the state by one of the companies that became Eversource, the Hartford Electric Eight Company. Connecticut River

The central piece of the yet-to-be completed stretch of pipeline would be tunneled beneath the Connecticut River. The stretch beneath the river is excluded from the environmental impact evaluation because DEEP said it doesn’t have permitting authority over the submerged land.

If, after the environmental review, the work proceeds, no one would see much of it because there would be little surface disturbance. About two-thirds of the 6,700 feet of 16 inch steel pipe beneath the river and crossing parts of the two parks would run through subterranean tunnels drilled by a high tech boring machine.

The purpose of the 34 mile pipeline from Middletown to Montville is to increase pressure in the existing distribution system and enable the company to continue gas service in the event of a failure by bypassing the trouble spot. Eversource said the region’s high volume gas customers include two casinos; four colleges, including the U.S. Coast Guard Academy; Pfizer’s global Research and Development center; the U.S. Naval Submarine Base; and the Electric Boat division of General Dynamics, which is hiring 8,000 people this year and building the nation’s top defense priority, the Columbia class ballistic missile submarine.

DEEP said it is requires an environmental evaluation because Eversource is modifying an easement it has over state land by installing a gas line where only electric transmission lines have been permitted. The company wants to run the pipe below massive, metal pylons carrying transmission lines that once tied the Connecticut Yankee nuclear power plant in Haddam to the electric grid.

For months, contractors with heavy equipment have working along the rights of way to maintain the electric lines.

Not surprisingly, Eversource Gas and its customers disagree with DEEP about the evaluation and resulting project delay. The disagreement has touched on larger questions about whether the state is moving to phase out natural gas, a fossil fuel, before securing adequate replacements.

“I urge DEEP to prioritize the completion of this project and recognize its essential role in safeguarding the well-being of Southeastern Connecticut,” Tony Sheridan, president of the Chamber of Commerce of Eastern Connecticut, wrote in a news opinion column. “The remaining work in Hurd State Park should be approached with thoughtful environmental consideration — but also with the urgency that energy security demands.”

DEEP said in written answers to questions that its environmental impact evaluation is required by law. The department said the evaluation has started and will delay the project at least through spring 2027 because an analysis of the pipeline’s environmental impact on the utility rights of way needs to be studied over all four seasons.

Eversource Gas, which is paying for the state consultant hired to do the impact evaluation, predicted it will delay completion of the project by two or possibly three years. The company estimates delay will push project cost from $193 million to $214 million. As of last month, the company said it had spent $146 million on the project so far.

The gas resiliency project took root about 5 years ago after severe winter storms and deep freezes knocked out power for prolonged periods during the administration of former Gov. Dannel P. Malloy.

“When I became governor I inherited a state that had been hands off on a lot of these issues,” Malloy said. “The storms bared how unprepared we were. The reality had been that there had been a lack of investment over a long period of time. It was all hands on deck quite frankly because no one had been on decks for a long time.”

Unlike today, policy makers then looked favorably on natural gas and even incentivized conversion to gas as an alternative to oil-generate energy.

In response to political pressure, Eversource Gas examined its distribution system’s “resiliency and redundancy” and developed a plan to strengthen it, president Kevin Kelley said. It proposed building 80 miles of pipeline across the state, the most important part of which would be the 34 mile southeast gas resiliency project connecting Montville and Middletown.

The Public Utility Regulatory Authority approved the project, calling it “a fundamental public policy goal, essential to the state’s economic vitality and protection of the public health, safety and welfare.”

Among other things the pipeline would deliver natural gas to fuel cells — like one operated by the town of Colchester that uses an electrochemical process to produce electricity from gas without combustion.

Eversource Gas began construction at the Montville end of the pipeline in 2019. A year earlier it had begun obtaining annual permits from DEEP that allowed it to do geological tests on the company electric rights of way through the parks in connection with locating the pipeline. The permits permitted “geotechnical borings” tests associated with pipeline design.

There were some restrictions on the testing. DEEP notified Eversource by letter that the state was placing conditions based on concern for two species of plants, two species of insect, two species of turtle, a snake and a bird found in the Hurd Park right of way.

“There should be a qualified herpetologist on site to avoid adverse impacts to all state listed reptile species,” DEEP’s letter said. “All personnel working on the project must be apprised of the reptile species description and the possible presence of a listed species, and instructed to relocate turtles and snakes found in work areas or notify the appropriate authorities to relocate individuals.”

To protect the plants, DEEP said all boring had to be done 15 feet away from the listed plants — one of which, the sand blackberry, establishes “utility transition corridors” as habitat. In addition, Eversource was to “install avoidance fencing, flagging or similar measures in the field for all known populations (of the plants)… under the supervision of a qualified botanist.”

To protect the two insect species, Eversource was instructed to avoid test borings at certain times of the year.

There is disagreement between Eversource and DEEP over how and when the company learned the project must submit to an Environmental Impact Evaluation and the ensuing delay.

DEEP said the evaluation is a legal requirement triggered because Eversource wants to modify its easement permitting electric lines on state land in order to permit the additional installation of a gas line. Kelley said the company believed the existing easement was satisfactory and wasn’t told otherwise until after investing years of work on he project.

“So they were well aware that we were planning on going in the easement that our electric friends have,” he said. “We have done some environmental studies on it. We didn’t feel that we had to go through this process. This all came to us as a surprise. Again, the state was well aware that we had this project on going. They approved it in our rate case. We were in contact with DEEP and PURA regarding this as we went through our rate case, explaining where we were at with the program, the costs, all of those things.”

“And then we ran into a roadblock with DEEP when they announced that we had to go through the (environmental impact evaluation) process,” he said.

DEEP acknowledges that it permitted years of testing on the easement associated with pipeline construction. But it said in a statement that doesn’t exempt the project from an impact evaluation.

“DEEP has issued separate licenses for testing related to the gas line dating back to 2018, licenses required in part because the easements did not provide for natural gas,” the agency said. “DEEP reminded Eversource of this need for new or modified easements in March of 2023, and Eversource applied for easement modifications in August of 2025.”

“The Connecticut Environmental Policy Act requires Environmental Impact Evaluations for state agency actions that could have significant environmental impacts where the full degree of the impact is unknown.” DEEP said. “Here, the full degree of the impact remains unknown, but the expansion might significantly affect the environment, given how rich in species and sensitive habitat the proposed easement area is.”

There also is disagreement over discussions between the two sides about whether Eversource needed to get approval from the state legislature in order to cross the Connecticut River with a gas pipeline.

“DEEP initially communicated that they wouldn’t entertain an application for an easement modification within Hurd State Park, claiming that we lacked necessary legislative approval, as the river crossing authority may come up as an issue and that they wanted to help us be aware of that,” an Eversource spokeswoman said.

Eversource said there was a six month project delay in 2024 while it argued that legislative approval was not necessary. Among other things, the company said it has crossed rivers with gas lines at least five times – rivers from Stamford to Ledyard – without obtaining approval from the Legislature. In the end, Eversource said DEEP decided to press the requirement for an environmental evaluation.

DEEP said the question of legislative approval arose because it advised Eversource that it does not have authority to grant easements beneath rivers.

“DEEP shared that those rights may need to be secured from the Connecticut General Assembly, and that ultimately, it’s Eversource’s responsibility to ensure it has the requisite land rights under the river to construct this project. DEEP communicated that whether or not Eversource has those rights would not affect DEEP’s work on the issues within its jurisdiction regarding the river crossing, such as permits,” the agency said.

DEEP said the purpose of its Environmental Impact Evaluation is not to approve or deny projects. The agency said ithe evaluation “recommends mitigation measures to avoid impacts if the pipeline moves forward, and examines alternatives to the proposed action.”

If Eversource does not agree to recommended mitigation measures, or if the easement modification were denied because the evaluation concludes the environmental harm is so great it could not be mitigated, DEEP said, “Eversource may opt to evaluate other options.”

Eversource said source said it already tried that.

Kelley said the company looked at eight alternative locations to cross the river before settling on on the route through the parks.

“Based on the easement we had, this is the perfect place,” he said. “It still is the perfect place to cross.”

If the project should be denied, Kelley said, “We would be in a full scale panic.”


Draft ruling clears way for 7,462-panel solar project near Glastonbury school

Andrew Larson

A proposed 4-megawatt solar facility spanning about 19 acres in Portland is on track for state approval after the Connecticut Siting Council issued a draft opinion endorsing the project.

In its June 18 draft ruling, the council found that the project would provide a public benefit and cause no substantial environmental harm, and that it meets the legal threshold for approval under state energy policy.

Those findings portend council approval of the project, which includes 7,462 solar panels on a 41.9-acre property owned by Walnut Hill Farms LLC. The site is accessed from Old Maids Lane in Glastonbury.

The $9.5 million project would sell power to Eversource Energy under a 20-year tariff agreement. According to the draft findings of fact, North Haven-based Greenskies Clean Energy expects to begin construction in spring or summer 2027, with the facility fully commissioned by the end of 2027.

If that schedule holds, the project would meet the federal deadline for the Investment Tax Credit, which requires solar projects receiving the benefit to begin commercial operation by Dec. 31, 2027.

The Siting Council’s final decision deadline is Oct. 22.

The proposal drew concerns from neighboring Glastonbury because the site sits about 1,050 feet south of Nayaug Elementary School.

Glastonbury was granted party status in the proceeding, and Old Maids Lane resident Charles Walsh participated as an intervenor. Both raised concerns about construction noise, potential glare and long-term site restoration.

The council addressed those concerns, but largely sided with the developer. The draft opinion directs Greenskies to coordinate construction activities with the town and school and to conduct a post-construction noise study to verify compliance with state standards.

Glastonbury, represented by Hartford law firm Halloran Sage, filed comments with the council seeking stronger conditions in the final ruling, including a firm requirement that pile driving occur during school recesses.

Construction would require clearing about 5.2 acres of trees and 4.8 acres of an apple orchard.

The facility is designed to operate for at least 20 years. During that time, Eversource would own the electricity, capacity rights and renewable energy credits generated by the project.


Waterbury Branch trains to be replaced by buses for nearly a year starting July 20 

Brianna Gurciullo

This Wednesday, fares will go up 5% for customers taking CTrail and Metro-North Railroad trains in Connecticut.

On top of that, riders on the Waterbury Branch will switch entirely to bus service starting July 20 because of construction at four of its six stations. Rail service is expected to return in June 2027.

Waterbury branch riders have experienced such switches previously. Buses replaced trains for about two months in 2024 after extreme rainfall resulted in washouts along the rail line. In 2021, trains were unavailable for four months because of infrastructure upgrades.

Last Thursday afternoon at the Bridgeport train station, where the Waterbury Branch connects to the New Haven Line, Abrina Geyer was about to board a bus that already runs on the line between trains.

She said she thinks the full switch to buses, which are a bit slower than trains, will “be inconvenient for a lot of working people and people traveling, period,” and so will the fare hike.

The Connecticut Department of Transportation has said the fare increase and a previous 5% hike that took place in September 2025 were necessary to maintain rail service levels amid rising costs.

Adam Bosworth, who was taking the train Thursday because of car trouble, said he thinks the fare increase has to be done.

“But I think it’s going to take a lot away from people who can’t afford it,” he said.

DOT conducted what is known as an equity analysis last year, finding that the 10% total increase wouldn’t result in a “disparate impact or a disproportionate burden on minority or low-income customers.”

In a statement, agency spokesperson Eva Zymaris said that whenever buses replace trains in the state, fares are charged to cover the costs of bus service. She noted that buses are currently running on the Hartford Line in the place of several weekday trains because of infrastructure work by Amtrak.

At an unrelated event Friday in Wethersfield, DOT Commissioner Garrett Eucalitto said riders continue to pay full fare because conductors must still be paid to check tickets and assist customers.

“We still have to pay for full service of the complement of Metro-North staffing,” he said.

Construction on the Derby-Shelton, Ansonia, Beacon Falls and Seymour stations started in May and is scheduled to finish by spring 2028. The work is part of an estimated $193 million effort to upgrade all the stations on the branch, whose ridership and service levels are up about 47% and 35% from pre-COVID levels, respectively.

Officials have said that work at the Beacon Falls and Ansonia stations can’t be done safely while trains are running on the single-track line.

“This includes shifting the track to align with new, longer platforms,” according to a May press release from Gov. Ned Lamont’s office. “Suspending service allows crews to work at both locations at the same time and complete the work as quickly as possible.”

During the outage, DOT also plans to perform bridge, signal and infrastructure upgrades between Stratford and Bridgeport as part of a separate project.

“By completing these efforts together, the state expects to save more than $47 million and shorten the Waterbury Station improvements by approximately one year,” according to the release.

Cheryle Corbo, who takes the Waterbury Branch a couple days a week to avoid paying high gas prices, said she would like to see improvements to the experience on the trains themselves.

“People are loud and obnoxious,” Corbo said. “There’s 17 different iPhones going at the same time, with people’s music blasting. Nobody says anything to them. I think that’s so rude, so unacceptable. They need to work on that.”

Come July 20, Corbo said she will probably drive because she is concerned about the reliability of the buses.

“I only have to come in two days a week. I don’t want to deal with that,” she said. “I’ve heard too many times that the buses don’t show up or they’re late and you don’t have any notification.”

Zymaris from the state DOT said riders “can still expect the same level of service and reliability while being bused to their destination.”

At the event in Wethersfield, Lamont announced that on July 4 and 5, there will be free rides on CTtransit buses and $2.50 fares charged for rides between stations on the Hartford Line and Shore Line East for celebrations of the 250th birthday of the U.S.


Estimated $5 million Middletown roads project expected to lessen crashes

Cassandra Day

MIDDLETOWN — A road construction project — estimated to cost a little over $5 million — awarded state funding years ago has been reworked with a smaller scope.

The Saybrook Road reconstruction and pedestrian access project is slated for Saybrook Road, from Tryon Street to the intersection of East Main Street, Acting Deputy Director of Middletown Public Works Brian Gartner said in an email Tuesday. The area has been identified as having an excess of motor vehicle crashes, and the project aims to address that, local officials said.

Gartner said the project is estimated to cost anywhere between $5.1 million and $5.3 million.

Construction will be primarily funded by a $3.3 million state Local Transportation Capital Improvement Program grant, Gartner said during a presentation to the Common Council at its June 1 meeting.

“The potential exists for supplemental LOTCIP funding, and will be explored once the design is complete and the final cost estimates are available,” he explained Tuesday.

The city will pay for the project design and nonparticipating construction costs that aren’t eligible for funding. Money will come from speed camera revenue, Gartner said June 1.

The project was initiated in 2013. Recommendations included further work, including on other streets, such as Bow Lane and Wall Street. That is no longer in the plan, Gartner said. 

There were a few problems in the project's first iteration, Gartner said June 1, including that it was a "little too ambitious for funds available at time," he added. 

Nocera said 39 easements were needed from nearby property owners to widen the road in the first rendition, which, he added, proved "impossible." Now, only eight properties would be affected, according to the slideshow.

“We’re looking to take far less property. We’re looking to have far less impacts on private property,” Gartner said June 1. “There will essentially be no impacts on the east side of the road now, where previously we were looking to encroach on several properties pretty significantly with the addition of the bike paths and sidewalks,” he explained.

The city’s 2013 Complete Streets master plan lists Saybrook as a priority to incorporate complete streets policies, according to Gartner's PowerPoint presentation at the June 1 meeting.

Proposed improvements include building an 8-to-10-foot-wide multiuse trail on the west side of Saybrook Road, Gartner said in the email Tuesday. Also, one travel lane in each direction will have 2-foot-wide shoulders. 

“The existing pavement will be milled and overlain except in areas that require widening, and existing curbing will be replaced with concrete curbing,” Gartner said Tuesday. Also, existing catch basins will be relocated as necessary.

Data Gartner obtained from the University of Connecticut Crash Data Repository shows there were more than 50 accidents over a five-year period in the blocks surrounding Saybrook Road, including at the intersection of Mill Street, Wall Street, and the Stop & Shop plaza, he said.

Presently, there is a well-worn but narrow path made by pedestrians, he said during the meeting.

“There are always folks walking on the side of the road. There is no safe passage for people to get from the shopping plaza, to the school, to the apartments. (Bielefield) Elementary School children who walk to school need to cross Saybrook Road. Yet again, there’s no provisions for crosswalks, for sidewalks, there’s no safe way to accommodate this movement,” Gartner continued.