March 28, 2025

CT Construction Digest Friday March 28, 2025

Portion of Flanders Road to be rebuilt as part of I-95 reconstruction

Jack Lakowosky

East Lyme — Flanders Road commuters might have to visit the car wash more often, as a portion of the road will soon be fully reconstructed as part of the $156 million Interstate 95 Exit 74 interchange project.

Starting in mid-April the road will be gravel for 500 feet from the intersection with Frontage Road to the entrance of Walgreens, said Andrew Millovitsch, project engineer with the state Department of Transportation.

Officials expect the work to finish May 1.

Millovitsch said based on road conditions, the work could extend to the Flanders Four Corners intersection.

Drivers are asked to reduce speed in the work zone, which is part of the effort to widen Flanders, also known as Route 161. Crews have already widened part of Route 161, from Industrial Park Road to King Arthur Drive. Drivers are advised that the work, which will raise the height of the road about two feet in some locations, will be done at night.

Route 161 northbound will eventually be joined with a new road, New Frontage Road, in front of Cash True Value Home Center, with a new four-lane approach consisting of two exclusive left-turn lanes and two through lanes. The southbound approach to this intersection will consist of two through lanes and exclusive turn lanes, according to state information.

In order to widen 161, the I-95 bridges over the road must be replaced. The northbound side of the bridge was recently demolished, work that temporarily closed Route 161.

Crews Thursday were working outside Daddy's Noodle Bar, which is getting its own signal directing drivers onto Flanders Road.

This is all part of the third of four stages in a project meant to make travel safer between Exits 74 and 75, an area with a high number of traffic accidents and 80,000 drivers a day, said project Resident Engineer Robert Obey. Recently concrete barriers were installed to guide drivers into two, 11-foot-wide lanes with 1-foot shoulders compared to the typical 12-foot travel lanes with 3- to 4-foot shoulders, a configuration that will last a while longer.

Between the north and southbound lanes crews are readying the highway for another upcoming change, when southbound traffic will shift to what is now the median from the Route 1 overpass to a location beyond Costco.

Obey said one of the biggest improvements, which comes later in the project, is a new dedicated right-turn lane onto a new Exit 74 northbound on-ramp, eliminating the need for Flanders commuters traveling southbound to take the hairpin left turn onto I-95 north near Starbucks, Obey says. That configuration severely backs up Flanders Road.

That new on-ramp will curve around a new commuter lot, Obey said, and will neighbor the new northbound off-ramp that lands drivers in front of the Flanders Road Burger King.

Obey said the main goal of the project is improving visibility and sightlines. To that end, the height on the south side of the bridge will be raised 14 feet and on the north side, it's dropping 10 feet. Obey said the changes to the highway are some of the most significant of his 35-year career.

The project cost has risen from the original estimate of $150 million, after officials needed more supplies than expected, Millovitsch said. He added it's "amazing" that after two years the large project has only increased in cost by $6 million.

"More than a construction job"

Obey said any major roadway or highway project requires balancing public safety and inconvenience.

"None of it matters if there's a major accident or a fatality," Obey said. "Our job is always to make sure we're operating in the safest way."

"It's not just a construction job," he added. "My wife goes to Costco, our friends and families use these roads. That's why it's important to us."

And sometimes a project requires traffic control measures that may irk drivers. That's why, Millovitsch said, these projects need some cultural engineering, too.

"We're in the Northeast, everyone hustles and bustles," he said, pointing out that when the project started, both cars and trucks often flew by workers on the highway at 80 miles per hour.

Officials piloted a enforcement program last year that significantly reduced speeding.

Obey said the number of people who signed up for updates and alerts about the project, 22,000, surprised him.

"It caught us off-guard how involved people were," he said.


Large Simsbury roadwork project set to begin as Aquarion Water starts water main replacement

Steven Goode

SIMSBURY — When the weather gets warm, construction season heats up.

And more than a half dozen Simsbury streets and the motorists who use them will be subjected to the offshoots of construction season with slow-downs and detours beginning Tuesday and lasting into October.

Aquarion Water Co. will be initiating a water main replacement project that will cover just short of 8,000 feet of pipe. The affected roadways will be Katherine Lane, Windham Drive, Valley View Road, Bob White Way, High Hill Circle, Richard Road, Branch Brook Road and Cornfield Road.

Aquarion officials said the work is part of an ongoing program to improve the company's water distribution system, with Aquarion representatives planning to work closely with residents and businesses to minimize any disruptions.

During construction, residents should expect minor traffic delays and possible detours between 7 a.m. to 4 p.m.

Compass Enterprises Inc. of Simsbury will serve as the contractor for the project, Aquarion officials said.

Peter Fazekas, Aquarion's director of corporate communications, offered several suggestions for motorists and pedestrians. They include following reduced speed limits in the construction zone and any other posted signs; preparing for changes in traffic patterns, lane shifts and the presence of workers and equipment in the roadway; obeying flaggers directing traffic through the construction zone; maintaining a safe distance between vehicles; being aware the roadway may be uneven due to temporary patches and/or steel plates; practicing situational awareness by keeping heads up and phones down; and if walking near the construction zone, ensuring pets are leashed and children are supervised.

In an effort to keep motorists and residents informed about scheduled and unscheduled work, Aquarion uses the Everbridge notification system to call affected customers. Customers are encouraged customers to sign up in advance online for the free service.

For project-related questions, contact Project Manager Brianna Paolillo at 203-362-3070. For service or water-related issues, contact Aquarion customer service at 800-732-9678.


Yearlong road work project to start in Greenwich's Glenville neighborhood next week

Andy Blye

GREENWICH — After years of planning, Greenwich will finally start a major project to upgrade Glenville Road this week.

This project, known as the “Glenville Corridor,” will make changes to the roads and sidewalks between the intersection of Glenville Street and Glen Ridge Road and the intersection of Glenville Road and Weaver Street.

The project area spans about 1,500 feet, from the future home of DeCicco and Sons, past Glenville Pizza to the Shell gas station on the corner at Weaver Street.

Work is scheduled to begin on Monday and it is expected to take a full year to complete, according to the Department of Public Works.

Crews will be widening parts of the road, upgrading traffic signals, filling slopes in some areas, adding sidewalks, adding stamped concrete pedestrian crossings, adding a traffic signal at the intersection of Glenville Road and Pemberwick Road and more.

“This major infrastructure project will reduce congestion, improve air quality, and enhance safety for motorists, bicyclists, and pedestrians traveling along the Glenville Corridor,” DPW wrote in an announcement.

This project has been in the works since 2016, when Greenwich was first awarded grant money to fix the roadway.

The project got into more serious planning by 2019, but the COVID-19 pandemic struck and altered the town’s timeline, in part because construction costs increased the price of the project. Neighbors also objected to some elements of the design, specifically a loss of trees.

The work was supposed to begin last year, but it was delayed after bids came in too high. State legislators helped secure additional funds from the state government, which administers federal grant monies, and put the town on course to start the work this spring.

“The Glenville Corridor is a heavily traveled commuter route, providing access to major highways and local schools,” DPW wrote. “These improvements will help ease traffic flow and create a safer, more efficient roadway for the entire community.”

Visit the town website for additional information, as well as project updates when they are available.


Torrington High School spring sports prepared for many road games as construction continues

Peter Wallace

TORRINGTON – In a world of modern miracles, the multi-million-dollar, multi-year construction of Torrington’s new high school/middle school almost literally under the feet of its faculty, students, coaches and athletes is a local version demanding attention in its clockwork operation.

Budding engineers, architects, construction workers…and athletic directors couldn’t get a more hands-on education in four years of college.

Torrington athletic director Mike McKenna is one of a myriad of heroes he’s happy to name in making it possible, but the dawn of a new sports season makes him a key to another season’s success in a difficult situation.

“It’s controlled chaos,” he chuckles from a storage-room office that will become a  cafeteria storage room when “the envy of every other school in the area” is complete, somewhere around next October.

Meanwhile, former playing fields are rubble, tennis courts are gone and the state-of-the-art Robert Frost Sports Complex with its turf football/soccer playing field and track are almost unreachable in the midst of earth moving tasks in the construction of additional turf fields for softball and baseball in the school’s back yard.

For McKenna, the true miracle is the cooperation he constantly shares with the school’s administration, Parks and Rec Department and outside companies to keep the balls literally rolling.

“I haven’t heard one complaint from coaches or athletes,” says McKenna. “Their only questions are ‘Where do I go?’ ‘What do I do?’.

For many people, the task of providing those answers would be ulcer-producing or worse.

“I haven’t had a heart attack yet,” he laughs, noting that the Covid year was far worse for logistics.

“Then, you never knew what was going to happen the next day. Three kids on a team would show up with symptoms and we’d have to reschedule. This time, we have more control of it.”

To a point. Cooperation, lots of it, is still the key.

Last season, the boys and girls basketball teams were on the road for the final 14 games of their regular seasons while O&G, the prime contractor, began work on the school’s new gym.

This season, while Fuessenich Park and Romanello Field remain home options for baseball and softball games and practices, thanks to the Park Department, McKenna cites 73 away games for all the spring teams, scheduled between April 1 and May 29.

Getting there is the main problem.

“Mary Bussetti and Justine Lunberg, among others, have done backflips for us in Torrington’s branch of All-Star Transportation, the school bus company,” McKenna says. “The reality is they just don’t have enough buses. Nevertheless, it’s come down to just four dates when they can’t help.

 “We have two small buses of our own, but, while we’re trying to get another driver certified, Michelle Matrascia is our only driver.

“Winter was easier because the games were at night. Now, with afternoon games, we’re on the same schedule as the rest of the students.

“In some cases, the administration has allowed us to get kids out of their last classes of the day to accommodate the buses. In others, a bus will drop one team off and come back for another.

“I’m telling coaches they’ll have to wait 15 or 20 minutes sometimes. Nobody gripes.”

Meanwhile, Torrington high school and middle school students are settling into their new school while the rumble of progress continues outside, thanks to the clockwork planning of O&G engineers and Torrington directors Ed Arum and Mario Longobucco and many others.

Student athletes will continue to hit balls out of a park, set new track and field records and win tennis sets thanks to Mike McKenna and many, many others.

“It’s going to be a beautiful facility,” says McKenna, happy for now to have a storage room he can use for an office to help keep it all moving…like clockwork.


Former Briarwood College campus in Southington may become senior housing

Ciara Hooks

SOUTHINGTON— The former Briarwood College property may soon be transformed into a new senior development if the zone change is approved by the Planning and Zoning Commission. 

The project will have 150 age-restricted housing units spread out among seven buildings on site at 2279 Mount Vernon Road. The mix of studio and one-bedroom apartments will range between 350 and 1,000 square feet, Severino Bovino, an engineer and vice president of Southington-based Kratzert, Jones & Associates Inc. said at the recent meeting.

He added a new pool area would be included along with six acres of land dedicated to open space. 

The impacts on the surrounding environment should be minimal, as no new building construction is planned, said Johnny Grunblatt, a representative of New Haven-based PGX Holdings LLC.

Bovino said all roads and facilities would be maintained by the property owner on site and the project would be served by the 311 parking spaces that are presently there.

The site has been vacant since the for-profit school, Lincoln College of New England, closed in 2018, citing enrollment and financial difficulties. It had been founded as Briarwood College in 1966.

PGX Holdings bought the property in 2021 for $3.5 million, according to earlier stories. 

There were a multitude of different options for the 32-acre campus over the years including 83 age-restricted ranch homes and medical offices in 2020. Other ideas were a family center, day therapy and a school. Over the years, the campus has been listed for $6 million to $9.5 million.

PGX Holdings LLC submitted an application on Feb. 18 to change the zone from R-40 to ARCHZ, ultimately going from a residential zone to allowing for an age restricted development for those aged 55 and over.

Once the zone change is approved PGX will return before the PZC for a site plan review/approval. And go before the Southington Zoning Board of Appeals as well to get a variance that will allow for part of the facility to be used as rented space.


Meriden City Manager proposes $36 million in capital improvements that excludes senior center

Mary Ellen Godin

MERIDEN — City Manager Brian Daniels proposed a $36 million capital improvement plan for fiscal year 2026 that falls nearly $1 million under the city’s spending cap and is $20 million less than the current year.

“We have kept it extremely tight,” Daniels recently told members of the City Council Finance Committee. 

Daniels added that funds from the American Rescue Plan Act helped offset additional costs. Funding for the Board of Education, Harbor Brook flood control work and enterprise funds for water and sewer were exempt from the spending cap calculation.

The 2026 expenditure represents a $36 million commitment for capital improvement spending and calls for $4.5 million in net city costs when grants are factored. The cap is 2.5% of the prior year’s general fund revenue or $5,071,555. 

More than 70% of the costs cover seven projects over several years, Daniels said. The capital improvement budget contains the funds allocated for all capital projects in a given year. 

Of the $36 million, $5.8 million will go toward continuing the West Main Street bridge replacements, $5.4 million for almost a mile of a critical sewer main replacement, $4.4 million of annual road resurfacing, $3 million to replace a Carpenter Avenue water storage tank cover, $2.9 million for required lead service line inventory, $2.4 million to replace a ladder truck within 3 to 4 years and $2 million to finish the Edison Middle School roof.

The funds aren’t spent until the projects are authorized and ready to begin.

The capital improvement plan eliminated $25 million included in fiscal year 2025 for a senior center. The proposed senior center at 116 Cook Ave. has been delayed until at least 2027. 

City Councilor Dan Brunet questioned the exclusions from the spending cap and whether the numbers represented a true picture of the city’s obligations. 

“It seems like there are so many things excluded, I’m not sure where we’re going with this,” Brunet said. Some of this “was included in the cap. Our debt service has gone up every year.”

Brunet said the city’s debt service has increased to 7% for the past several years and called for consistency in calculating the city’s debt. 

Daniels said that regardless of where the expenditures fall within the budget, they still need to be paid. For instance, a police cruiser or firetruck may not appear in the capital improvement budget, but it will show up in the police or fire budget line. A school boiler replacement could show up in the Board of Education budget. 

He said he and Finance Director Kevin McNabola would prepare a more thorough review of the prior calculations and projections. 

Department heads from the public works and facilities departments presented the numbers behind the requests. The Meriden Public Library also requested $20,000 to repair window leaks in a portion of the library that was not part of a 2023 $13 million renovation.

Library board members faced some backlash on the request.

“It’s an embarrassment,” said City Councilor Bob Williams. 

Of the $233,072,991 total spending plan, 3.88% comes from increases in seven categories of expenses over which the city and the Board of Education have no control, Daniels recently told city councilors.

Those drivers include $2.6 million in city and BOE health insurance increases, $2.1 million more in salaries and benefits and $1.3 million in debt service on 2024's bonds. 

Hearings on Daniels' $233 million budget proposal will continue through March before a public hearing set for 5:30 p.m. on April 14. 


Park or artwalk? Business owner proposes art tourism site for Capehart Mill: What happens now?

Matt Grahn

The City of Norwich wants to turn the Capehart Mill site into a public park. However, a developer who owns an adjacent property, the former Atlantic Packaging site, says the city will miss out on an economic opportunity if that is done.

Evan Blum wants to buy and merge the Capehart Mill site with his property to develop it into an art tourism site with an artwalk among the ruins, multiple restaurants, a marketplace, a theater, a smaller park space, and space for a solar panel manufacturer. This plan includes the Shawmut Diner building he brought to Norwich in August.

But Norwich officials are not interested in Blum's plan. 

On Feb. 3, The Norwich City Council approved the city's purchase of the Capehart Mill property from A Foot of Fifth for $1. A Foot of Fifth would then pay the city $800,000 "to offset sums owed as a consequence of any liens or encumbrances."

The sale closed on Thursday, March 27, according to Norwich Community Development Corporation President Kevin Brown.

Blum's primary business is Demolition Depot and Irreplaceable Artifacts in New York, which reclaims antiques and architectural features from demolition sites to sell to wealthy clients and film and TV productions. With his clientele, he estimates his plans to redevelop the Norwich site could bring in 5,000 to 10,000 visitors a week, create hundreds of jobs, and spur further investment in Norwich.

Blum and Brown have met to discuss his current property and the future of the Capehart property. Blum said showed Brown a book full of ruins that have been turned into attractions and gave him the artwalk pitch. Brown declined Blum’s plan, Blum said.

Blum's idea is unique, but not effectively planned, Brown said.

"If he came to me with a viable solution, and had a compelling ask, I'd be the first one to work with him," Brown said.

Brown and other city officials are also concerned about Brum's plan because of the condition of his property, the former Atlantic Packaging site. 

"We've not said no to him on these ideas he's floated on Facebook and in other places, but I don't know if he has the means to do it," Building Official Dan Coley said. 

With Irreplaceable Artifacts, Blum hasn't taken the steps to get the permits to convert it from a factory to a storage building. The warehouse's sprinkler system isn't running "which is a major problem when you have that much stuff inside there," said Coley. 

The Shawmut Diner building is also sagging, Coley said. 

"When we've talked to him, he's a nice guy, but he hasn't followed through with anything we've asked him," he said. 

Blum’s complaints about the city’s plans 

Blum claims they hadn't given him a fair shot at explaining the plan. So now he is seeking public support for his plan, so the City of Norwich will talk with him about his plan. If this effort doesn’t work, he’ll consider moving his redevelopment efforts elsewhere.

Norwich is a distressed area, which Blum argues the city isn't doing enough to revitalize. A strong commitment to the arts and private investment has revitalized cities from San Francisco to New Orleans, he said.

Blum insists Norwich’s park plan wouldn't do anything about the drug and crime problems in Greeneville, and would devalue his property.

What is the state of the Capehart Mill site in Norwich?

Blum said he has worked on his concept for years including contacting the owner of the long-abandoned property.

Blum said he got the owners to do some maintenance on the property. The fires, which were arson, stopped at that point. The Norwich Fire Marshal was about to indict Foot of Fifth because of the fires that kept happening.

Blum and Foot of Fifth had planned over a year ago to give the property to Blum and provide $800,000 if he indemnified them, Blum said.

Despite Blum paying attorneys $6,000 to draft a contract, which only needed the signatures, Blum claims Brown “stole” the property from him by approaching Foot of Fifth himself, after Blum brought the Shawmut Diner building to Norwich.

“I could do it for a lot less money than they’re getting from the taxpayers, and they can return some of the money from the government for another project,” he said.

The City of Norwich has long been interested in improving the Capehart Mill property, regardless of what Blum does or doesn't do, Brown said.

Why Evan Blum thinks Capehart Mill can be saved

While the City of Norwich claims the mill can’t be salvaged, Blum insists it can still be fixed. The ruins could be turned into an attraction, like Bannerman Castle in New York, Blum said.

The Uncas Leap Heritage Site in Norwich uses a stabilized ruin, so it could be possible to do the same thing for part of the Capehart Mill. However, much of the building is too delicate or dangerous to save, as new collapses were found during Coley's visit to the property last week.

Brown says Greeneville deserves an unobstructed view of the Shetucket River. Brown expects the park in Greeneville to be similar to Red McKeon Park in Occum, in that it is well-kept and appreciated by the neighborhood.


March 27, 2025

CT Construction Digest Thursday March 27, 2025

Bids for two new Norwich schools range from $102 million to $133 million

Daniel Drainville

Norwich — School Building Committee Chairman Mark Bettencourt said Tuesday the bids the city has received to build two new elementary schools are within the funding amount approved by voters.

The bids, which are available on the city's bidding portal, show that the lowest possible cost for 26 categories of work to complete the Greeneville and Stanton elementary schools, including sitework, demolition, heating, venting and cooling, is $102 million. That estimate, calculated by adding the lowest bids submitted in each of the 26 categories, does not include the cost of Downes Construction, the construction manager for the two schools, and Construction Solutions Group, the project manager for the $385 million project to build four new schools and renovate two buildings. It also does not include the cost of architectural design or woodwork, a 27th category which did not attract any bids.

The highest possible cost for the two schools, based on the initial bids, is $133.2 million. It would be unlikely for the city to choose all of the most expensive bids.

Bettencourt said some of the bids were higher than expected, while some where lower, but all fell within the various contingencies included for each of the schools. Bettencourt could not provide the contingency numbers on Tuesday.

Work to build the new Stanton and Greeneville schools is expected to begin this spring. The second two new schools, Uncas and John M. Moriarty, are in the early stages of being designed. The plan also calls for Teachers' Memorial Global Studies Middle School to be either renovated or replaced, and for the former Samuel Huntington Elementary School to be converted into a central office and adult education building.

Stanton, Uncas and Moriarty will be built on the grounds of the current schools while they continue to operate. Once the buildings are finished, the old schools will be torn down and used to create playgrounds and athletic fields. Greeneville will be built on the site of the demolished Greeneville School and adjacent land on Golden Street.

Bettencourt said Downes is currently in the process of reviewing the low bids with the contractors who submitted them, establishing a guaranteed maximum price for the work.

"Then we'll know exactly where we stand," he said, adding he hopes firm numbers will be ready by the next building committee meeting on April 15.

Bettencourt added that certain work that was more costly than expected could be rebid, as well as the architectural woodwork.

Other aspects of work that attracted bids included plumbing work, communications systems, electrical systems, fire alarms and security.

The bid period lasted nearly two months.

A bid tabulation sheet posted last Friday on the city's bidding portal shows all the contractors who submitted packages, along with their base bids in the 27 categories of work. Overall, there were more than 90 bids for the different areas of work.


Naugatuck offers incentives for businesses impacted by downtown construction

Andreas Yilma

NAUGATUCK — Borough officials are exploring an incentive plan to help downtown businesses make it through another seven months of construction work that has torn up Church Street and kept customers away.

Utility companies last March began to dig up Church Street for various utility projects including sanitary sewer, storm water, gas and underground electric and communication. Work will continue into October. 

Brady's Pub & Restaurant owner Ray Kloc said all of the construction has been poorly planned and has definitely been keeping people from coming downtown. 

"It's been horrible," Kloc said. "The whole plan, the way they're doing it, doesn't make any sense. There's absolutely no parking. They don't even make it easy for you to get from the parking lot across the street." 

Mayor N. Warren "Pete" Hess is proposing the town use its Tax Incremental Financing funds and the significant interest it has earned to help businesses which look to stay. 

"My thought would be not that we award anyone for anything that happened but we could consider setting some money — I'll say $200,000 or $300,000 — something like that from our interest to stabilize and incentivize businesses that are going to stay, remain, improve," Hess said. 

Hess said the infrastructure work resolves storm water and sanitary sewer issues that have plagued the west side of the borough for years and has created havoc in the downtown area when there is a heavy rainfall in a short period of time. 

"The biggest problem that some of those businesses are going to have is increases in rents from their landlords because the properties are all going to be more valuable and have higher rental value," Hess said. 

Public Works Director Jim Stewart said workers are now putting in the concrete underneath the new proposed brick sidewalks which will include granite curbing. Once they finish the lower end of Church Street, they will move work to in front of the Town Green and then the Maple Street Bridge that will have a new surface similar to the existing bricked crosswalks. The town was also doing some utility work before March of 2024, he added. 

"What they're seeing in front of their stores right now is a borough project but what I think they've been complaining about in the past was 100% utilities that for things that had to be done bur right now is the borough project," Hess said. 

Deputy Mayor Rocky Vitale said he thinks that the hardest part is going to be the measure of damages, almost like an insurance when businesses shut down. 

"To me, it's not nearly as much as about losses because we didn't cause any of those losses, those were caused by the utilities," Hess said. "It's more about, to me, taking an existing business and saying, you know in the next year, you're going to stay and you're going to prove to us you're going to stay." 

Buiness owner Kloc said a few businesses have already closed their stores on Church Street and relocated elsewhere including Team Image and Little Black Dress. 

"It doesn't seem like work is moving very fast and I don't think the plan was well done," he said. "Obviously it needed to happen. There was a lot of outdated utility lines that had to get replaced but it seems like they're ripping the same spot over and over again and it doesn't really seem to be a big sense of urgency on their part to get it done and they haven't really taken account, they don't seem to try to accommodate the businesses at all." 

Hess said the town will put a group of talented people together to move forward with the incentive program as town officials look to have something more formalized. 

The borough board initially approved in 2022 to select Kleinfelder Northeast, a national engineering firm, for the final design of storm water and sanitary sewer upgrades and streetscape designs for Church and Maple streets. 

The engineering firm is partnering with Richter & Cegan Inc., a landscaping, architecture and planning firm, for the streetscape portion of the project. 


CTDOT to discuss future of transit and transportation in CT. ‘So much is changing,’ officials say

Sean Krofssik

The Connecticut Department of Transportation is starting what they hope will be an annual tradition.

The CTDOT is hosting the inaugural 2025 Transportation Showcase on April 1 at the Connecticut Science Center in Hartford. The two-hour event is free to the public and starts at 8 a.m.

“It’s almost a monthly occurrence where a different group or organization will invite our commissioner or someone from our agency to serve on a panel or give a keynote address to the construction industry or the building trades,” CTDOT spokesperson Josh Morgan said. “We thought we should talk about what is happening here in Connecticut and host our own panel or our own showcase. That was the genesis of where this began.”

The discussions will be about everything involving transportation in the state and will include a panel including Marian Andoh-Clarke, the Hartford Chamber of Commerce’s director of small business development, CTDOT commissioner Garrett Eucalitto, Capital Region Council of Governments executive director Matt Hart and the Connecticut Institute for Resilience & Climate director of resilience planning John Truscinski. Arthur Guzzetti, the American Public Transportation Association’s vice president of mobility and public policy, will be the keynote speaker.

“The Transportation Showcase will bring together industry leaders, policymakers and innovators to explore how infrastructure investments will shape the future of transportation in Connecticut,” said Benjamin Limmer, CTDOT bureau chief of public transportation, said. “We look forward to exploring how enhanced public transit can drive economic growth, strengthen communities and create a more sustainable and accessible Connecticut.”

Morgan said the CTDOT is putting support behind this event to make this information available to stakeholders and the public.Read More

“It seemed like a good opportunity to launch here in 2025,” Morgan said. “We are going to be talking about what is happening right now on transit and transportation here in Connecticut, as well as some of the things the state is working on and thinking of working on.”

Some topics include how to make trains operate faster, improving travel time, investments into bus services and micro transit services to help with connections near train stations.

“Even if someone is not a daily driver or transit rider, the food that they are going to eat is going to come via our roads and rails. The goods and the clothes that they are wearing come from our roads and rails. Transportation touches everything and everyone. That will be a key focus of the showcase.”

Registration and breakfast are from 8 a.m. to 8:40 a.m. The keynote speaker and panel will follow. The panel will be moderated by WNPR’s ‘Where We Live’ host Catherine Shen and the showcase will appear on a future episode.

“We hope people will take the opportunity to come out and listen to the experts and stakeholders speak about how important mobility is for people in their day-to-day life,” Morgan said. “So much has changed and so much is changing in the area and it’s important that we have an event like this. We would love for this to be a successful event and would love to turn it into an annual celebration of transportation in Connecticut.”

Morgan said the showcase has already reached their registration goal but is speaking with the venue about increasing capacity. To register for the event, visit the showcase website.


The construction materials most at risk for tariffs

Sebastian Obando

Steel and aluminum prices have jumped sharply since the turn of the new year, and more volatility could be on the horizon.

Contractors are bracing for a new wave of tariffs set to take effect April 2, this time on certain material imported from Canada and Mexico — such as steel, aluminum and lumber. Though reports indicate the Trump administration could roll back the ultimate scope of this action, contractors say just the threat of tariffs can have an immediate impact on material costs.

That’s why that looming deadline on Canadian and Mexican imports has already sparked concern across the construction industry, particularly around reinforcing and structural steel, curtainwall systems and Canadian lumber, said Steve Stouthamer, executive vice president of project planning for Skanska USA Building.

Here, Stouthamer talks with Construction Dive about the materials most at risk, tariffs’ impact on budgets and negotiations and steps contractors can take to minimize financial exposure.

CONSTRUCTION DIVE: Which construction materials do you expect will see the greatest price volatility due to tariffs?

STEVE STOUTHAMER: The materials being impacted the most are products made from steel and aluminum.

For example, reinforcing steel used in concrete, structural steel used in the building frame, aluminum curtainwall and window wall systems used in the building envelope, piping and ductwork used in mechanical and electrical systems and many building mechanical and electrical equipment components.

Steel prices have increased 15% to 25% since the beginning of January and aluminum is also up 8% to 10% from the beginning of January. The Trump administration has indicated Canadian lumber will be included in the reciprocal tariffs which are set to take effect on April 2. Lumber has already seen a significant increase, 10% to 15% in cost, in anticipation of this tariff.

How might these tariffs affect project costs and timelines?

We are in the early stages of helping our clients understand the order of magnitude cost impacts we see based on current tariffs and those will vary based on the type of project and the material composition of those projects.

At present, we are not expecting a near-term impact on project timelines. If there is a considerable shift to onshoring manufacturing, supply chain schedules could be constrained, but this is not like the situation we experienced during the pandemic where the supply chains were impacted by global shutdowns. 

At the moment, the broader Mexico and Canada tariffs on products protected by the United States-Mexico-Canada Agreement are suspended until April 2.  Upon resumption, it is our current understanding that 25% broad tariffs on all goods from Mexico and Canada would stack on top of the all-country steel and aluminum tariffs of 25%, resulting in a 50% levy.

With the latest tariff suspensions, it is unclear if this will ultimately be the case. We will be monitoring the situation in the weeks ahead.

How do you see tariffs affecting negotiations with owners and developers?

Tariff cost impacts will put pressure on project budgets. Many of those are already challenged by the significant period of escalation experienced post-pandemic.

We are only a few weeks into the tariff executive orders so it’s too early to comment with certainty as to how contracts will be impacted or negotiated. Our approach will be to engage with our clients and discuss the most cost-effective ways to manage the tariff risks.

Do you expect issues with tariffs to be temporary or a long-term factor that construction firms need to adapt to permanently?

It’s too early to comment on this.

History would suggest that even when tariffs are removed and trade agreements are reached, costs don’t just return to previous levels.

What policy or industry efforts could help mitigate the impact of tariffs on construction firms?

Estimating professionals will need to take deeper dives into their projects to understand product volumes, sources and tariff impact to assist clients in better understanding the financial impacts of tariffs and potential alternative products and product sources.

Strategic supply chain teams, such as our own at Skanska, will need to remain closely connected to the supply chain and major fabricators of steel and aluminum products as well as other key construction materials that will be impacted by tariffs. It is essential to have this connectivity so that companies such as ours can continue to advise clients and industry partners on the best strategies to mitigate the impact of tariffs.

Projects can benefit by investing additional time into the mapping of the specified materials for the project to determine their source, if those sources are impacted by tariffs and whether alternative products and sources could mitigate financial risk.


March 26, 2025

CT Construction Digest Wednesday March 26, 2025

Harding High School sale to Bridgeport Hospital falls through

Brian Lockhart

BRIDGEPORT — The proposed sale of the shuttered Harding High School is off, and the 8-acre Central Avenue property may instead become the location of a new structure for pre-kindergarten through eighth grade students.

"It's something we really, really need to consider," Jorge Garcia, the school district's director of facilities, said Tuesday. 

Thomas Gaudett, Mayor Joe Ganim's chief administrative officer, said, "There aren’t a whole lot of places in Bridgeport to build a new school, and the Harding site happens to be kind of in a centralized location," referring to its placement where the East End, East Side and Mill Hill neighborhoods meet. "It happens to be in the city’s control already, so it's a great opportunity."

Built in 1924, Harding has been vacant since 2018, when students and staff moved from that Central Avenue spot across Boston Avenue into a state-of-the-art facility on Bond Street. In January 2023, the city's economic development department began accepting proposals from prospective buyers of the closed school, with neighbor Bridgeport Hospital emerging as the front-runner with a $3 million offer.

Months passed with no news of the status of any behind-the-scenes negotiations. Then, a few weeks ago, the school district released a facilities assessment that envisions shuttering aged Beardsley, Dunbar, Edison and Hall schools and replacing them with a new building at the former Harding site for 750 pre-kindergarteners through eighth graders.

On Tuesday, the city's economic development director, Thomas Gill, and the hospital each confirmed the latter would no longer buy the former school for an expansion. The final decision was made over this past winter.

Gill said the proposed sale price was $3 million and the city would have torn down the structure. The hospital would have remediated any contaminated soil. He said the Bridgeport City Council wanted the hospital to be on the hook for the demolition as well. 

"That was not a deal (the hospital) wanted to do," Gill said.

Bridgeport Hospital in a brief statement said, "Unfortunately, we were not able to come to an agreement by the city's requested deadline and are unable to move forward with the purchase."

Council President Aidee Nieves confirmed, "I had an issue with the sale" because the city's responsibilities before Bridgeport Hospital took over the land would have eaten up the $3 million and likely cost more.

"(It) was going to be net zero for us," she said, noting that the hospital, as a nonprofit, also does not pay local real estate taxes. "If it's for a nonprofit, I'd rather it be for a school."

"We have no problems with that," Gill said. "The only concern ... I have is the timing of when that building would be demolished." Gill said before that happens, plans for a new school would need to be submitted to and approved by the state in order to receive the necessary construction reimbursement from Connecticut. That amount is typically 80 percent.

"So it's a matter of waiting now," he concluded.

This time two years ago, the original Harding High's abandoned status was a source of friction between city and school district officials. Steve Ronin, who has a large social media following for "documenting the world's abandoned places" on video, posted footage of a half-hour visit he and his crew made to the building. The video has 136,000 YouTube views.

Ronin revealed all of the furniture, equipment and supplies left in the deteriorating building, leading to finger-pointing between the school board and council over whether the school district or the municipality was responsible for the potential waste.

A year ago, there was a fire at the property.

On Tuesday, Garcia said he broached the concept of reactivating the Harding land for educational purposes with the Ganim administration over the last few months.

"While they were in conversations with the hospital, we brought it to their attention that there aren’t any other parcels in that part of town buildable for a school," Garcia recalled. "We wanted to make sure they understood the needs in that area."  

"Harding is a perfect site," he said.

However, Board of Education Vice Chairperson Joseph Sokolovic emphasized that for now, the reuse of Harding is just a proposal in a brand new report that is still being reviewed.

"My initial thoughts? A new school is a good idea," Sokolovic said but added he is not eager to leave "three or four empty buildings" — Beardsley, Dunbar, Edison and Hall — in exchange, possibly harming those neighborhoods.

Nieves, who represents the East Side, agreed, noting traffic could also be an issue. "They have a lot to do before they can say, 'We're ready to build that school.'"

East End and Mill Hill community leaders Tuesday expressed support for repurposing the Harding acreage for education.

"I would prefer a new school there," Councilwoman Eneida Martinez said, arguing it is a good, centralized location. But she is worried about the extent of the environmental cleanup required before construction. 

Councilman Ernie Newton said ideally housing would have been built on the land.

"We need housing over there," he said.  But, Newton continued, given the state of some of Bridgeport's existing school facilities, "it just makes good sense" to redevelop Harding for a similar use. 

"The hospital plan we saw we thought was a good plan," said Ralph Ford, a prominent Democratic leader on the East End. "If they can't work it out, providing better educational opportunities for the city, for students in Bridgeport, is just as good. Might even be better. They'll be able to close some of those outdated schools."

Nick Roussas runs the Mill Hill Neighborhood Revitalization Zone, one of a group of NRZs around the city established to weigh in on economic developments in their respective sections of Bridgeport. He lamented that Harding is an eyesore. 

“One way or another, we want something to get built on there," Roussas said. "Anything that gets fixed up in our neighborhood is better than nothing. ... Whether the hospital takes it or the city and develops it into a school or apartments, something's got to go there."


Destroyed in catastrophic CT August floods, Oxford's seventh and final bridge reopens

Steve Bigham

OXFORD — Town officials hailed the reopening of the Park Road bridge Tuesday morning, the completion of the seventh and final bridge replacement project here following the catastrophic flooding that hit the area more than seven months ago.

Park Road has been closed since the historic Aug. 18 flooding event when torrential rains wreaked havoc on homes, roads, bridges, and culverts.
Oxford was among the hardest hit towns in the area. Two of its residents lost their lives after being swept away along Route 67 when their cars became trapped in water that rose as much as six feet above the banks of nearby Little River.

Oxford First Selectman George Temple gathered with dozens of town officials for a ribbon-cutting ceremony yesterday while standing at the site of the new bridge, a celebration of both Park Road’s reopening and the overall resilience of the town.

“This is the culmination of a lot of blood sweat and tears for the people of Oxford. It goes back to the devastation of that flood, and this is the final stage of the recovery,” Temple said. “I think the town is going to be able to withstand the storm. I guess that’s a metaphor for the real storm that caused all this damage.”

Temple said he is confident the new bridge has been built to effectively survive a similar flood in the future. He said the previous bridge gave way during the flooding, and then later, in December, a Revolutionary War-era stone archway — that was beneath the bridge — also collapsed.

Temple said the bridge replacement by Brennan Construction took less than six months to complete, noting that similar projects in the past, not connected to the storm, often took two years to complete.

Oxford town officials say the total cost for reconstruction of local roads will likely come in around $8 million, of which the town is hoping to receive about 70 percent reimbursement from the federal government’s FEMA program.

Southbury still recovering from the damage 

Meanwhile, in neighboring Southbury, which was also heavily impacted by the flooding, Old Field Road is the only road yet to be reopened.

First Selectman Jeffrey Manville said the bridge there was one of dozens in town destroyed by the flooding. However, its reconstruction is taking longer to complete because it had already been earmarked for replacement and was in the design phase prior to the flooding, meaning it is
not eligible for FEMA reimbursement.

Southbury town officials say they are moving ahead with the project just as they would have had there not been any flooding. The roadway is expected to reopen in the spring.

Southbury had an estimated damage amount of about $10 million, slightly higher than Oxford, in part, because its losses included more local roads, while, much of Oxford’s damage centered along Route 67, and those repairs fell under the auspices of the Connecticut Department of Transportation.

Southbury’s damage also included the public library along Poverty Road where the basement, and all of the building’s mechanicals, were destroyed by the raging floodwaters.

Manville recently announced that the library is scheduled to reopen by November, meaning it will have ended up being closed for some 15 months.
Manville said he has been disappointed that Southbury is not being provided the level of funds to “built back better,” noting that most of the roads have simply built back the way they were, no less susceptible to future floods.

Manville said he has also been disappointed that Southbury has not received additional funding for the reconstruction of the library.
“The state and federal government have come through with nothing and we were told that we were going to get help,” Manville said. “The library in Hartford received $1 million for water damage, but we have received nothing.”

The town recently established a temporary library in the lobby of the Heritage Hotel.

Southbury is also looking to replace the three tennis courts at Community House Park, which were all destroyed in the floods.


NYC developer buys Windsor land for $5.85M to construct industrial building

Alexander Soule

A New York City developer paid $5.85 million for a parcel of land in Windsor near Bradley International Airport, with plans to cobble together an industrial building at the site using building "blocks" made elsewhere to reduce the cost and construction time.

With construction to take place at 36 Hazelwood Road, the PNK Group industrial building would total 218,000 square feet of space. That stretch of Windsor is home to multiple warehouses and production facilities, including for Dollar Tree, Little Caesars, Tire Rack, Walgreens and PepsiCo.

The Hartford area had 250,000 square feet of industrial space under construction at the close of 2024, according to the latest quarterly report by CBRE, a single project in Windsor Locks by the New Jersey-based developer Silverman Group. The region's industrial property vacancy rate is 5.5% and lease rates average $7.69 a square foot.

PNK Group uses factories in Pennsylvania and Georgia to build "large-unit block" structure components, in its words, which it then transports to sites for assembly into warehouses and other industrial buildings. The company's projects include a 1.1 million square-foot project in Georgia where mattress maker Purple Innovations is a tenant, with PNK Group selling the facility to investment giant KKR in 2021 for a reported $103 million.

The company did not state immediately whether it has any commitments from distributors or manufacturers to lease space at the Windsor site. A PNK Group partner could not be reached immediately Tuesday for further information on the plans.

PNK Group completed the 22-acre land purchase on March 6 through a limited liability company called PNK CT1 LLC. The property had been owned previously by UW Realty VII, a limited liability company registered to real estate investors Bradford Wainman and Robert Urso of Glastonbury, who paid $1.15 million for the land in 2022.


US infrastructure improved with Biden-era spending but there's a long way to go

TAMMY WEBBER and MICHAEL PHILLIS

A once-every-four-years report card on the upkeep of America's infrastructure gave it a “C” grade on Tuesday, up slightly from previous reports, largely due to investments made during former President Joe Biden's administration.

The report from the American Society of Civil Engineers, which examined everything from roads and dams to drinking water and railroads, warns that federal funding must be sustained or increased to avoid further deterioration and escalating costs.

“We have seen the investments start to pay off, but we still have a lot of work to do out there,” said Darren Olson, chair of this year’s report. He said decrepit infrastructure – from poor roads that damage cars to delayed flights to power outages that spoil groceries — hurts people and the economy.

“By investing in our infrastructure, we’re making our economy more efficient, we’re making it stronger (and) we’re making ourselves globally more competitive,” he said.

It’s especially critical that infrastructure can handle more extreme weather due to climate change, said Olson, noting hurricanes that devastated the East Coast and parts of Appalachia last year. The U.S. saw 27 weather disasters last year that cost at least $1 billion, second-most since 1980.

The 2021 Infrastructure Investment and Jobs Act provided $550 billion in new infrastructure investments, but is set to expire in 2026. Another $30 billion came from the 2022 Inflation Reduction Act, including for projects focused on clean energy and climate change, the engineering group said.

President Donald Trump's administration has targeted some of Biden’s green policies. Public parks improved to a C-minus from a D-plus, for example, thanks in part to significant investments over several years. Recently, however, the Trump administration moved to slash National Park Service staffing.

In 2021, the U.S. earned a C-minus overall. The investments made since then are just a fraction of the $9.1 trillion that the civil engineers group estimates is needed to bring all of the nation’s current infrastructure into a state of good repair.

Even if current federal infrastructure funding were maintained, there still would be a $3.7 trillion gap over a decade, according to the report.

The bill to upgrade and maintain the nation’s roughly 50,000 water utilities, for example, is $625 billion over the next two decades, according to the federal government. The grade for drinking water was C-minus, unchanged from four years ago.

Many communities already struggling to maintain old, outdated drinking water systems also face new requirements to replace lead service line s and reduce per- and polyfluoroalkyl substances, collectively known as PFAS.

The bipartisan infrastructure bill helped complete or start “a lot of really important projects,” said Scott Berry, director of policy and governmental affairs at the US Water Alliance. “But the gap has widened so much over the last couple of decades that a lot, lot more investment is going to be needed.”

The bill also provided billions to help the U.S. Army Corps of Engineers upgrade inland waterways, which move roughly $150 billion in commerce every year, improving the grade from a D-plus to a C-minus.

Barges on the Mississippi River, for example, carry enormous amounts of coal, soybeans, corn and other raw materials to international markets. But critical infrastructure like locks and dams — many built more than a half-century ago and requiring regular maintenance and repair — is often invisible to the public, making it easy to neglect, said Mike Steenhoek, executive director of the Soy Transportation Coalition.

And when big projects are funded, it too often comes in stages, he said. That forces projects to pause until more money is appropriated, driving up costs for materials and labor.

“If we really want to make the taxpayer dollars stretch further, you have got to be able to bring a greater degree of predictability and reliability in how you fund these projects,” he said.

The report's focus on engineering and money misses the importance of adopting policies that could improve how people use and pay for infrastructure, according to Clifford Winston, a microeconomist in the Brookings Institution’s economic studies program.

“You fail to make the most efficient use of what you have,” said Winston. For example, he noted that congestion pricing like that recently adopted by New York City — charging people to drive in crowded areas — places the burden on frequent users and can pressure people to drive less, reducing the need for new bridges, tunnels and repairs.

Roads remain in chronically poor shape, receiving a D-plus compared to a D in the last report, despite $591 billion in investments since 2021.

Two categories, rail and energy, received lower grades. Disasters like the derailment of a train carrying dangerous chemicals in East Palestine, Ohio, in 2023 lowered rail’s previous B mark to a B-minus.

The energy sector, stressed by surging demand from data centers and electric vehicles, got a D-plus, down from C-minus.

Engineers say problems in many sectors have festered for so long that the nation must figure out how to address the shortcomings now or pay for them when systems fail.

On Wednesday, a delegation of engineers will visit Washington to talk to lawmakers about the funding impacts and “the importance of continuing that investment,” said Olson, who said the needs are a bipartisan issue.

“When we talk about it in ways of how better infrastructure saves the American family money, how better infrastructure supports economic growth, we’re really confident that ... there is strong support,” he said.


March 24, 2025

CT Construction Digest Monday March 24. 2025

Connecticut lawmaker wants to make 'pipeline' for construction workers

Ken Dixon

HARTFORD — Legislation aimed at helping non-college-bound students and workers train for Connecticut's construction trades won overwhelming approval last week in the legislative Labor Committee to create a group of professionals to look into existing entry-level programs and increase access to various apprenticeship programs.

The bill, which next heads to the House of Representatives, is aimed at increasing awareness and creating additional financial incentives and tax incentives for employers, said Rep. Tim Ackert, R-Coventry, an electrical contractor who is the chief proponent of the bill, backed up by House GOP leadership.

"These are good-paying jobs, but you need to get on the first rung," Ackert said in a recent interview. "Home builders are struggling to find people who can wire and plumb houses."

He would like an eventual program to mirror the state's tuition-free Eastern Connecticut Manufacturing Pipeline, in which students at community colleges enrolled in two-month programs to learn skills that can be transferred to jobs at Electric Boat in Groton, including welding, ship fitting and other skills. Manufacturers can receive $7,500 tax credits for hiring apprentices.

Ackert said he developed the proposal after speaking with home builders and remodel contractors who complained about the lack of trained help in trades such as heating, ventilation and air conditioning. A group of professionals has met occasionally over the last year. Ackert said he has been in communication with the state Office of Workforce Strategy on the issue and would like to see similar tax benefits for businesses. "We should say that you're investing in them and here's a credit toward your business taxes. "Energy efficiencies, infrastructure upgrades, workforce housing, and any of these construction opportunities are important," Ackert said.

While Ackert's original proposed bill would have created a new construction pipeline emulating the manufacturing program, the legislative process so far has turned it into a study. As currently written, the study group would examine opportunities in existing public high school curriculums and include pre-apprenticeship programs and avenues to higher education including college degrees in construction management.

The group would make recommendations to the General Assembly and would include representatives of statewide trade associations including electricians, HVAC technicians and plumbers, statewide businesses, residential construction, high school and higher education. The group would have a December 31 deadline to report findings to the Labor and Public Employees Committee.

There are a variety of apprentice programs available through the state Department of Labor that registers young workers who can earn while they are being trained. Some of the programs can take one to four years for young workers to complete. But workers can earn portable credentials; certificates of completion; can confer "master of their craft;" and make them eligible to take appropriate occupational licensing examinations.

Some of the state's unionized worker forces, such as the International Brotherhood of Electrical Workers Local 488 of Western Connecticut has a free apprenticeship program.

State Sen. Julie Kushner, D-Danbury, said the working group legislation needs some redrafting before debate in the House, then Senate. "We certainly appreciate that we have a very vibrant, existing work force in the construction trades and we want to make sure that all voices are heard on the construction workforce pipeline," she said during a brief committee discussion. 


Bridgeport should build new schools before closing old ones, acting superintendent says

Richard Chumney

BRIDGEPORT — Acting Superintendent of Schools Royce Avery believes the school system must first secure the funding and construct new school buildings before it moves forward with a proposal to shutter several old facilities.

A recently completed study found the district’s aging buildings will need $702.5 million in upgrades over the next decade and recommends closing seven aging schools to save money on costly repairs. 

But Avery said during a community forum Tuesday that the schools should stay open until new buildings have been erected to replace them — a process he noted could take three to four years to complete. 

“We can’t close buildings until we get new facilities,” Avery said. “So until that happens we’re not even going to talk about school closures because we have nowhere to put the kids.” 

The spectre of school closures was raised earlier this month when consultants hired to study the conditions of each of the district’s 37 buildings delivered a long-awaited report recommending the city shutter seven buildings, construct four new ones and perform major renovations on eight others. 

The report notes many of the schools were originally built more than a century ago and that replacing badly rundown facilities with brand new ones could help the cash-strapped district save millions of dollars in maintenance costs.  
 
Avery’s comments were made in part to assure parents that the district does not plan to revive a since-abandoned proposal by former Superintendent Carmela Levy-David to quickly close several neighborhood elementary schools.  

The controversial plan sparked backlash from scores of parents, students and teachers who protested the decision and helped contribute to a breakdown in the relationship between Levy-David and the school board that ultimately resulted in her departure last fall. 

In contrast to last year, Avery said the school system will use the new recommendations to develop a 10-year master plan for the district’s facilities and hopes to incorporate the public’s feedback into the yet-to-be-finalized document. 

The district is holding three public forums this spring about the future of the facilities. The first will take place on March 31 at Harding High School, while the second will be on April 1 at Central High School and the third will be on April 2 at Bassick High School. 

“We understand that neighborhood schools are near and dear to a lot of folks,” Avery said. “And we don’t want to just tear that apart. We want to make sure that we have a plan for new facilities before we even do anything with any other facility.”  

Avery said the district is working to secure funding from the state for future construction projects, but noted it is not yet clear how much money the school system can obtain and when the funding could become available. 

Tuesday’s discussion was held at the Charles F. Greene Homes on Highland Avenue as part of the first in a series of community forums scheduled at a handful of public housing complexes across the city. 

Avery and other district officials spent about an hour answering questions from the residents about the state of the school system, including a looming budget deficit in the upcoming fiscal year and the proposal to close some schools. 

“I need to be able to connect with the community,” Avery said. “One of the most important pieces is making sure the community really understands everything that is happening. So being able to have these forums gives me the opportunity to bring clarity.”

Flora Vazquez, the mother of a third grader and a fifth grader, was among the handful of parents who attended the forum. She said she appreciated that Avery took time to speak with her about security measures inside the schools. 

“I think these meetings are good because we can meet the staff and learn what they’re planning,” Vazquez said. “It's good to know that they are trying to improve the schools and want to listen to the community.”

The district plans to hold two additional forums at public housing complexes. The second will take place on April 15 at P.T. Barnum Housing on Bostwick Avenue and the third will be on May 9 at Beardsley Terrace Housing on Trumbull Avenue. 

Jillian Baldwin, the chief executive officer for the city’s housing authority, praised Avery for organizing the forums. She noted the authority serves more than 5,000 residents and about 12,000 voucher recipients, including hundreds of parents and students. 

“I think it's important to meet people at home where they’re at, especially if you have critical information that the community needs to hear,” she said. “Transportation is often an issue in our communities, and sometimes parents work two jobs and their availability window is very short.”


Wallingford approves Choate Rosemary Hall building pedestrian bridge over Christian Street

Christian Metzger

WALLINGFORD — An elevated pedestrian bridge will now be able to connect Choate Rosemary Hall’s north and south campus along Christian Street. 

The proposal was brought before the town council last year when the school sought an air easement to construct the 17-foot-tall wooden bridge, which is planned to be located just south of Rosemary Lane. It was recently approved by the Planning and Zoning Commission.

It will have a crosswalk and ramp so it's wheelchair accessible and will connect parking lots primarily used by students and families with the sports facilities across the road. 

"We do not have a construction timeline for the bridge yet; we need to finalize the design before we can estimate when it might be installed and open for use," said Allison Cady, the school's communication director. "However, we are excited and eager to move forward with the project."

The bridge was proposed as a means of preventing traffic backups along Christian Street and potential hazards to students and visitors trying to cross when cars have the tendency to speed there.

It will take the form of an elevated wooden boardwalk that extends over the road, with a crosswalk on the opposite end across Rosemary Lane and a ramp to make it wheelchair accessible. 

“What this linear connection, the pedestrian access, seeks to do is provide a connection for the formalized parking here in Colony Hall and also other uses during the regular school day,” said Darin Overton, project manager with SLR consulting.

The designers said the bridge would be a largely unobtrusive feature of the surrounding landscape, with trees hiding portions of the 66-foot span on either side of the road. 

Officials said the project would have limited environmental impact due to the narrow footprint and the porous asphalt that will be used for the overflow parking area. While twice as expensive as normal asphalt, it would allow the water to seep into the soil directly beneath the paved area and wouldn’t require a catch basin, which would likely come at a greater expense for the school to maintain in the long term. 

Officials said the landscaping and railings would discourage unsafe crossings.

“The way we’re designing this is so that people use it," said Patrick Durbin, chief financial officer at Choate. "We have no interest in building a bridge that won’t get used or that people will find a way to bypass." 

The bridge had been a cause of discussion between Chaote and the town, with some town council members wondering if the school should provide a greater fee to the town for the requested air easement to build the bridge as compensation for properties that have been taken off the tax rolls in recent years. Others felt it was located too far away from the other main crossings or central campus facilities to be of use. 

A majority of the members did agree the project was worthwhile however, if just as another means to ensure pedestrian safety at a dangerous crossing that’s often busy during the school’s sporting events in the spring. 

Choate officials also said they were considering adding a road sign with the speed of approaching vehicles so they slow down in proximity to the bridge. While members of the commission also suggested putting in a speed bump, Choate representatives said they’d collaborate with the police department to assess available options to continue to moderate traffic safety. 


Torrington company lands contract for Railroad Square Revitalization project

Sloan Brewster

TORRINGTON — The approximately $4.2 million Railroad Square Revitalization project has been awarded to Yield Industries.

Officials are now awaiting approval by the Connecticut Department of Economic and Community Development, said City Engineer and Deputy Public Works Director Paul Kundzins.

“Construction will begin as soon as we can mobilize,” he said. “The project is required to be completed by the end of this calendar year, so we’re going to be done. Busy, busy summer.”

At $4.1 million with $207,355 for contingencies and quantity fluctuations, the Torrington-based Yield Industries' bid was the lowest, Kundzins said.

“The bids came in very favorably, actually under the engineer’s estimate. Bids came in 6% under and were even under the DECD funding,” Kundzins told the City Council. “So we were very pleased with the results.”

The project will be funded by a DECD Community Challenge Grant, the City of Torrington Pavement Management Program Bond Fund and the state Department of Transportation Town Aid Road program.

The overall project includes the replacement of the railroad platform and construction of a canopy at Railroad Square, the $632,967 contract for which was awarded to Millennium Builders Inc. in January.

The newly awarded portion constitutes the remainder of the effort, which encompasses facelifts on Water Street from Prospect Street to the railroad tracks, John Street from Water Street to Mason Street, Mason Street from Prospect Street to Church Street and Church from Mason Street to Migeon Avenue.

Greenway trail to expand to Chrismas Village

The effort will include the extension of the Sue Grossman Greenway from Water Street to 160 Church St., along railway tracks beside Christmas Village to a new parking lot behind Christmas Village, Kundzins said. The greenway will just about link to the greenway at Riverview Parking Lot, behind the library with only a small gap along a portion of Prospect Street.

John Street will also get road, sidewalk, and crossing upgrades.

A 10-foot-wide trail will be added on John and Mason streets and a pedestrian promenade will be installed at 136 Water St. resulting in a public walkway between the train station, greenway and green spaces with benches, trees and landscaping.

When passengers get off the train from Thomaston, they will be able to use the walkway to link to John and Mason Streets, Kundzins said.

Project will include expanded parking 

The effort will include some road reconstruction, the installation of sidewalks, lighting and drainage fixes. John Street will be converted to a one-way street with new granite curbing, sidewalks and lighting. Mason and Church Streets will also be partially reconstructed and get new curbing.

The project also includes a new parking lot behind Christmas Village with 70 parking spaces. The new parking lot will be used by teachers at Vogel-Wetmore School, who currently park in a lot on Mason Street, next to the Northwest Connecticut YMCA. The new lot will free up the one on Mason Street for public use, Kindzins said.

Mayor Elinor C. Carbone, at the City Council meeting, noted that she is always hearing about the need for more parking downtown, including from management at Torrington Savings Bank, who bemoan the lack of spaces whenever she meets with them.

“There is such a high demand for parking spaces,” she said.

She noted that if the Yankee Pedlar Inn is redeveloped, it too will need parking.

The project also includes a small pocket park next to Christmas Village, with areas for food trucks, at the intersection of Church and Mason Streets.

Construction of the train platform and canopy should be starting soon, Kundzins said.


State cites downtown Bridgeport renovation project for labor violations

Brian Lockhart

BRIDGEPORT — State officials recently temporarily halted renovations to the former American Telephone and Telegraph (AT&T) building downtown over labor law violations.

Juliet Manalan, a labor department spokesperson, confirmed that agency's wage and workplace standards division issued stop work orders to a trio of businesses involved in the project for misclassifying workers and not having workers' compensation insurance: Odysseus Multi-tech and Pillar Management, both of New York, and a J. Gonzalez, of Connecticut, which had the insurance but not for the correct amount of employees or type of work. 

Odysseus was also cited for having unlicensed personnel performing plumbing. 

According to the U.S. Department of Labor's website, "Misclassification occurs when an employer treats a worker who is an employee under the Fair Labor Standards Act as an independent contractor. Misclassifying employees as independent contractors is a serious problem because misclassified employees may not receive the minimum wage and overtime pay to which they are entitled ... or other benefits and protections to which they are entitled under the law."

The state's stop work orders were lifted for J. Gonzalez and Pillar in early March after they took corrective actions, Manalan said, while Odysseus' remains in place. She also said fines were issued but could not immediately provide those specifics, along with more details about the respective businesses like addresses, as of press time Friday.

Of the three, only Pillar, run by Kiumarz Geula, could be reached for comment. Pillar purchased the old AT&T site at 430 John St. and the rear parking lot fronting Fairfield Avenue in December 2021. Geula had proposed 77 artists lofts and two restaurants for the former address, and 60 housing units for the Fairfield Avenue property, and received a pair of state loans totaling $1.98 million to help fund the necessary environmental cleanup.

"Approximately two weeks ago, state agencies visited the site and issued a stop-work order based on their findings," Kiumarz acknowledged Friday in a statement. "Since then, we have worked closely with our contractors to address most of their concerns and have adjusted our site to meet their expectations. Our goal remains to collaborate with all agencies and continue developing innovative and dynamic spaces in Bridgeport."

Geula is also the new owner of three other significant downtown properties — the former State Street location of the Connecticut Post, the Bijou Theater on Fairfield Avenue and the Downtown Cabaret Theater on Golden Hill Street. Geula also owns an East End brewery that opened last summer at 800 Union Ave.

A pair of construction unions — the Fairfield County Building Trades and Carpenter’s Local 326 — scheduled a 10 a.m. rally Saturday at 430 John St. to protest the violations. Their announcement noted this is the second high profile redevelopment in Bridgeport where stop work orders were issued over workers' compensation and misclassification issues.

The first occurred earlier in the winter at the construction site for new luxury apartments on the Steelpointe harbor front project off of Interstate 95. 

Miguel Fuentes, a representative with the Carpenter's, said such issues are proving to be "an epidemic in the City of Bridgeport, in the state of Connectuct and throughout the United States."

Dan McInerney, president of the Fairfield County Building Trades, claimed more local contractors need to be employed on these major redevelopments.

“As someone born and raised in Bridgeport who graduated from Bullard-Havens (Technical High School), I want more residents to get an opportunity to rebuild Bridgeport and build a career the way I did,” McInerney said.


Vote to Restore Bridge Traffic Heads to Stamford Reps

Angela Carella

STAMFORD – A historic iron bridge has taken people over Mill River since 1888, but it is proving unable to cross a deeper divide.

It’s the gap between the struggling West Side and the thriving downtown; between longtime residents and newcomers; between the haves and the have-nots.

The breach was on display last week, when the Board of Representatives’ Operations Committee held a public hearing before voting on what to do with the intricate 125-foot West Main Street bridge, one of the few of its kind left in the country.

Through its stages of deterioration, the bridge has been closed to cars, shored up as a pedestrian crossing, replaced with a “temporary” prefabricated walkbridge, and now abandoned in a sorry state.

West Side residents and their supporters say no one cared about the West Main Street bridge before the then-deteriorating downtown was turned around. Luxury apartment high-rises went up, and city officials began spending millions of dollars to reroute the stagnant Mill River and rebuild what had been a neglected, crime-ridden Mill River Park.

A recent engineering study resulted in five options for the bridge, which connects the West Side to the park. But the choice appears to have come down to two. 

One is to restore the historic elements of the bridge and rebuild it to support two lanes of car traffic. The prefabricated walkbridge would be removed. Estimated cost: $6.7 million.

The other is to take down the iron bridge and remove the trusses, installing them as a historic artifact in the park. The prefabricated walkbridge would remain. Estimated cost: $1.2 million.

A rare safe crossing

Downtown resident Zach Oberholtzer explained during the hearing why he favors a pedestrian-only bridge.

Reopening it to car traffic “takes one of the few car-free places in the city and it plows cars through it,” Oberholtzer said, asking city representatives to consider downtown’s Bedford Street, which is lined with bars and restaurants that set up tables on the sidewalks.

“It’s very nice to sit on Bedford Street in the summer, except then you have these noisy, polluting cars driving by while you are trying to have a nice night out eating dinner,” Oberholtzer said. “The same principles apply to the West Main Street bridge. … It’s one of the few safe places for crossing Mill River where you don’t have to interact with cars.” 

Angelo Bochanis, another downtown resident, said he walks the area every day and doesn’t understand why representatives would consider allowing traffic on a bridge that is near a park, a playground, and an apartment house for seniors.

“The roads were built to accommodate as many people as possible, driving as fast as possible,” Bochanis said. “Drivers are careless.”

He likes the West Main Street bridge because “it’s quiet and safe and pleasant … I don’t have to worry if a car is coming; I don’t have to worry about waiting for the light or a signal,” Bochanis said. “People don’t want roads running through their parks.”

Chris Dawson of North Stamford, a volunteer with People Friendly Stamford, which advocates for bicyclists and pedestrians, said the same.

“I’ve run around the West Side for exercise  … I helped paint street murals outside the Yerwood Center … as part of People Friendly Stamford, I promote walkable neighborhoods,” Dawson said. “West Side residents tell me they are fed up with bad driver behavior. They want drivers to slow down and actually stop at stop lights and stop signs.”

Most West Side residents “won’t speak at a public hearing … they are busy with their lives,” Dawson said. “I’m sharing what they’ve told me so you have a more complete picture of resident perspectives.”

Some West Side residents did call into the meeting, held over Zoom. 

Let the West Side decide

Lifelong West Sider Cynthia Bowser said “let West Side residents speak for the West Side.” The neighborhood has long endured the traffic and pollution resulting from Stamford’s growth, Bowser said.

“We on the West Side have paid enough for the good intentions that have not had equitable outcomes,” Bowser said. “Those with high incomes control the quality of life,” but those decisions should be “for the people who live on the West Side, not for new people coming in and trying to impose their will on those of us who live here.” 

The bridge needs to be reopened to cars because “we have excessive traffic … we can’t get up and down West Main Street, and more apartments are being built,” Bowser said. “Let’s begin to make Stamford an equitable city, listening to low- to moderate-income residents as well as those with high incomes. Stamford is a wonderful place to live, but it is more equitable for you if you have more money.”

West Sider Renee Brown said people who live in North Stamford, one of the city’s wealthier neighborhoods, and other areas made inaccurate statements during the hearing.

“They are saying our kids use the bridge. That’s not true. The kids do not walk that way,” Brown said. “It always seems like it’s not about what we want on the West Side, it’s about the ones who live in North Stamford. They come down here when they want to fight for what they want to fight for. The mayor preaches diversity – then let us speak about the bridge. We live it every day. The people in North Stamford … want to fight for what they see as a pretty project. It’s not about that. It seems like we’re nobody. It’s just, ‘OK, I got money, this is the way it’s going to be.’”

West Sider Debbie Joyner said people from outside the neighborhood made it sound like a restored bridge would draw heavy traffic.

“There was never major traffic. It was a very nice shortcut for the neighborhood,” Joyner said. “And I jog in Mill River Park, but I only jog on the bridge to get home. People don’t jog on the bridge. They jog in the park.” 

She asked people from outside the neighborhood to not “use your resources to disagree with us … let us have something on the West Side that we can decide to have, not … have it decided for us,” Joyner said.

‘The real issue is gentrification’

After the public hearing was closed, city representatives discussed the bridge options. Like the residents who called in, they were divided.

City Rep. Sean Boeger said groups such as People Friendly Stamford and the Mill River Park Collaborative undertook a letter-writing campaign urging representatives to vote against restoring car traffic to the bridge.

“They are the newer, more connected, more organized, more wealthy voices,” Boeger said, but “marginalized voices don’t have an organized platform.” 

Boeger, a police officer, said fears of cars speeding on the West Main Street bridge are unfounded.

“I don’t understand how people could come here and paint that picture … when traffic, sometimes in excess of 50 miles an hour, is flying on Tresser Boulevard” 50 feet from the park, Boeger said.

He supports the park renovations – that’s not the problem, Boeger said.

“Turning Mill River into a lush park … is a wonderful idea. It’s a thousand times better than what it used to be,” he said. “The real issue is gentrification” – the process by which a low-income area changes as wealthier people move in and displace the original residents.

Boeger said he cannot back those who do not live on the West Side and are advocating for a walkbridge.

“I would not expect the West Side to march into my Springdale neighborhood and tell us what to do,” he said. “I support a vehicle bridge for the residents of the West Side.”

City Rep. Chanta Graham said she grew up on the West Side and has family there. She sees seniors leave the West Side with their walkers on the dangerous trek across Washington Boulevard and its speeding traffic, on their way to Atlantic Street to catch a bus. 

“I take offense that people are worried that they can’t jog without traffic, when the people of the West Side have to struggle to get to the doctor’s office,” Graham said. 

To make things worse, seniors can’t sit at the bus stop because the downtown business district removed the benches to prevent homeless people from gathering on them, Graham said.

“The people of the West Side are definitely being disenfranchised,” she said. “Closing the bridge created a dead end where crime has increased, especially drug activity. We are being beyond selfish in not giving West Side residents what they need.” 

Crime in the dead end

City Rep. Vanessa Williams said she “fell in love with Stamford” after her job had her commuting to First Stamford Place from Litchfield County. She purchased a home on the West Side and raised her family there, Williams said.

“I am not marginalized, but I have witnessed the challenges of my neighbors,” Williams said.

She was dismayed by comments during the hearing that many West Side residents don’t own cars. She owns a car and so do all of her neighbors, Williams said.

“The volume of residents has increased … now 110 luxury units are going up … and things will get more congested,” she said. “Opening the bridge won’t create speed-based risks – that’s Tresser Boulevard.”

She refuted comments from those who don’t live on the West Side that the spot near the prefabricated walkbridge is safe. 

“I do not feel safe … because of the dead-end area – there’s garbage, broken glass, little Baggies, condoms. I have seen narcotics exchanges at 7:45 in the morning on my way to work,” Williams said. “It spills over into the park.”

Allowing cars back on the bridge would “alleviate the increased congestion and create healthier thoroughfares connecting the West Side to downtown,” Williams said.

The two ‘no’ votes

City Rep. Don Mays of North Stamford reminded fellow representatives that the mayor’s office did a survey of West Side residents a few years ago, asking whether they wanted car traffic restored to the bridge.

“There was no definitive answer, kind of like what we heard tonight. It was split,” said Mays, who was voting to close the old iron bridge. If that happens, “what can be done to enhance the quality of life in that area?” he asked.

He didn’t appear to agree with what West Side residents said about the bridge drawing limited traffic.

“I’m about child safety; that was my career,” Mays said. “If we intersect a park with a busy road, it increases risk.” 

City Rep. Ashley Ley, also from North Stamford, said that, as an urban planner, she thinks a pedestrian-only bridge would be safer, especially since restoring a car bridge would create a five-way intersection at Main, West Main, Greenwood Hill, Smith and Mill River streets.

Recognizing the “criminal element” that resulted when the bridge was closed, forming a dead end, Ley said “creating eyes on the street makes a neighborhood safer,” but “that can be done in ways other than adding vehicles” on the bridge. 

“I support … reusing the historic bridge as an art element in the park … and improving the dead end,” Ley said.

At the end of the discussion, six members of the Operations Committee supported restoring the iron bridge and opening it to two-way car traffic. Mays and Ley were opposed. 

The recommendation of the majority goes before the full Board of Representatives for a vote on April 7.


Study: Costs to prep Hartford’s 80-acre former trash-burning site for residential redevelopment range up to $333.87M

Michael Puffer

An 80-acre site in Hartford’s South Meadows received garbage from most of Connecticut for decades, processing it in a massive facility that burned trash for energy.

The quasi-public Materials Innovation and Recycling Authority shut the faltering plant down in 2022, and local officials have been pushing to prep the large site in Hartford’s industrial South Meadows neighborhood for redevelopment.

That preparation will take years and cost anywhere from $27.87 million to $333.87 million, depending on how many of the existing buildings are demolished, and what sort of future development is pursued, according to a recently completed study.

“That study is basically setting the groundwork for a starting point for a future development of the site,” said Mark T. Daley, president and chief financial officer of the MIRA Dissolution Authority. “This is everything under those various scenarios that would need to be done to turn the site over to a future developer and put the site into a future use, whether it’s commercial or residential or industrial.” 

Those cost estimates are also based on a 2026 start date, and rise sharply with delay. 

The dissolution authority was formed by state lawmakers in 2023 to oversee the winding down of MIRA operations and the disposition of its various transfer stations and, most dauntingly, the South Meadows site.

The dissolution authority has sold two recycling properties in Hartford and a transfer station in Watertown to companies tied to USA Waste & Recycling. A sale of an Ellington property is in the works.

The dissolution authority also hired Rocky Hill engineering and environmental company Weston & Sampson to outline the likely steps and costs for getting the South Meadows property ready for various redevelopment scenarios. 

With that study, dated March 10, in hand, the authority is nearly ready for its own dissolution, which is expected to be completed by June 30.

After that, management of remaining MIRA properties will be in the hands of Gov. Ned Lamont’s administration and the state Department of Administrative Services.

Lamont administration officials have asked staff at the Capital Region Development Authority to consider if the agency can organize the South Meadows site’s redevelopment preparations, CRDA Executive Director Michael Freimuth said Thursday.

CRDA – a quasi-governmental agency responsible for economic development efforts in Greater Hartford – is a logical choice for the job, Freimuth said. But his 13-staff agency already has a hefty workload and would need additional manpower and money to take on the South Meadows site, he said.

“We have been asked to assess whether CRDA can play a role,” Freimuth said. “It would be a major undertaking of our staff and resources. Hopefully, we would get more resources if that comes our way.”

Hartford Mayor Arunan Arulampalam said his administration is focused on getting the South Meadows site back into productive use to its maximum potential, whether that means new housing opportunities or industrial development that brings jobs. Arulampalam said he’s not set on any particular use case.

“The city is 18.5 square miles, half of it untaxable, so it is really important to maximize every bit of land that we have,” Arulampalam said.

Long industrial use, hefty cleanup

The MIRA site in the South Meadows has seen more than a century of heavy industrial use. Even with two decades of cleanup to present-day industrial standards under MIRA and its predecessor agency, preparing it for reuse isn’t a cheap or short-term prospect. 

The Hartford Electric Light Co. completed a coal-fired power plant on the site in 1921. The plant transitioned to petroleum fuels by the 1940s. The trash-to-energy plant began operations in the 1980s.

Today, the 80-acre site along the Connecticut River, just north of Brainard Airport, hosts the repeatedly upgraded power plant and a sprawling waste-processing facility. The waste-processing facility includes a 202,000-square-foot main building, 38,000-square-foot storage building and a handful of smaller ancillary buildings and structures.

Getting the site ready for redevelopment would vary in cost and time depending on future use. Containing or cleaning pollution to accommodate the state’s residential standards, for instance, would be far more costly than getting it ready for continued industrial use.

Daley expects the MIRA Dissolution Authority to wrap up with about $50 million in reserves, which he notes would be enough to cover the cost of preparing the site for continued industrial or commercial use.

The Weston & Sampson study considered several redevelopment scenarios including:

Industrial or commercial use with demolition of the “power block facility” alone. This scenario is estimated to take three years and cost $47.7 million if work begins next year.

Industrial or commercial use with demolition of the waste processing facility alone. This would require just over three years of effort at a cost of $27.87 million.

Industrial or commercial use with demolition of all structures. This would require three years and six months of effort at a cost of $68.49 million.

Residential development with environmental land-use restrictions in place to keep pollution undisturbed. This option would take six years of effort and cost $250.84 million.

Residential development with 13 feet of imported, clean fill over much of the site. This would allow much less restricted use of the site. But it would also require eight years of effort and $333.87 million in expense.

The far higher costs of getting the site ready for residential development is driven, in large part, by the cost ($178.54 million) of moving an Eversource electrical substation in the middle of the property, Daley noted.

It would have to be moved for residential purposes because a required buffer from the high-voltage equipment would rule out a large section of the best land for redevelopment, Daley noted. Also, he said the station would be a huge aesthetic turn-off to potential residents.

“I would say the marketability of a large residential development with a large switchyard right in the middle of it is diminished greatly,” Daley said.

The study notes that its cost estimates could vary widely up or down.

As a development scenario is picked and specific designs are drafted, cost estimates will become more precise, noted Robert Carr, senior technical leader with Weston & Sampson. 


Massive off-campus housing development planned at UConn. Think pool, fitness center, walk to campus.

Sean Krofssik 

A 738-bed student housing development is expected to break ground later this year in Storrs just off of the University of Connecticut campus in an effort to help alleviate the ongoing student housing crunch.

Landmark Properties has closed on the property called The Mark Mansfield, which will be located at 134 North Eagleville Road adjacent to the UConn main campus, and will serve as the general contractor.

The 1.56-acre site was acquired in partnership with Peninsula Investments.

“The UConn market is one we have been attracted to for a long time, particularly with this project,” said Landmark Properties’ senior director of development Chase Powell. “We like to be as close to campus as possible. It’s technically off-campus student housing, but this property is surrounded by UConn on three sides. It’s a phenomenal location. Easily walkable to the main academic core as well as the athletic facilities at UConn.”

This will be the second Landmark Properties project near the UConn campus. In 2022, The Standard at Four Corners broke ground at 1717 Storrs Road. That project includes 890 beds and 390 units and is expected to be completed this August. The Standard at Four Corners will be available to lease beginning at the start of the fall 2025 semester.

“That was the first housing project delivered in the UConn market in over a decade,” Powell said. “What attracted us to the market is the walkability to the campus, and it will be the best purpose-filled, student housing project in the market in terms of location and amenities and offerings to the residents.”

UConn spokesperson Stephanie Reitz said student housing options on UConn’s Storrs campus and nearby have been in flux, with large additions that include the opening of Connecticut Hall and the addition of more than 650 beds there at the start of the current academic year.

“However, we also recognize that increased enrollment translates into increased need for student services, including on-campus housing options, and continue to focus on ways to maximize availability without compromising quality,” Reitz said.

Reitz said the UConn education is in high demand and that there has been continual growth in enrollment.

The number of undergraduates enrolling in the school during the fall has steadily increased. In 2022, there were 18,768, in 2023, it was 19,147 and 2024, the number increased to 19,835. First-year students on the Storrs campus have increased 6.9% from the fall of 2023 to the fall of 2024.

Reitz said UConn is increasing the number of off-campus beds it will lease for students’ use at The Oaks on The Square apartments complex in downtown Storrs, which will add more than 600 beds in support of enrollment growth. These options will increase the options available to UConn students as they decide whether they live on campus or commute, added Reitz.

“First-year UConn students are guaranteed housing under the university’s on-campus residency requirement,” Reitz said. “Additionally, UConn guarantees housing for transfer and campus change students (those moving from a regional campus to Storrs) if the application deadline is met.”

Reitz said students may apply for on-campus housing during the defined residential application periods.

“Residential Life will notify students via email of their status after the application is submitted. Students notified that they qualify for housing selection will complete the housing selection process in April,” Reitz said. “Although all students may apply for housing, eligibility to live in residential housing is not guaranteed for rising sophomores, juniors and seniors and is based on multiple factors including space availability, primary campus designation and academic standing.”

Those students who are eligible for housing but do not receive a spot are placed on a wait list. Offers for housing will depend on availability, and the demand for housing and will occur through the spring and summer months if possible, according to Reitz.

Reitz said UConn was able to offer housing to those on the wait list this past year because beds became available.

“We anticipate the same trend this year, given the off-campus options opening and the regular “melt,” or reduction of students, that occurs at the start of a new semester,” she said.

Powell said Landmark is bullish on the UConn market due to “continual enrollment increases coupled with the lack of supply in the market.”

Powell said The Mark Mansfield, from an off-campus perspective, offers something that hasn’t been seen in the UConn market.

“We are offering a professionally managed property with onsite teams with robust amenities packages with pools, hot tubs, club rooms, study rooms and fitness centers. The majority of this supply at UConn is really older, outdated products. We are going to be offering something compelling to the market,” Powell said.

Powell said there will be three-, four- and five-bedroom units “attracting students to the university that enjoy living with their peers.”

The Mark Mansfield will break ground this summer and is expected to be completed by the summer of 2028.

Huskies Tavern, which was previously located 134 North Eagleville Road, will return and be located on the first floor of the property in 7,000 square feet of retail space.

“As part of our new development, the restaurant will be incorporated back into the project when we are open. It will be on the ground floor, and they will have a fully operated space, and we are excited that Huskies will reenter the property, and we think they will be a part of our long-term success there,” Powell said.

Powell said Landmark, based in Athens, Georgia, is the largest student-housing developer in the country. The company has $15 billion in assets under management including 115 residential communities and 72,000 beds across the country. The company specializes in acquisition, development and management of high-quality residential communities. Landmark has also expanded its business out of the country as well.

This is the 22nd property that Landmark and Peninsula Investments, headquartered in Miami as well as Montevideo, Uruguay, have combined on.

“We are thrilled to expand our presence adjacent to this prestigious campus with our second student housing development in the market, providing high-quality living spaces designed to complement the university experience,” Peninsula Investments managing director Juan Fernando Valdivieso said in a statement. “This investment underscores our commitment to supporting UConn’s vibrant community by delivering modern, thoughtfully designed residences that meet the evolving needs of students.”

Mansfield town manager Ryan Aylesworth said the new building will fit the character of the buildings near the UConn campus.

“The project is well supported for a few reasons. The location is a high-density area that wouldn’t impede on lesser development areas,” Aylesworth said. “We know there is a high demand for additional housing at UConn.

“We want to see affordable housing built for all ages and socioeconomic groups in town,” he added, “but this will be primarily student-housing at this location.”

Aylesworth said with more student-housing available, other housing units that were previously used by students may now become available to non-students.

“The state has asked UConn to grow its enrollment, and any additional students, faculty and staff will need housing,” Aylesworth said. “We are very committed to working with UConn on shared housing on a few fronts. Housing for the UConn workforce.

“We want people when they take a job at UConn and relocate from somewhere else and move here. We would love them to find housing here in Mansfield where it could be walkable or bikeable to their job. We want them to live in Mansfield because recent trends have gone away from that. With students scooping up off-campus housing, many UConn staff end up renting or buying in another town.”


Amid major I-91 ramp reconfiguration and detours, plans in works for another nearby ramp

Sean Krofssik

Among its busy schedule for work on state roads this spring and summer, the Connecticut Department of Transportation is planning some Interstate 91 ramp work.

The DOT said it is developing plans to realign the Interstate 91 north and south ramps at Exit 24 in Rocky Hill.

According to the DOT, the goal of the project is to address the intersection at the I-91/CT 99 ramps. Slip ramps will be removed to create shorter pedestrian crossings and ramps, according to the agency.

There will also be “full signal upgrades and integration into the Computerized Traffic Signal System are also included,” the DOT said in a statement.

The design will be completed in April of 2026, with construction expected to start later that fall, “assuming acceptance of the project, availability of funding, receipt of any required right-of-way and environmental permits,” according to the CTDOT.

The project will be undertaken with 100 percent state funds, according to the DOT.

There are 545 active capital projects planned for this year on state highways, bridges and roads.

Two hundred of the projects, like Rocky Hill, are in the planning phase and 171 are under construction.

Among the largest multi-year projects in the state continuing this year: the East Lyme Interstate-95 Interchange 74 Improvements at Route 161, the I-91/I-691/Route 15 Interchange Project that spans Meriden and Middletown as well as the Norwalk Bridge Transmission Relocation Project in Norwalk.

“It’s going to be a busy construction season,” state Department of Transportation Communications Director Josh Morgan said this month. “We have a lot of major projects that are in the middle of the process and years two, three and four is when that really picks up.

“There’s a lot of projects happening all over Connecticut. We certainly hear the frustration from the residents in the state about getting stuck in traffic because of a lane closing. But progress is going to take some patience and there is a lot of infrastructure coming into the state in the coming months,” Morgan added.

The Connecticut Department of Transportation also recently noted that it has begun construction on the Dutch Point Viaduct rehabilitation project on Interstate 91 southbound in Hartford. That means detours to access the highway.

Viaduct work Detour Map (CTDOT)

The work means the closure of the State Street on-ramp to I-91 southbound for approximately 18 months, according to the DOT.

The viaduct is an 1,800-foot-long elevated bridge structure that carries three lanes of Interstate 91 southbound over the Connecticut Southern Railroad and the I-91 northbound ramps to and from Whitehead Highway in Hartford, according to the DOT. It is near the Connecticut Convention Center and the Colt Armory.

According to DOT, the viaduct work intends to “upgrade the structural elements of the bridge to current safety standards. Improvements include the replacement of the viaduct’s bridge deck, drainage system, and installation of new barrier walls and highways lights, among other structural enhancements.

The “reconstruction project will improve safety for motorists, increase the viaduct’s load-carrying capacity, and extend the viaduct’s service life until it is replaced as part of the Greater Hartford Mobility Program.”

funds, according to DOT.

“The Dutch Point Viaduct is a vital artery for thousands of commuters and visitors traveling through the Hartford region every day,” Gov. Ned Lamont has said. “Modernizing this aging bridge is a crucial investment to ensure the safety and reliability of this key stretch of highway. I appreciate the hardworking Connecticut Department of Transportation crews and contractors for their dedication to completing these upgrades.”

About the viaduct work:

One lane of I-91 southbound in the area will be closed for approximately 18 months while work on the project is underway.

Temporary nighttime lane closures between 7 p.m. and 6 a.m. and daytime shoulder closures between 9 a.m. and 3 p.m. will occur throughout the duration of the construction period.

Additionally, the State Street on-ramp to I-91 southbound will be closed during all three stages of the project.

Motorists should anticipate potential delays during these times but can rely on traffic control measures and signage to guide them through the work zone.