July 20, 2026

CT Construction Digest Monday July 20, 2026

Bridgeport crane company proposes redeveloping Stratford property into storage yard

Andreas Yilma

STRATFORD — A Bridgeport crane and rigging company is seeking approval to transform property on Stratford's west side into a construction equipment storage yard, giving the company a second location in the region.

The applicant, 348 Surf Avenue LLC, has submitted a coastal site plan and erosion and sediment control plan to redevelop about 1.1 acres spanning several adjacent parcels on Surf Avenue and Charles Street, adjacent to the Interstate 95 southbound Surf Avenue exit.

The property would become a second location for A&A Crane and Riggings, which has provided crane, rigging and trucking services in the Bridgeport area for about 30 years. The company currently operates from 900 Rusciana Ave. in Bridgeport.

The site, which is in Stratford's light manufacturing zone, is currently occupied by Barre Granite Memorials, a stone monument manufacturing and sales business that has operated there since the 1940s. Owner Donna Miller said the business plans to relocate to a smaller location elsewhere in Stratford later this year.

According to the application, the property contains three structures — a garage and two commercial buildings — and is in poor condition, resembling a junkyard.

Plans call for demolishing the garage, renovating the two remaining buildings, installing new lighting and landscaping, and replacing existing asphalt parking areas with gravel and crushed stone. A new 12-foot-wide gravel driveway would be built from Charles Street while the existing driveway from Surf Avenue would remain.

About 15 to 20 pieces of construction equipment would be stored on the site, including mobile cranes parked outdoors. Air handling units and generators would be stored inside the buildings.

The yard would generally operate Monday through Friday from 7 a.m. to 4:30 p.m., although employees could access the property earlier for out-of-state jobs. The application says the site would typically be used only three or four days a week and is not expected to generate offensive noise, smoke, odors, dust or excessive vibration.

The proposal is before the Stratford Zoning Commission, which continued its public hearing until July 22 to allow review of outstanding information. 

The state Department of Energy and Environmental Protection also recommended changes to the project's stormwater management plan, including the use of permeable paving materials such as permeable asphalt to reduce runoff, according to meeting minutes.


Shelton may forgo state funding to speed up Constitution Boulevard project

Brian Gioiele

SHELTON — With completion of the first phase of the Constitution Boulevard work in sight, Mayor Mark Lauretti may turn down state funds, instead dipping into the city's coffers to pay for the remaining two phases. 

Paving on phase one of the Constitution Boulevard West extension — from Bridgeport Avenue up the hillside — is expected to be completed by year’s end, according to Lauretti. 

This work comes some three years after initial groundbreaking, with the delays a product of state Department of Transportation requirements demanded as part of accepting $5 million in Connecticut grant money for the project. 

It is those requirements — and potential for future delays — that has Lauretti rethinking accepting future state monetary awards for the final two phases and instead paying out of city coffers. Lauretti did not have an estimated figure for the work as city officials await bids for the second phase of the road creation which focuses on roadways inside the Mas property, home to what the mayor envisions as a manufacturing hub.

“We may just fund the rest ourselves,” Lauretti told Shelton Economic Development Corp. board members and guests during a tour of the site Tuesday. 

“But we have all the delays from the state for Phase One behind us now,” Lauretti added. “We hope to pave the road (up to the Mas property) by the end of the year.” 

That paving plan involves the lowering of Cots Street by 8 to 10 feet to meet the roadway leading to the Mas property.

Necessary state permits entered an administrative logjam, Lauretti said. It was during that forced hiatus the city learned it had to purchase the state right of way along Bridgeport Avenue — where the city was to break through to connect the road.  

The city purchased the strip of land for $876,000 from the state, land which was then leveled to allow for construction of the roadway. 

The city has been awarded some $3 million state grant for the final two phases: phase two being the roadwork inside the Mas property, which is currently out for bid, and phase three the final connection to Route 110. 

But Lauretti said he remains unsure if he will take the money. 

“We may shift gears, bite the bullet and pay for phase two and move forward,” Lauretti said. 

Lauretti said the city owns virtually all the needed property from Bridgeport Avenue all the way to what would be a connection on Route 110. 

“If we just fund it ourselves, we can build the road quicker, get people on those properties and get people paying taxes,” the mayor added. 

Constitution Boulevard West — long just a concept on paper — will allow development of the nearly 76 acres known as the Mas property, which has been landlocked. The city has already agreed to sell portions to various companies, including Bigelow Tea. 

Shelton Economic Development Corp. President Sheila O’Malley, who has obtained millions of dollars in state and federal aid for various projects over the years, says accepting state funds can add 6 to 9 months to a timeline as the state demands significant paperwork and requirements. 

O’Malley said if the city accepts the $1.6 million for phase two, it would be required to complete an engineering study for phase three — a move that would add a year to the overall project. 

“The goal is not to make money on the sale of the land, although the city will get a significant return,” said Lauretti. 

The city years ago purchased the Mas property for $600,000. The city has reached contract agreements for nearly all 76 acres at $85,000 per acre, which calculates to nearly $6.5 million. 

“The real prize is the taxes the city will collect over the next 40, 50 years. … Imagine what that would mean for the grand list,” Lauretti said. 

The mayor added there remains a “waiting list” to purchase land on the Mas property. While the land has been rezoned for corporate manufacturing, Lauretti said he has even received interest from a hotel and banquet hall. The anchor is Bigelow Tea, which is under contract to purchase some 25 acres and plans to build a 300,000-square-foot facility.

“We’re in a really good position here,” Lauretti said. “Now we just have to finish this.” 


Naugatuck road project will close key streets for about a month starting Monday, police say

Tyler Fedor

NAUGATUCK — Motorists in Naugatuck “should expect significant traffic impacts” as road construction begins Monday near May Street and Lincoln Street, according to a post on the Naugatuck Police Department’s Facebook page. 

Police said these roads and intersections will be closed to through traffic for about a month starting July 20: May Street between Donovan Road and Mulberry Street; Lincoln Street between May Street and Auburn Street; May Street at Donovan Road; May Street at Mulberry Street; Lincoln Street at May Street and Auburn Street at Lincoln Street.

There will be detours, but those could change as construction goes on, police said. 

“We encourage motorists to plan ahead, allow extra travel time and use alternate routes whenever possible,” police said. “Thank you for your patience and cooperation as these roadway improvements are completed.”


Major changes planned for a Route 15 interchange, including removal of stop signs

Brianna Gurciullo

It's out with the stop signs on the Wilbur Cross Parkway near the Hamden-North Haven border, and in with acceleration and deceleration lanes.

That’s the state Department of Transportation’s plan for the stretch of Route 15 where drivers enter from or exit to Whitney Avenue.

The agency recently announced it will hold a public meeting about the project, which aims to make it easier for drivers to merge onto the parkway, on Sept. 15 at Hamden Government Center. It will also accept comments by email and phone for two weeks after the meeting.

Construction could start as soon as spring 2028, depending on availability of funding, right-of-way acquisitions and permit approvals, DOT said.

On its webpage for the project, DOT said it needs to ditch the stop signs because they lead to a high number of rear-end crashes. It wants to install acceleration lanes for both the northbound and southbound on-ramps and a deceleration lane for the northbound off-ramp.

The interchange currently includes an Exit 51, formerly Exit 61, on the northbound side and an Exit 51 on the southbound side.

DOT plans to remove the southbound Exit 51 off-ramp as part of the project. Drivers would instead use Exit 52, where the agency has proposed installing a signal at the end of the ramp to allow for both left and right turns onto Whitney Avenue.

The agency also wants to install pedestrian crossings where the Route 15 ramps meet Whitney Avenue and build sidewalks where there is currently a 1,500-foot gap along the road.

In addition, a wooden noise barrier along Route 15 southbound would be replaced.

The estimated cost of the construction is about $28 million. In all, 80% of the project’s funding is expected to come from the federal government.

DOT previously provided a cost estimate of $19.6 million, but agency spokesperson Joe Cooper said that figure was from the “conceptual design phase.”

“It later increased to $27.6 million to reflect design updates, including the addition of a retaining wall adjacent to the Mill River and acceleration lane onto Route 15 northbound,” Cooper said.

With both the design and construction costs included, the total estimated cost of the project is $32 million, he said.

Last year, the agency was considering adding bike lanes to Whitney Avenue as part of the project, but DOT did not immediately return a request for comment on whether bike lanes are still part of the plan.


New Hopkins School Gibbs Innovation Center building gets green light in New Haven

Mark Zaretsky

NEW HAVEN — The private Hopkins School, located on a hill overlooking the Westville section, will build a 35,137-square-foot  building to expand research, robotics and technology programs and house the Gibbs Center for Innovation after winning unanimous approval from the New Haven City Plan Commission. 

The CPC approved the project — funded by a record $50 million gift from Hopkins alumnus John C. Malone, the Milford-born billionaire founder and chairman emeritus of Liberty Media Corporation — Wednesday. Malone graduated from Hopkins in 1959. 

Approval came after Hopkins  representatives assured members that all truck traffic would enter only between rush hours and only off Forest Road, which is a state highway.

The project would be built on 2.9 acres of the historic prep school’s leafy 101-acre campus, located on a hill at 986 Forest Rd. overlooking Westville.

Several of the dozen or so neighbors who spoke raised questions about trucks, dust and traffic. Concerns were fueled in part by memories of Hopkins' last big construction project, a now-completed performing arts center, known as "APAC," that is located near the 366-year-old school's northern boundary, off Knollwood Drive. 

That project caused problems for neighbors, several of whom said they would like to see the private school, which is the third oldest independent school in the nation, install sidewalks along Knollwood, which doesn't have them.

The commission stopped short of requiring that, but Hopkins representatives didn't rule out the possibility.

Trucks for the APAC project entered from a different entrance off residential Knollwood Drive, not Forest Road, which is state Route 122, members of Hopkins' development team said. Forest Road is what West Haven's Campbell Avenue becomes north of the Boston Post Road.

Much of the truck traffic would be expected to come through West Haven, off Interstate 95 Exit 43, members of Hopkins' development team said. But Route 122, while residential north of Route 34,  is a much wider street than Knollwood.

Hopkins attorney Meaghan Miles of Carmody & Torrance said trucks would only be allowed to enter and exit the campus between the hours of 8:30 a.m. and 3 p.m., and only through the Forest Road entrance.

The Knollwood Drive entrance, which was used a few years ago for the APAC project, "wouldn't work" because trucks would have to drive the length of Hopkins main quadrangle to get to the new construction site, she said.

"Hopkins' interest in (controlling) trucks is aligned with the neighborhood, because those trucks affect their students," Miles said.

City Plan Commission member and Westville Alder Adam Marchand, D-25, who lives nearby and whose ward borders the campus, said he was glad to see "that you're not going through Upper Westville." But he expressed concerns because "it's a very steep hill getting up there. I know, because I ride my bike up there."

Westville Alder Amy Marx, D-26, who lives on Knollwood, raised questions about the quality of Hopkins' communication with its neighbors, pointing out that she represents "almost all the houses noted on the maps," yet she received no notice of the proceedings.

Marx pointed out that "noise carries in this neighborhood. I hear noise all the way down at 290 Knollwood Drive from the football field." She also expressed concerns about traffic.

Forest Road "is an old carriage road" and "we have serious concerns about how many trucks" it can handle, Marx said. She suggested that it might be a good idea for the commission to require a traffic study as a condition of approval. She also was one of the people to suggest that Hopkins install sidewalks.

The City Plan Commission did not include either as a condition.

More generally, "we have a problem" with Hopkins parents and employees "not being good neighbors," Marx said. "...We have a lot of people thath treat Knollwood Driveway like a motor speedway."

Miles later responded to Marx, saying her office "sent out a little over 250 letters, including on the West Haven side." She said it's in Hopkins' interest, as well as that of neighbors, for the trucks not to disrupt people in the neighborhood or on campus.

Tim Appelbee, an architect with the S/L/A/M Collaborative in Glastonbuy, said they anticipate about 1,400 trucks over 96 days, with a maximum of 4.5 trucks per hour. He pointed out that the APAC project, unlike this one, "was right next to Knollwood Drive.

Other neighbors expressed concerns, including Davis Darsch, who lives across Forest Road from the entrance, who said he worried the construction would make the traffic situation worse. Darsch asked for measures to slow construction traffic and enhance safety, including possibly installing convex mirrors to help guide trucks entering and existing.

"I'm not objecting to the building, itself. I'm asking for protections for people who live directly across Forest Road from the campus," Darsch said.

Corey Smith of Knollwood Drive said he worried about impact on the neighborhood. "We've gone through two previous construction projects with Hopkins," including the APAC project and tennis courts, and the local impact in both cases went beyond what neighbors were led to believe, he said.

"What we found were many trucks ended up idling on Knollwood," with "heavy traffic in the mornings ... and it really creates a dangerous situation," Smith said. 

Erica Garcia-Young, who lives on Allston Avenue on the opposite side of Forest Road, said that a few years ago, "neighbors and I had to work with Hopkins because students were advised to park along Allston Avenue" during a previous project.

Lauren Hui of Oliver Road, also off Forest Road, said she also was concerned about trucks "using streets for idling or staging." She said she would like to see signs posted, stating, 'No construction traffic allowed along neighboring roads.'"

The area where the center would rise is now a lawn, known as Pratt Field, and temporary parking lot at the southern end of the campus quadrangle. It is just south of Thompson Hall on the campus, the application states.

The Gibbs Center is named after pioneering scientist Josiah Willard Gibbs, another Hopkins alumnus — Class of 1854 — whom Albert Einstein once hailed as “the greatest mind in American history,” according to the application.

The Georgian Revival facility would include a robotics design and competition studio — for a program that now serves more than 130 students — and a 2,500-square-foot research center for the school’s Hopkins Authentic Research Program in Science, known as HARPS.

It also would include computer science classrooms, an innovation and fabrication space for engineering, entrepreneurship and interdisciplinary projects, a digital media production studio, a learning center, flexible classrooms and a 360-degree immersive theater, according to the plans. 

The design was prepared by The S/L/A/M Collaborative of Glastonbury, Tighe & Bond, Salas O’Brien and Cavanaugh Tocci Associates Inc. Construction is anticipated to begin in March 2027 and be completed in August 2028.