New NPU wastewater treatment plant 80% complete 

Daniel Drainville

Norwich — Nearly three years into a $200 million project to build a new wastewater treatment plant, Norwich Public Utilities says the project is about 80% complete.

Construction began in November 2023, and is expected to complete in 2028. Both plants are on Hollyhock Island, and the current one continues to operate during construction of the new one.

"The analogy we use is changing a flat tire without stopping the car," said NPU spokesperson Chris Riley, one of several NPU officials who offered a tour of the facility last week.

The current wastewater plant has served the city for nearly 100 years. It was upgraded in 1955 and again in 1973. NPU says each of the upgrades was designed to give the plant another 25 years of use.

Construction workers were working Friday while NPU workers carried out regular plant operations. Plant Operator Dave Grundwalski said the construction constantly changed the path plant workers take in and out of the facility.

Water/Wastewater Utility Project Engineer Matt Hross began the tour showing a new concrete "influent junction chamber" — where the three wastewater pipes carrying sewage and storm water to the plant will meet.

The three pipes are the Cove Street Force Main, the Rose Alley Force Main and the Yantic Interceptor, a gravity line that brings sewage to the plant from homes and businesses along the Yantic River. A gravity line uses a downward slope to bring the wastewater in, while a force main uses a series of pumps to push the wastewater through.

Grundwalski explained that the Cove Street Force Main brings sewage and wastewater from Route 82 all the way out past the post office. Rose Alley brings all the sewage from Don Mallon Chevrolet throughout the city all the way to the industrial park. The two mains converge at the chamber — a concrete box where all the wastewater gets mixed together before heading into the plant.

The current junction is underground and the new junction, which is not yet connected, is above ground.

After being mixed in the new junction, the wastewater will head to the new headworks facility, a building where debris and grit is filtered out from the wastewater.

Grundwalski said items such as plastics, flushable wipes and even the occasional pairs of jeans, can get stuck in the junction.

Inside the plant, biological processes and UV light are used to clean the water before it is discharged into the Shetucket and Thames rivers.

NPU General Manager Jeff Brining said the project will benefit the health of the rivers and Long Island Sound.

NPU says reducing the amount of nitrogen discharged into the Thames River by building the new plant will have an enormous beneficial impact on water quality in the Sound.

The new plant will discharge 75% less nitrogen than it does currently, equivalent to a reduction of about 100 tons of nitrogen into the Thames River each year.

In addition, large rainstorms currently overwhelm the current plant, leading to untreated wastewater being discharged directly into the Shetucket and Thames rivers, and ultimately, the Sound. The new plant will be able to manage an additional 3 million gallons of wastewater per day, cutting down the amount of untreated wastewater that will go to the river.

The state Department of Energy and Environmental Protection ordered the city to upgrade the plant because its was not meeting water treatment requirements. NPU faced fines if it did not build the new plant.

Last month, NPU's Board of Utilities Commissioners approved a new, three-year rate schedule for all utilities which increases sewer customers' wastewater rates by 15.1% in each of the three years. The increase is largely due to having to repay loans for the project. The new rates take effect Nov. 1.

The project is funded by $72 million in state grants, and another $128 million in 20-year, 2% low-interest state loans, which will be repaid by NPU's 7,800 sewer customers.

If NPU did not increase the rates, Brining said, it would default on the loans and go bankrupt, affecting all gas, water, sewer and electric service to customers.


North Haven voters to decide on $19.8 million for road improvements

Brian Zahn

NORTH HAVEN — Residents will decide whether to use up to $19.8 million in bond appropriations for a variety of road upgrades, including pedestrian and cyclist safety improvements and paving. A vote on the projects will take place at an Oct. 20 town meeting.

This comes after the North Haven Board of Selectmen approved five separate items related to road improvements at its Thursday meeting, including upgrades to Sackett Point Road, Church Street and Pool Road.

First Selectman Michael Freda said four of those five items are eligible for state reimbursement and only one proposal, a $7 million bond authorization for milling, paving and other road improvements between the months of April and September 2027, will be fully encumbered by the town's debt service.

Freda said in an emailed comment Friday that the list of roads that would be repaved under that $7 million bond is "under discussion but not finalized for next year."

All five of the items will be up for a vote at the Oct. 20 meeting, and they will be grouped together as one question. Residents will vote on a total of three questions at the meeting. One of the other two is a tax cut for veterans with disabilities connected to their services and the spouses of those killed in action. The last item is a grouping of various budget line item transfers from the 2025-26 fiscal year.

Of the five projects headed to the Town Meeting for public approval, three are related to specific roads.

One of those projects, which would be funded by a bond appropriation of up to $7 million, would contribute to reconstruction efforts of Sackett Point Road, including road paving, the installation of new sidewalks and lighting, signage and better drainage. Last year, the town reached an agreement with a rail line operator to add signage near the Sackett Point Road underpass to prevent a recurring issue with tractor-trailers getting stuck beneath the 12-foot-9-inch underpass.

Another bond authorization proposal would allocate up to $3 million for drainage improvements on Pool Road, including replacements of storm drains, sewer pipes, curbs and runoff and pavement repairs.

 Additionally, up to $2 million would support pedestrian safety improvements on Church Street, which bridges the Town Green to Town Hall.

The fifth proposed bond ordinance would include up to $800,000 for an initiative to make town roads safer for pedestrians and cyclists, encompassing a $784,000 state connectivity grant North Haven received last year.

The Oct. 20 town meeting is scheduled for 6:30 p.m. in the North Haven High School auditorium.