EB breaks ground on $500M pier project
Alison Cross
Groton — Electric Boat broke ground Monday on two new piers that will triple the shipyard’s capacity for post-launch submarine construction, testing and upkeep.
In a dockside news conference, U.S. Rep. Joe Courtney, D-2nd district, said the company’s $500 million investment will allow EB to accelerate submarine delivery well into the future.
“This is really ultimately about trying to get the production cadence up to a faster point, which is exactly what the Navy and Congress are really pushing for,” Courtney said.
“You don't make an investment like this unless you're playing the long game,” Courtney later added. “This is going to ensure that the employment (and) the work that's been happening in this program is going to continue for decades.”
EB said the two concrete wet berths, which are 53 feet wide and 510 feet long, will accommodate up to four Virginia and Columbia-class submarines — increasing the shipyard’s waterborne berths from two to six.
EB said each pier will be equipped with a crane mounted on rails as well as electric, water and air support systems. The primary contractor for the project, Weeks-Cashman JV, is expected to complete the south pier in November of 2028 and the north pier in April 2030.
Devin Xenelis, EB’s director of facilities and real estate, said the piers will support the Columbia and Virginia post-launch programs.
“These will accommodate ships after they're launched and handle all the work that happens post-launch for delivery,” Xenelis said. “There'll be in the hundreds of people out here working … (and) cranes on each pier that support loading of any of the final ship's equipment pre-delivery and all of the utilities and systems that are required to bring the ships off to sea when they're complete.”
Xenelis said crews dredged hundreds of thousands of cubic feet of sediment from the Thames River to accommodate the project.
“Getting to this milestone required months of dredging, underwater rock blasting, environmental coordination, and site preparation,” Beth Rafferty, EB’s vice president of real estate and facilities, said.
“What makes this project especially challenging is that we're building in the middle of an active shipyard,” Rafferty added. “Submarine construction work happening around us cannot and does not stop. Submarines will continue to be built, testing will continue, deliveries will continue. Our challenge is to construct this major new infrastructure while supporting one of the nation's most important shipbuilding operations.”
Rafferty said the construction is an important part of the “EB Now” initiative, which includes the ongoing conversion of the former Crystal Mall into EB’s Waterford Campus, and facility, technology and workforce investments throughout the company.
With EB on track to hire 8,000 workers by the end of 2026 and 8,000 more in 2027, Larry Runkle, the vice president of Groton operations, said EB is “building the workforce required to support full rate production of Virginia and Columbia class submarines.” He added that the new piers and other facility investments will provide the “infrastructure they need to succeed.”
Courtney said EB is surpassing expectations with output up 30% in the Virginia program and 55% in the Columbia program compared to last year. However, Courtney said EB still needs to hit the Navy’s target of delivering 2.3 Virginia-class submarines and one Columbia-class submarine a year.
As the Navy works to grow its fleet to 14 ballistic submarines and up to 60 attack submarines, Courtney said submarine projects in the pipeline are expected to continue into the 2040s.
Based on the backlog, Courtney said EB’s workforce of 29,000 employees will likely have to grow to 40,000 to 45,000 to support construction in the coming years.
“There's just no question that even though we are at very high levels of employment, … we have to grow bigger and the production has to go faster,” Courtney said.
Three Connecticut towns could get fuel cell facilities. Vernon seeks a hearing
A renewable energy developer has filed plans to build three
similar fuel cell facilities in New London, Suffield and Vernon.
New York-based Dispatch Energy filed three petitions with
the Connecticut Siting Council on Oct. 7, seeking declaratory rulings that
would allow it to build, maintain and operate a 4.975-megawatt fuel cell
facility in each town. The proposed sites are 75 Crystal Ave. in New London, 2
Bennett Road in Suffield and 784 Talcottville Road in Vernon. All three
properties are zoned for commercial or industrial use, though some are near
residential areas.
At each site, Dispatch Energy would install 16 solid oxide
“Energy Servers” made by Bloom Energy. The company’s equipment has also been
used in projects in New
Britain and Plainville.
Dispatch Energy said in its petitions that the projects
secured 20-year agreements with Eversource and the state Department of Energy
and Environmental Protection in 2025 through a competitive bidding process
under Connecticut’s Shared Clean Energy Facility program.
Under the agreements, Eversource would buy and
distribute the electricity generated by the facilities, which Dispatch Energy
would build and maintain. Eversource would then provide renewable energy
credits to income-eligible homeowners and people who cannot install solar
panels on their properties.
On Oct. 29, Vernon officials asked the Siting Council to
hold a public hearing on the petition. The request included a letter from Town
Planner Ashley Stephens urging the council to “carefully scrutinize” the
proposed facility on Talcottville Road
Stephens said the town wants the council to require a sound
study and sound-attenuating features to shield nearby residential areas from
low-frequency background noise the facility could produce. Her letter also
raised concerns or requests involving stormwater management, technical issues,
compliance with municipal zoning standards and funding for Dispatch Energy’s
emergency response plan.
“We respectfully request that the Siting Council hold a
public hearing or conduct a formal site visit in Vernon to review these
engineering and environmental constraints firsthand before issuing a final
ruling,” Stephens wrote.
The Siting Council is scheduled to consider Vernon's
public hearing request at its upcoming Nov. 12 meeting.
Dispatch Energy wrote in its petitions that the facilities
would not have a substantial adverse environmental effect, owing to an energy
production process that "nearly eliminates" regulated emissions
including particulate matter and requires an initial 1,920-gallon injection of
water but does not discharge or use water after startup.
Dispatch Energy indicated in the petitions that, if
approved, the facilities would begin construction in summer 2027, with an
anticipated six month construction period and electrical generation expected
to begin later that year. In all three cases, the Siting Council has until
Dec. 7 to take action on the petitions and must deliver a final decision by
April 6, barring any extensions.