April 30, 2021

CT Construction Digest Friday April 30, 2021

Winds of change

Scott Ritter

Think of it as Oil Patch version 2.0.

As the nation's nascent offshore wind industry begins revving up, New London and the surrounding region are poised to become front-and-center in the push to bring large-scale offshore renewable energy to the nation.

Roughly 10 big commercial wind projects — some languishing in the pipeline for years — are beginning to catch a tangible updraft. Once turning, colossal turbines rising off southern New England's coast will bring enough power ashore to light millions of homes.

Wind turbine height
Illustration by Scott Ritter/The Day 

In Connecticut, a major overhaul of State Pier in New London is expected to begin this spring. Danish wind developer Orsted, and its partner, New England's Eversource Energy, will use the revamped pier as a staging area for three big projects in federal waters just east of Block Island, R.I.

And in Washington, the Biden administration says it wants to start a slate of environmental reviews, make cash available to ports and developers, and offer new areas for lease off the coast of New York and New Jersey. The goal is to open the spigot on projects that promise to spur the economy while slashing harmful carbon monoxide emissions.

Indeed, the Bureau of Offshore Energy Management announced Thursday that it will begin an environmental review of Orsted and Eversource's Revolution Wind, starting the clock on a 30-day public comment period. Revolution Wind, located in federal waters 20 miles south of Rhode Island, would supply 304 megawatts of power to Connecticut and 400 MW to the Ocean State.  

The nation's first and only commercial wind farm came online four miles off Block Island in 2016. It's five turbines generate a modest 30 MW of power for the popular tourist destination.

Wind turbine jack-up barge
Illustration by Scott Ritter/The Day

In contrast, Vineyard Wind will erect 62 state-of-the-art General Electric Haliade-X turbines to supply Connecticut with 804 MW of electricity — about 14% of the state's electric supply — when it plugs into the New England electric grid in 2025. Vineyard Wind, which will use port facilities in Bridgeport, is a project of Copenhagen Infrastructure Partners and Avangrid Renewables.

"Things are going to start happening fast," says Sylvain De Guise, who runs the Connecticut Sea Grant College Program at the University of Connecticut's Avery Point campus in Groton. He likens the recent developments to the coming of spring: "A couple of buds, next thing you see are some flowers and trees blooming. When it starts happening, it happens pretty fast."

To be sure, the projects face some headwinds. Commerical fishermen say wind farms threaten their livelihoods. The State Pier project is a target of critics who cite poor oversight, cost overruns and a lack of transparency.

Still, Connecticut has signed two deals to buy electricity generated offshore. And a lot of people see a huge potential for well-paying new jobs.

"It's not for the faint of heart to try to figure out how to do this. But I think the rewards are worth the effort," says David Hardy, a former U.S. Navy submariner who runs Orsted's North American offshore wind operations.

The Day sifted through hundreds of pages of regulatory filings to take a look at where and how these massive turbines will rise from the sea bed. In the coming months, we'll follow the wind farms' progress and examine their impact on Connecticut consumers, fishermen, workers and communities.

Wind speed map
Illustration by Scott Ritter/The Day 

Meantime, companies like Groton-based ThayerMahan are ready to jump in. ThayerMahan's cadre of young, whiz-kid engineers are developing cutting-edge technology to help the industry monitor offshore waters and the marine mammals living there. The company has already signed on with Revolution Wind, where as many as 100 giant turbines could be turning by 2023.

"We don't mine coal or drill for oil," says Connecticut Rep. Joe Courtney, a Democrat. "This is just completely turning that on its head, so that now we're going to be instrumental in terms of developing global energy.

"We're suddenly becoming the new Oil Patch," he says, "even though it's not oil."

Cable cross-section
Illustration by Scott Ritter/The Day

Illustrations by Scott Ritter/The Day. Sources: U.S. Bureau of Ocean Energy Management; U.S. Geological Survey; Northeast Ocean Data.org; National Renewable Energy Laboratory; Narrbay.org; ESRI; Ørsted/Eversource; Copenhagen Infrastructure/Avangrid. Illustrations are not drawn to scale; export cable routes are approximate.


An improved and expanded passenger rail line could add thousands of jobs to Hartford and Springfield, but it might cost $9 billion

Stephen Singer

It’s back to the future for regional planners promoting a rail line that would revive the Inland Route linking New York and Boston by way of Hartford, Springfield and Worcester.

The cost is estimated at between $6.4 billion and $9.4 billion over a 10-year construction period, according to a study commissioned by the Capitol Region Council of Governments. While there is no funding for the rail line, supporters are encouraged by President Joe Biden’s proposal to spend billions of dollars on the nation’s infrastructure.

Advertisement

The study also estimates that “between 20,000 and 40,000″ jobs have left the region “due to limited regional rail access.” An improved and expanded commuter rail line would help bring them back over the next three decades.

The benefits of restoring the rail line that’s deteriorated due to a lack of investment would be tremendous for the Hartford-Springfield region, which is 40th in size in the U.S., the study says.

“We’re not a village,” said Lyle Wray, executive director of the council of governments, a planning group.

The Metro Hartford-Springfield region “suffered a degradation of passenger rail service” in the 1970s and 1980s that coincided with its regional economic decline, the study said. The study also calls for adding stations to an upgraded Hartford Line, including West Hartford, Newington, Enfield and North Haven.

Rebuilding the rail line would stoke investment in the region over 30 years of between $47 billion and $84 billion linked to new jobs in professional services, according to the study. It would include $27 billion to $48 billion in wages, residential and commercial construction jobs between New Haven and Worcester and local and state taxes in Connecticut and Massachusetts.

The study points a way for the Hartford region and Connecticut to capitalize on its location between New York and Boston.

“We’re in the middle of the barbell,” Wray said. “We’re in the middle with a bad rail system.”

President Biden is proposing about $2 trillion in public works spending, though legislation must wind its way through Congress. In addition, all 435 House members and 100 senators will compete for the federal aid.

Wray sees an advantage for southern New England, with Rep. Richard Neal, D-Mass., who is chairman of the House Ways and Means Committee, and Rep. Rosa DeLaura, D-3rd, chairwoman of the House Appropriations Committee and a New Haven resident.

Work would not have to start from scratch. The Hartford Line that connects New Haven, Hartford and Springfield opened in 2018. Remaining work includes electrification, a replacement of the Connecticut River Bridge at Windsor Locks, double-tracking in areas, five new or relocated stations and upgrading the downtown Hartford rail viaduct, the study said.

The East-West Rail project in Massachusetts would link Springfield to Worcester and Boston, and potentially westward to Pittsfield.

“These services nominally exist today, but with only one train in each direction ... unreliable performance and uncompetitively slow speeds — about an hour longer than driving in mid-day conditions,” the study said.

 “Together, the East-West Line and the completed Hartford Line would reconstitute a 21st century version of the old Inland Route — regular train service from Boston to New York via Worcester, Springfield, Hartford and New Haven, which the region has lacked for decades,” the study said.

The compactness of Southern New England establishes a “natural rail market” reinforced by the push to decarbonize the economy in response to climate change and a “gravitation to smaller, well-connected cities” in response to COVID-19, the study said.


City's School Building Committee gains approval to have authority to enter into contracts

Catherine Shen

NEW BRITAIN – The city’s School Building Committee will be exempt from holding daytime meetings and have the authority to enter into contracts, following the final approval of any feasibility study, preliminary and final plans by the Board of Education and the Common Council.

In a 9-6 vote, the council approved Wednesday to allow the SBC to hold meetings that are earlier than 6 p.m., an exemption that is also given to the commissions on aging, persons with disabilities, youth services and board of assessment appeals.

The SBC is a non-paid seven-member organization appointed by the city, according to the city’s ordinance. It is responsible for developing preliminary plans and cost estimates for each school construction project and reports are made to the Board of Education, the Common Council and the Mayor’s Office.

Two amendments were made to the approved resolution. The first involves the membership of the committee, which would still be composed of seven electors of the city appointed in accordance with the charter and while no alderpersons can be appointed, they can continue to serve as liaisons.

The second change relates to the advertisement for bids and entering into contracts. According to the resolution, it reads that upon final approval by the BOE and the Common Council of any feasibility study, preliminary and final plans, and by the BOE of the educational requirements and specifications, the SBC shall, subject to the Common Council authorizing resolution, advertise for bids for the construction and enter into contracts in the city’s name.

Two residents called in to express their concerns about the proposed changes, stating that the changes are not good governance.

Ann Speyer, a longtime resident, said it does not make sense for the Common Council to be removed as one of the final authorities to enter into a contract and guidelines that have served New Britain well for decades should not be changed. Fellow resident John McNamara agreed, echoing that the BOE should have final approval on any decisions that are made by the SBC.

Alderwoman Sharon Beloin-Saavedra, who co-led the resolution with Alderman Daniel Salerno, said nothing happens with the SBC that does not ultimately have to go through the BOE and the state, who oversees project funding.

“The BOE has always been the sole entity that makes the educational decisions for construction projects,” she said, which includes the use of the space, the architect, and the designs.

She said the new resolution does not change that process. After the BOE does its work and moves forward with the Common Council, the responsibilities of the day-to-day management of the project goes to the SBC, who hires the construction team based on the feasibility study that is approved by the BOE.

“I don’t understand the objections and the question on oversight because there’s a ton of oversight,” Beloin-Saavedra said.

Alderman Chris Anderson, who voted against the resolution, said while the amendments were good changes, they were not enough for him to support it. He believed the resolution consolidated power, reduced transparency and eliminated checks and balances.

Referencing to past practices, Anderson said if the SBC was violating the intent of the resolution, “That’s a problem and that behavior should have been corrected rather than retroactively going back and changing the wording.”

Oversight coming from the state is critical, “but we’re not a legislative body that governs anything the state does,” Anderson said. “What we can do is look at the checks and balances between the powers that be here in New Britain. That’s what’s being changed now. By removing the common council and the board of education’s checks and balances, I think that’s a bad move.”


 Developer seeks to build more than 100 age-targeted units in New Hartford

Kathryn Boughton

NEW HARTFORD — A developer is rapidly moving toward a deal to build 100 to 150 new age-targeted and age-restricted dwelling units in town.

Age-targeted is for renters ages 52 to 55 and age-restricted is for tenants older than 55. The need for senior housing has been recognized for years in the community where seniors are the fastest-growing demographic.

During the first in-person Board of Selectmen meeting in more than a year, First Selectman Daniel V. Jerram said Monday work on the proposal has been going on behind closed doors for three years. The developer is seeking a tax abatement for the project, which could cost $18 million.

“He has filed a letter of intent,” Jerram said, “and we are at the point of discussing the ‘hows and whys’ of New Hartford’s future. How do you feel about it? Would the town consider a tax abatement? This developer has asked for one over a period of time and we need to address publicly that we are thinking about it.”

The selectmen, who in open meeting appeared enthusiastic, went into executive session to discuss the ramifications of such a deal. The public, however, will have to give final approval for any abatement to be put in place.

Jerram said the property under consideration is open space and generates only $500 in tax revenue annually. If an abatement were approved, it could be for any period up to 20 years and be phased out in stages.

“For instance, we might get $5,000 in taxes in the first year, which is a lot better than $500, and then the taxes could increase over the years,” he said.

The developer reportedly wants to build the project over time, with perhaps 40 units in the first phase, another 40 in the second wave and the remainder later.

Also at issue is the impact on the sewer and water system. More than a decade ago, the town built a large sewage treatment facility, based on the assumption of rapid municipal growth. The 2008 recession left the town gasping, with a large debt and small user base as the anticipated growth became a distant dream.

The town is now selling its sewer and water systems to Aquarion Water Co. for $8 million. The town’s Water Pollution Control Authority is forming a public-private partnership with AWC to extend sewer service into Pine Meadow.

WPCA Chairman Denton Butler said his authority’s response to the proposal was “overwhelmingly positive.”

But, he added, the WPCA must consult with AWC.

“We have one set of regulations and they have another,” Butler said.

Jerram said, “The developer is looking for a signal from us. Abating taxes on a property that brings in $500 is a no-brainer, but there are a number of different ways to approach it.”

He said the trickiest part will be to balance the town’s need for senior housing with fairness to other taxpayers.



April 29, 2021

CT Construction Digest Thursday April 29, 2021

UConn Board of Trustees approves $70 million on-campus hockey arena with completion projected for fall 2022



Alexa Philippou

The UConn Board of Trustees unanimously approved a final $70 million budget for a new on-campus hockey arena on Wednesday, giving the school the green light to proceed with construction this spring in hopes of completing the long-awaited project in the fall of 2022.

The budget was $25 million more than the facility’s initial $45 million expected cost and $22 million more than anticipated in September. A total of $52.8 million has been allocated for construction. There will additionally be a $7 million set of improvements to the I-Lot parking site to relocate 360 parking spots and accommodate the hockey arena’s construction.

The new arena will offer a total capacity of 2,600, with 80 percent of bowl seating on seatbacks and the other 20 percent on benches. Upon completion, the new arena will host all of the women’s team’s games, but the school still intends to play most of its men’s hockey games at the XL Center.

Though the capacity isn’t overwhelming, the arena plans have been called “state-of-the-art” by Hockey East Association commissioner Steve Metcalf. The facility will be complete with locker rooms, training and conditioning spaces and coaches’ offices. Fans will be able to enjoy a center-hung display scoreboard and an ice-level lounge behind the goalkeeper.

“I had the pleasure of speaking with [men’s hockey] coach [Mike] Cavanaugh this past weekend and he’s very excited and appreciative of the UConn hockey arena,” said trustee Andy Bessette Wednesday in the board meeting. “I think this is going to be a real game-changer.”

UConn hopes that an upgraded facility will stir fan interest, improve recruiting and propel the hockey program to new heights, with executive vice president for administration and chief financial officer Scott Jordan evoking his alma mater of UMass as an example.

“Really what kicked it off for [UMass] several years ago was the construction of a rink on campus,” Jordan said. “When I attended UMass, there was no rink, no team, and now they’re national champions. We hope the same happens to us.”

The UConn men’s hockey team is coming off a historic season, earning its first top-20 ranking.

“I would like to pass along my gratitude to University leadership for its continued commitment to athletics and for taking the final step in making this project a reality,” athletics director David Benedict said in a statement. “Our men’s and women’s ice hockey programs have been competing at a high level under challenging circumstances, and the future of both programs got a lot brighter today.”

The project, which pre-COVID-19 pandemic was initially scheduled to be completed in the fall of 2021, will use $17 million in university funds, $33 million in revenue bonds and an expected $20 million from philanthropy, over double what the school initially anticipated they’d receive in donations. Proceeds from the sale of the school’s former West Hartford campus and the Nathan Hale Inn are responsible for $11.5 million of those university funds. Money from those sales must go toward capital projects and cannot be applied towards operating expenses.

Jordan said that the university has not issued all of the $185 million in bonding approved by the board for various new athletics projects, so the remaining $33 million will be issued for the hockey arena.

The construction of a new arena stems from the university’s decision to join Hockey East in 2013, as the conference requires schools to have an on-campus arena that seats at least 4,000 people. As the school explored options for how to comply with that stipulation, UConn was permitted to hold games at the XL Center and ultimately negotiated down the on-campus facility seating requirement to 2,500.

The on-campus Freitas Ice Forum, which holds 1,650, is typically used as the men’s practice rink and for the women’s games, though during the COVID-19 pandemic it hosted all the men’s home games. The new arena will be located adjacent to Freitas.

“We have been working with Hockey East on a scope that we could afford and through a variety of construction delivery methods to find the most efficient way to get this done,” Jordan said. “For a time, we worked with a public-private partner to try to bring this in at a much lower cost. We, in that process, did develop a design for the building with an architect, but we and the private developer both agreed that we could not build it for what they originally proposed and that the university would continue work on our own.”

The school ultimately bid the project out and received bids for $70 million, Jordan said.

The architect for the arena is JCJ Architecture, and Turner Construction Company is the construction manager.


Republicans attack Lamont climate-change and truck-tax proposals

Ken Dixon

HARTFORD — Republicans lawmakers, along with trucking and food-distribution executives, on Wednesday declared war on Gov. Ned Lamont’s proposed regional climate initiative and user tax for heavy trucks on state highways.

They called for the state to invest instead in greenways and open space, and again called for the Connecticut’s delegation in Congress to push for air pollution reductions in midwestern states whose emissions drastically affect air quality here through prevailing winds.

On a downtown street corner a block from the State Capitol complex, House Minority Leader Vincent Candelora and Senate Minority Leader Kevin Kelly charged that Lamont’s participation in the regional Transportation and Climate Initiative would steadily raise gasoline taxes on working families while providing subsidies for wealthier residents to buy electric cars.

“Gov. Lamont and his majority are advocating for $200 million of taxes levied against gasoline and trucks that the middle-class families of Connecticut are going to have to pay at a time when the middle-class family is struggling,” Kelly said. “These taxes are the most-regressive taxes. They’re coming after the middle-class wallet. What’s worse is that these taxes won’t even deliver on the promised environmental clean air that they are focused to be used for.”

Kelly, who represents Stratford, announced a “Stop the Gas Tax/Food Tax” rally that is scheduled for Thursday at the Wheels gas station and convenience store, located at 440 Lordship Boulevard in Stratford.

Under the TCI, petroleum wholesalers would pay for emission credits, raising pump prices by 5 cents a gallon in the first year, and not more than 10 cents a gallon by 2032, Lamont has said. The GOP lawmakers warned that it is likely to rise steadily over 10 years. Currently only three states in the region, Massachusetts, Connecticut and Rhode Island, along with the District of Columbia, have joined the TCI.

The proposal, which is estimated to bring in about $90 million in new state revenue in 2023, was approved by the legislature’s Environment Committee last month and awaits further action in the General Assembly. The money would be used for transit and transportation improvements.

“Common sense dictates that three states, some of the smallest states in the union, could somehow come together and have an impact on our overall emissions throughout the state of Connecticut, doesn’t make much sense when you think about it,” Candelora said. “And what this is really all about is another attempt by the Democrats to pickpocket the state of Connecticut.”

Joe Sculley, who as president of the Motor Transport Association of Connecticut represents the state’s haulers, said the TCI could “crush” small business in the state by raising prices. “It’s just a money grab,” he said, adding that the truck mileage tax has failed in 20 states. He stressed that with no auditing in the rule, out-of-state-based companies would not pay it.

He called for the state to use its emergency reserves of more than $3 billion and federal pandemic relief of $2.7 billion to fund the state’s transportation infrastructure needs. Additional money may come from the federal government to Connecticut under Presiden Joe Biden’s proposed infrastructure program.

For John Pruchnicki, owner of the Ansonia-based Coastal Carriers of Connecticut, Inc., the highway-user tax on heavy trucks, which was approved last week in the legislature’s Finance Committee, would add $175,000 to $200,000 a year to his business costs. He said he would pass that cost to his customers.

“We don’t understand why there seems to be a target on the back of the trucking industry from this governor,” Pruchnicki said.

“Simply put, the supply chain cannot be disrupted,” said Pruchnicki, whose fuel trucks supply gas and heating oil dealers. “We as an industry won’t let it happen. Those companies will pass on the additional costs at the pump, or the consumer of a house heated by heating oil.”

“What we would rather see happen is that we utilize our funding to reduce congestion on areas like [Interstate] 95, to reduce greenhouse emissions through that,” Kelly said, adding that rebates, credits and changes to building codes could be low-cost ways to fight climate change, combining with conserving green spaces.

Lamont, after an event in Meriden on Wednesday morning, said that the highway use tax is aimed at out-of-state trucks that take advantage of free interstate travel. He said he would listen to alternative proposals on how to fund the state’s future transit needs at a time when the gasoline tax is failing to provide enough revenue.

“They keep making it up,” Lamont said of the GOP criticism and campaign against his proposals.

“These trucks come in from four different states,” he said. “Each of those states has either highway user fees or tolls, then they come into the state of Connecticut and get a free ride. I want to make sure these trucks pay their fair share when it comes to keeping up our roads and bridges. If they have a better idea on how they want to pay for the roads and bridges, I am all ears. Last time they said ‘Let’s raid the rainy day fund.’”

The governor’s campaign pledge of 2018, to establish trucks-only tolls, was turned down by legislative Democrats. But during their attempts to defeat the idea, Republicans suggested that infrastructure costs could be paid through $700 million transferred from the emergency reserves — commonly called the rainy day fund — which is currently more than $3.5 billion.

The Republican leaders on Wednesday backed away from possibly suggesting such a use of the reserves this year.

Lamont recalled a recent news conference in which Republican lawmakers joined him at the Waterbury train station, where he promised improvements including two-way traffic on the train line to and from Bridgeport, if his transit initiatives win approval in the General Assembly.

“Everybody usually stands with me and says ‘I’m all in favor of two-way service to Waterbury. I’m all in favor of infrastructure.’ And I say, are you going to help me pay for it? Nope.”


After seven years, foreclosure set for Beaton & Corbin site; here's what will take its place

Brian M. Johnson

SOUTHINGTON – After seven years, the foreclosure of the Beaton & Corbin site is taking place this week, clearing the way for the land to be remediated and developed by Lovley Development, Inc. into a 13,000 square foot strip mall.

Southington Economic Development Director Lou Perillo said the town has been working to get the property sold and back on the tax rolls since 2014. He anticipates the site should be remediated and the strip mall should be up by April or May of next year. The acre of property is expected to generate $40,000 to $50,000 in tax revenue.

“We’re meeting this week with the Brownfield Land Bank who will be taking title of the land – that cleared court on Friday,” Perillo said. “We should start reactivating the property by the end of next month. Crews will start by removing the brick pile foundation and we hope to have the new foundations in place by the end of the year.”

Perillo said Mark Lovely has been on-board since 2014.

“We went out to bid publically and he was the only one to respond to the bid at the time,” he said. “He could be using the strip mall for office spaces, retail or restaurants. The tenants have not yet been identified.”

For this project, the town of Southington received a $400,000 grant from the Department of Economic and Community Development. Both the town and Lovely each put in $150,000 to the project as well. Additionally, Lovely secured a $400,000 low-interest loan from the Naugatuck Valley Council of Governments for the development of the site. The town is providing Lovely with a 10-year tax abatement contingent on the building being put up.

“We’re very excited to see this project moving forward,” Perillo said. “Some of the development will be done concurrently with the remediation work. As the excavators dig up the soil they can also dig the footings for the new foundations.”

The former plumbing manufacturing plant site, located on the corner of Chapman Street and N. Main St., is adjacent to the firehouse. It was abandoned in 1989 and the site suffered from a fire in September 2003.

Town Council Chair Victoria Triano said the council is also “very excited” to see the project moving forward.

“We have been working on this for a very long time,” she said. “We tried and tried and now we’ve finally got the property sold and headed for a productive relationship with the town.” 


Waterbury receives funding for Brownfield cleanups

Michael Puffer

WATERBURY – The Naugatuck Valley Council of Governments has granted the city of Waterbury $486,000 to help ongoing cleanups of polluted industrial properties.

Most of this money will go to cleanups that have already cost millions of state, federal and local dollars and will cost millions more before they are finished.

Still, every contribution counts, Mayor Neil M. O’Leary said.

“When you do these brownfield projects, you get money from wherever you can in whatever amount you can because they can seem like bottomless pits in the beginning,” O’Leary said.

Thomas Hyde, interim director of the Waterbury Development Corp., anticipates the money from the council will be more easily accessible than some of the larger state grants. This will help the city pay for planning and experts needed to be ready to begin heavy work once larger state grants can be accessed, Hyde said.

The city will use $200,000 of the council’s money to further the cleanup of the 17-acre Anamet Industrial site off South Main Street.

The city has already spent about $5.3 million in state and local funds to buy the Anamet site, demolish several buildings and fix the roof of a large industrial building. The city has four additional building it plans to demolish on the site, including a “very dirty,” powerhouse with a large brick smoke stack, Hyde said.

Earlier this month, the state awarded Waterbury a $2 million grant for the Anamet site. Another $2 million state grant request for the site is pending.

The city will use $200,000 from the Naugatuck Valley Council of Governments to further cleanup of the 14-acre former Anaconda American Brass site off Freight Street. The site hosted metals manufacturing for more than a century. Beginning in the 1970s, it was used by a company that processed industrial wastes.

The city has spent about $1 million to demolish eight industrial buildings at the Freight Street site. The city has one additional building left to demolish.

The city has about $400,000 left from a previous state grant for the former Anaconda site, but estimates place the demolition of the remaining 15,600-square-foot building at up to $1.1 million. The city has another $2 million grant application with the state pending on this site as well.

Another $86,000 from the council will be used to monitor underground water for pollution at the newly constructed Brass City Harvest Food Hub in the city’s South End. That facility was built on a site that underwent an industrial cleanup.

It takes great sums of money and years to tackle polluted sites, but O’Leary said he has been committed to tackling the long-standing problem of abandoned industrial sites from his first day in office in 2011.

With patience, polluted and dangerous eyesores have been made safe and put back on the tax rolls, noting redevelopments at the former Chase Brass and Copper metalworks off Thomaston Avenue and the former Mattaco site in the city’s East End.

“You just have to recognize this is the legacy that is left to us and if you don’t do anything, like people didn’t do anything for decades, they get worse and worse and more and more expensive,” O’Leary said.

April 27, 2021

CT Construction Digest Tuesday April 27, 2021

‘A bittersweet day:’ Demolition begins on Fairfield University’s Alumni Hall



Katrina Koerting

FAIRFIELD — Wally Halas started watching Fairfield University basketball games at Alumni Hall when he was 12 years old.

Several years later, in 1965, he would take the court there as a member of the Fairfield Prep basketball team, helping the school secure its first state title in 1969.

And on Monday, he watched a crane tear into the roof of the now 62-year-old building at the start of demolition to make way for a new convocation center.

“It’s a bittersweet day, but good for the university and prep communities,” said Halas, who now serves as the vice president for university advancement.

Halas said he still remembers the exhilaration he felt on game days, running out of the locker room onto the court to cheering fans who would throw red and white streamers.

“It was like a cascade of color,” he said.

He pointed to the stands, describing the faces that would watch through windows at the end of the gym and a crowd that packed the bleachers until they were standing on the top row. Cheers would echo off the cement wall that used to separate the space into two courts in the early days, amplifying each fan’s voice, he said.

“Instead of 1,200, it would sound like there were 2,400,” he said.

It will take about a month for Alumni Hall’s demolition to be completed, said Katie Hurley, the project executive for Gilbane Building Company, which is building the center and recently completed the new nursing building on campus.

The new convocation center, to be built on the same spot, is expected to be completed by the end of 2022. It was designed by Centerbrook Architects and is expected to cost $45 million.

It increases the current footprint by about 33 percent, bringing the total square footage up to 85,000 square feet. It will be able to seat 3,500 — up from 2,800 — and will host Stags basketball and volleyball games, Fairfield Prep basketball, concerts and other events.

Until completion of the new facility, the university’s athletic events will be played at Webster Bank Arena, said David Frassinelli, the university’s vice president of facilities.

He too grew up with Alumni Hall, which is where he saw his first basketball game. His father was involved with some of the university’s earliest buildings.

Alumni Hall was built in 1959 — an innovation at the time and one of the earliest pre-stressed concrete buildings. The 11 pre-cast arches used to create the curved roof set a record, according to the university archives.

“That was pretty exciting to see the arches lifted in place,” said John Phelan, who served as the field engineer on the project. His father was the architect and E & F Construction Company, which was in charge of the project, built several of the buildings on campus.

Alumni Hall was Phelan’s first project after graduating from Yale, he said. He was also a Fairfield Prep graduate and was pleased to be involved in a project that would give other Fairfield Prep students a place to play basketball.

His son attended both Fairfield Prep and Fairfield University, where he also played basketball.

Phelan said he enjoyed watching his son play in a building he helped build and would frequent the site as a season ticket holder. His daughter, Betsy Blagys, is now the university’s assistant director of recreation, working next to Alumni Hall.

“It’s a little emotional,” Phelan said, adding he would always see the building as he drove on campus. “It’s not going to be there anymore.”

But whether Alumni Hall stands or is replaced, “The buildings are less important than the memories you made and the people who did it,” Frassinelli said.

The venue hosted some memorable concerts throughout the years, including performances from the Beach Boys, The Byrds, Ludacris and John Legend. Then-Vice President George H. W. Bush also made a campaign stop there in 1988.

Both Phelan and Frassinelli said it’s time for a new structure, allowing for more space and hosting events beyond athletic games. Replacing Alumni Hall with a modern venue is the capstone of the university’s master plan to improve the student experience, which is years in the making, Frassinelli said.

“It will really raise the bar for events on campus,” Frassinelli said.


Riverfront Recapture buys 60-acre Hartford-Windsor parcel, plans community park














Zachary Vasile

Riverfront Recapture, the nonprofit organization that manages riverside parks in Hartford and East Hartford, has purchased 60 acres of riverfront land on the Hartford-Windsor town line and plans to build a new community park there.

In a statement, Riverfront Recapture officials said the property will be redeveloped for recreation, with new trails, open green spaces, piers and docks.

“This land purchase gives us a rare opportunity to conserve one of the last riverfront parcels in the region and significantly expand public access to the Connecticut River,” said President and CEO Michael Zaleski. “The redevelopment plan represents a transformational investment in the multimodal transportation system along the Connecticut River, will drive economic development and improve the environment and community health in the underserved neighborhoods surrounding the park.”

A purchase price was not disclosed.

Funding for the acquisition came from private investors, including the Richard P. Garmany Fund at the Hartford Foundation for Public Giving, the William and Alice Mortensen Foundation, and the Mowell Family Fund at the Hartford Foundation for Public Giving.

Currently, plans for the property include the creation of “Garmany Cove,” a nine-acre inlet where Riverfront Recapture plans to install a paddle sports and outdoor center, with rowing, kayaking, canoeing, dragon boating and stand-up paddle boarding all available.

New trails, space for a 10-acre commercial development and infrastructure such as fishing piers, docks and maintenance facilities are also expected to take shape, officials said. Walking routes in the park will help complete a regional trail connection between the Hartford and Windsor Riverwalks.

Wetlands within the parcel, which Riverfront Recapture said are of low quality, will be replaced by an ecologically developed floodplain wetland, and hundreds of new trees will be planted to promote the development of habitats in meadow areas.

Riverfront Recapture manages, operates and maintains four connected parks encompassing 148 acres along the Connecticut River: Mortensen Riverfront Plaza, Charter Oak Landing and Riverside Park in Hartford and Great River Park in East Hartford.


Connecticut Supreme Court hears high-stakes appeal from ousted developer of Hartford’s Dunkin’ Donuts Park

Kenneth R. Gosselin 

HARTFORD — The Supreme Court Monday heard a high-stakes appeal from the former developers of Hartford’s Dunkin’ Donuts Park, who are seeking a new trial in a wrongful termination lawsuit that sought as much as $90 million in damages from the city of Hartford.

An attorney for the developer, DoNo Hartford LLC and its construction company, Centerplan Construction Co., told a five-member panel of justices on the state Supreme Court that they did not get a fair trial in 2019. A jury in Superior Court in Hartford blamed Centerplan for not completing the minor league ballpark on time in 2016, justifying their termination by the city. The jury awarded the city damages of $335,000.

The Supreme Court will not conduct a new trial itself but instead used Monday to ask both the developer and the city questions about hundreds of pages of filings outlining their positions. The court could order a new trial in Superior Court or decide the first one was proper.

The appeal rests largely on the contention by DoNo Hartford and Centerplan that the trial in 2019 did not allow them to present evidence that they could not be held liable for “countless flaws” in the ballpark designs because the architect was under the city’s control.

That, the appeal argues, set into motion cost overruns, delays in the ballpark’s construction and finally, the termination of the developers.

“But isn’t it always the contractor’s responsibility as well to work with the architect?” Justice Maria Araujo Kahn observed. “If there’s a change and the change is because your client is in the middle of construction and now something needs to be revised, how does that become the city’s fault?”

The developer’s attorney, Louis R. Pepe, of Deutsch, Mulvaney & Carpenter, LLC of Hartford, responded: “Of course, the contractor has an obligation to work with the city and the architect, and that’s exactly what it did.”

But Pepe said an agreement in early 2016, just months before the ballpark was to completed stipulated that the city would contribute another $5 million to the project but would have signoff on any changes, leading to the missed deadline.

The city has pushed back on that contention, noting that Centerplan was working directly with the ballpark’s architects back to when construction first started in early 2015.

“Centerplan directed these architects to change the designs months earlier in several ways, in order, presumably to save money,” Attorney Leslie P. King, of Carlton Fields, who represented the city, told the justices Monday.

Few dispute the 6,100-seat stadium just north of downtown was on an aggressive construction schedule spanning just about 13-months, with a May, 2016 home opener with the Yard Goats, a Double-A affiliate of the Colorado Rockies.

With the ballpark not ready, the Yard Goats played their first season entirely on the road. A new contractor was subsequently brought in to finish the job, delaying the opening until 2017.

The development agreement for the ballpark spanned two mayoral administrations. Centerplan and DoNo Hartford were hired under former Mayor Pedro E. Segarra and fired by current Mayor Luke Bronin early in its first term in 2016.

At Monday’s hearing, justices delved deeply into contract and construction law, closely questioning both Pepe and King. From the gallery, Robert Landino, Centerplan’s chief executive, Jason Rudnick, a principal in DoNo Hartford and Attorney Ray Garcia, who represented the developers in 2019, looked on.

Landino declined to comment after the hearing.

While the appeal is largely focused on the termination from the stadium project, there could also be implications for the development around it, already underway. Centerplan and DoNo Hartford also were subsequently fired from that $200 million-plus project.

After the 2016 jury verdict, the same Superior Court judge in the case, Thomas Moukawsher, lifted restrictions that would allow a new developer to pursue building apartments, retail and entertainment space and parking garages.

If a new trial is ordered, the decision to lift those restrictions could potentially be revisited. Construction already has begun on the first of four parcels, located just south of Dunkin’ Donuts Park.

King declined to comment after the hearing, but Pepe said: “Hartford DoNo and Centerplan did not receive justice in the trial and it is our hope that this court will remedy that.”


Rocky Hill gets state funding to redevelop site of long-empty Ames headquarters

Steven Goode

ROCKY HILL — The state Bond Commission awarded the town of Rocky Hill $500,000 to help revitalize the former Ames headquarters site and transform it into what town officials hope becomes a town center village with a mix of housing and shops.

“It’s a project that’s been near and dear to my heart,” Mayor Lisa Marotta said Friday after learning of the award. “It’s been a top priority and I’m delighted to add this funding opportunity.”

The funding was secured by state Rep. Kerry Wood, a Democrat, whose district includes Newington, Rocky Hill and Wethersfield.

Wood said in a release Friday that the property has also been an important priority for her given its central location, years of sitting dormant and getting it back on the tax rolls.

“After many discussions on priorities for the town, there was no question that the Ames property redevelopment was top on the list,” Wood said. “We will create hundreds of construction jobs as well as permanent jobs and greatly increase the tax base on a property that has long been dormant. Our downtown will have more interconnectivity and truly be a wonderful place to live, work, and recreate.”

The property has been vacant and has had no redevelopment activity for at least 15 years, according to Raymond Carpentino, the town’s economic development director.

The site includes land totaling approximately 12.16 acres and a 225,000 square-foot building, most recently used for corporate offices for Ames department store, which employed up to 1,500 people at its prime, Carpentino said.

Prior to Ames, the site was used for a gas station/auto repair shop, a dry cleaners, a grocery and department store. The initial building was constructed in 1965 and subsequent additions were built as late as 1987-91 to comprise the current total area, he said.

Carpentino said the site also includes approximately 9 acres of paved parking and vehicle access areas.

“The project is a complete redevelopment of the site: demolition of the building and parking lot into a residential mixed-use development,” he said.

Marotta said the town is also seeking brownfields grants from state agencies for up to $2 million to aid with demolition of the site and that it has revised its tax abatement policies to incentivize developers.

“It’s a very expensive project,” said Marotta, adding that demolition costs could reach $1 million.

Marotta said the town is working with the property owner and a developer, who is under contract, but added that discussions are in early stages with the developer.

Wood also secured $400,000 in funding for updates to Elm Ridge Park, Rocky Hill’s signature outdoor entertainment and sports space. It includes ball fields, a skate park, basketball courts, pools, a pavilion, dog park, walking trails, and an amphitheater. The town rents various parts of the park to the public and recreation leagues to help support the upkeep of park.

The funding will be used for upgrades to help manage the increase in demand for use, which increased during the COVID-19 pandemic.


Three projects totalling $6.2M added to Winsted’s referendum

Kurt Moffett 

WINSTED — Taxpayers will have more than just the 2021-22 budget to vote on May 29.

The second question on the referendum ballot will ask residents whether they support the Water and Sewer Commission borrowing $6.2 million from the state for three infrastructure projects. The commission would pay back the loan via user fees, not taxes.

“It’s really a unique opportunity for the town to get good value and have the state participate in funding these projects,” Finance Director Bruce Stratford told the selectmen on Monday night at Town Hall.

The loan would come from the state Department of Public Health’s Drinking Water State Revolving Fund. Commission member William Hester told the selectmen early this month that the three projects have already been approved by the state public health department for low-interest financing and partial funding.

Stratford said the commission is eligible for a 25-year loan at an annual interest rate of 2%. It is also possible the commission would only have to pay back half, or $3.1 million, of that loan. A component of the state fund includes forgiveness clauses of 25% and 50%.

Selectman Candace Bouchard said these projects “support the residents and the businesses in downtown and the industrial parks so it’s really important for the town as a whole that they’re supported.”

The three projects are:

Replacement of 4,000 feet of water mains under Case Avenue, Center Street, Greenwoods Avenue, Thibault Avenue and the eastern section of Holabird Avenue, from Whiting to Florence streets.

Replacement of a decommissioned 1.5-million-gallon water storage tank on Wallens Hill with a 500,000-gallon tank to maintain fire protection, water quality and water pressure on the east side of town.

Construction of a 500,000-gallon water storage tank at the Crystal Lake water treatment on Route 263 so that the existing 25-year-old 1-million-gallon storage tank can be repaired.

A hearing on the three projects is scheduled for 7 p.m. May 25 at the Pearson School.

April 26, 2021

CT Construction Digest Monday April 26, 2021

A battle to get more clean energy into New England’s electric grid is underway. Here’s what you need to know.

Jan Ellen Spiegel

IN January 2020, Katie Dykes, commissioner of Connecticut’s Department of Energy and Environmental Protection — speaking to environmental advocates attending the Connecticut League of Conservation Voters annual environmental summit — leveled this broadside at the independent system operator that runs the six-state New England electricity grid and the federal authorities that govern it:

“Because of the lack of leadership on carbon at the ISO-New England, we are at the mercy of a regional capacity market that’s driving investment in more natural gas and fossil fuel power plants that we don’t want and that we don’t need,” she said. “This is forcing us to take a serious look at the costs and benefits of participating in the ISO-New England markets.”

It was widely misunderstood.

“People interpreted that as physically leaving the grid,” Dykes said a year later. “Ratepayers have gotten a lot of benefits of more reliable and affordable power by participating in a regional grid.”

What she had been talking about was a market paradigm the ISO uses to purchase power for the grid. Not much more than a year later, she is still talking about it. And with nothing short of evangelical zeal and little deference to a potentially paralyzing pandemic, Dykes has commandeered the other five New England states, the ISO, system stakeholders and more than a little national interest into a bona fide effort to figure out how to increase renewable power, decrease the use of fossil fuels and lower costs — or at least not let them go through the roof — and keep everyone on civil terms with each other.

“Our goal has been to ensure that we have an electricity supply that is meeting our carbon goals, that’s affordable and that’s reliable,” she said.

And that, she has also said repeatedly, means the grid needs to change.

A blueprint called the New England Energy Vision was unveiled in October, signed by all six states through the New England States Committee on Electricity (NESCOE), which represents the six New England governors’ electricity interests. The Energy Vision launched a series of online public forums featuring experts on the key areas the states felt needed overhaul: the wholesale market, transmission and governance. A fourth on equity and environmental justice was added later. The forums have generated a blizzard of documents, presentations, studies, comments and more — all laden with an alphabet soup of acronyms.

While success is not guaranteed, the effort is now bolstered by a new administration in Washington that is already making ambitious moves to deal with climate change including appointing new leadership at the Federal Energy Regulatory Commission, which regulates the ISO-NE and other grid operators.

Looking broadly at the issues that are driving what Dykes considers New England’s key problems is high up on FERC’s agenda. In March, FERC began a series of technical meetings on topics that include the market structures Dykes is complaining about.

The recent power crisis in Texas has provided extra heft by illuminating potential hazards for a grid that does not operate properly.

ISO 101

The ISO for New England, which is actually a non-profit RTO – a Regional Transmission Organization – has three main functions today: operating the transmission portion of the grid, running the wholesale markets that supply power for the grid, and doing the long-term planning for both.

The ISO-NE did not have all of those functions when it came into existence as part of deregulation in the late 1990s. Over its first 10 years, the ISO evolved from a regional power operator into one that also ran competitive wholesale electric markets and the regional transmission system — those tall power lines, not the ones that come to your house.

But it wasn’t until 2008 that it began operating what’s called the Forward Capacity Market (FCM). It’s the mechanism the ISO uses to purchase future energy resources three years in advance. It was envisioned to give the ISO the security that power will be there and to provide a commitment to potential new power sources so they can get financed and built, though not all are.

Up until 2008, states were deciding what future power they wanted, and the focus was still mostly on supporting a classic centralized grid, which has big so-called baseload power plants and long power lines crisscrossing the region. How clean the power was, from the standpoint of standard pollutants, as well as cost were the big considerations, so the push was to convert from coal and oil to natural gas.

And that was the thrust of the capacity market rules the ISO put in place for the auctions it uses to select that future power. Those rules are the crux of the dissatisfaction expressed by Dykes and others.

“We’ve been arguing about capacity market for over a decade,” Dykes said. “Connecticut was reluctant from the outset.”

The initial reluctance has exploded into full anger that the system favors greenhouse gas-emitting natural gas generation, ignores state policies and overall societal goals for clean and renewable energy to help curb climate change, and makes it next to impossible for clean energy facilities to be chosen. Dykes has been relentless in her complaint that as a result of the auction rules, ratepayers wind up paying more than they should.

In Connecticut, the ISO’s rules could make it difficult for the state to meet its greenhouse gas emissions goals and Gov. Ned Lamont’s executive order to have a 100% clean electric grid by 2040. And it makes the clean energy the state has already approved for development even more expensive.

The proposed Killingly natural gas plant has become the poster child for the failures of the existing system. The ISO has approved it through the FCM, while those concerned about climate change — including Gov. Lamont — say it’s the wrong choice and unnecessary.

Within the auction rules the ISO put in place is something called a Minimum Offer Price Rule. MOPR sets the lowest price that a resource can offer as its cost — that mainly being the amount it needs to recoup what it cost to build.

The auction is something of a reverse auction in which the lowest price wins — meaning it’s chosen by the ISO for use three years in the future. The point of the MOPR is to keep certain generators from undercutting others and manipulating the market price. The MOPR is specifically targeted at facilities that have state-sponsored contracts and other sorts of subsidies. Mostly those sponsored resources are clean and renewable energy. And that means they COULD offer cheaper power — but can’t, because of the MOPR.

Since newly built resources are mainly covering their capital costs, ones that receive subsidies and other incentives are already able to cover some of those costs. Dykes — along with a whole lot of other folks in other states even outside the ISO-NE — believe the clean resources should only have to offer a price accounting for the non-covered portion of their costs. That means they could offer a lower price and have a better chance of clearing the auction and beating out fossil fuel resources, since clean energy, while coming down in cost, still tends to be more expensive than natural gas.

Dykes and others say the ISO is over-estimating costs of clean power. And the draft Integrated Resources Plan released by her office late last year stated: “ISO-NE’s MOPR has gone well beyond its market-protection purposes.”

Indeed, the ISO has approved natural gas plants Connecticut doesn’t want and rejected the clean energy the state has already agreed to purchase. Ratepayers in Connecticut will wind up paying for both. And there’ll be an over-capacity to boot.

“Ratepayers should not have to pay twice,” Dykes said — her often-stated complaint. “We don’t want to build a whole bunch of new renewables and then find that the grid operator is extending or expanding reliance on fossil fuels.”

But she said MOPR is just one thing — the whole paradigm of clean energy, reliability and a 21st century grid needs comprehensive reform.

“We have this one-size-fits-all capacity market, but we’re not actually thinking about what does reliability look like in 2025 or 2030,” said Francis Pullaro, executive director of RENEW Northeast, an advocacy group uniting renewable energy and environmental advocates. “It’s not just having steel in the ground — we need certain types of steel in the ground.”

But there’s another player in the MOPR problem — the FERC.

Changes at the FERC

The FERC has to approve many of the processes the various ISOs have, including the forward capacity market. And the ISO-NE isn’t the only grid that uses a MOPR-style rule in its capacity auction. New York, a one-state grid, does. So does the huge PJM Interconnection that covers the mid-Atlantic all the way into Illinois — 13 states plus the District of Columbia.

During the Trump administration, in late 2019, the FERC ruled that PJM’s capacity market auction MOPR had to include the full cost of clean energy projects, even if some of the cost is already subsidized. While it didn’t directly order this for other ISOs/RTOs, it was widely seen as a shot across the bow and that all the ISOs would have to do it.

“It really set everybody back a number of years,” said Rob Gramlich, a one-time adviser to former FERC chair Pat Wood. Gramlich is now an energy consultant at Grid Strategies, the company he founded and runs. “It simply makes no sense, and they need to quit doing it.”

Bruce Ho, senior advocate in the climate and clean energy program at the Natural Resources Defense Council, added his voice to the chorus. “A very simple, straightforward fix would be to stop doing that,” he said.

The elimination of the MOPR is not a solution in itself, said Eric Johnson, the ISO-NE’s director of external affairs.

“It certainly would address the challenge some of the states have identified for bringing clean energy resources into the capacity market,” he said. ”But if we just eliminate the MOPR without finding a way to provide adequate revenue for the other resources that you need to balance renewable and clean energy, it’s not really a full solution.”

The ISO-NE has generally argued that power like natural gas needs to be available to backstop sources that may not be available all the time, like solar, or might be available in lower amounts, like wind

But is ending the MOPR a necessary first step toward getting more clean energy on to the grid?

“That’s a great question,” Johnson said without directly answering. He pointed out that the MOPR was a directive of the FERC, so the ISO can’t just eliminate it. He also said changing the capacity market rules would have to be a whole package, more than a step one followed by a step two. “We’re operating a system; we’re not operating just renewables.”

In written comments to the FERC in advance of that March 23 technical meeting on the capacity market situation, the ISO-NE seemed to be trying to have it both ways.

“While we believe that capacity markets are still the right vehicles for ensuring resource adequacy, they must evolve,” the comments said, indicating that “energy adequacy” should replace “resource adequacy,” to indicate the variability of some types of resources and newer means, such as energy efficiency or rooftop residential solar could lower energy needs.

The comments indicated the MOPR did need examination, though elimination must “be consistent with the maintenance of reliability.” In other words, it can’t jeopardize grid operations. And then went on: “Without taking additional action, the elimination of the MOPR creates risk for investors in unsponsored resources” — such as natural gas.

The FERC could very well push the ISO faster than anticipated to get rid of the MOPR and make other reforms to enhance clean energy. The change of administration from Trump to Biden is already signaling a changes in thinking on MOPR. At the March 23 session, the commissioners — including Republicans who supported MOPR in the past — indicated they’d be willing to reconsider it.

The FERC has five commissioners — no more than three from any single political party. Three are presently Republicans, but one of those positions expires in June, and Biden more than likely will fill it with a Democrat. On the day after his inauguration, Biden named one of the Democratic members as chair. And the new chair — Richard Glick — has relentlessly objected to MOPR.

He’s called arguments that MOPR protects the competitiveness of the capacity market “just plain garbage,” which he also called a “charitable” description.

And he’s said that the FERC was purposefully “making it very difficult for state-preferred resources to [be selected] in the capacity market.”

Pretty much what Dykes has said.

The FERC may well deal with MOPR, but Dykes has no intention of waiting around.

Replacement ideas

A few ideas for reforming the capacity market have bubbled to the top in the Energy Vision process. The idea with the most traction right now is the concept of a forward clean energy market, FCEM. While there’s no existing model, it would essentially be a clean energy-only market.

It’s been suggested by several groups in the past and resurfaced in Energy Vision comments from RENEW and a coalition of environmental advocates. The ISO is acknowledging it and plans a study, contracting with an outside consultant for a report due later this year. The report will also look at the ISO’s longstanding preference for a carbon charge as a solution, essentially paying to pollute as a way to incentivize lowering emissions, even though states have pointed out for just as long that a carbon charge is likely politically untenable.

Other ideas include returning capacity responsibilities to the states, instead of leaving them in the hands of the ISO, essentially subdividing the market to share the decisions between the ISO and the states, or even delegating it to the retail energy providers.

Over the last 15 years, the states gradually relinquished to ISO-NE all responsibility, control and authority over how much generation gets built, what kind and where, said Mike Hogan, a one-time generation developer who is now a senior advisor at the Regulatory Assistance Project, a group assisting the transition to clean energy.

He said the ISO had done a pretty good job maintaining system reliability, noting that the last “Texas-sized grid failure” here was the 2003 failure in the northeast. “New England managed to stop it at their border, pretty much,” he said.

But regarding the balancing act between state policies on clean energy and the ISOs, he said: “I don’t see any way out of it other than for the states to take back, in some form or fashion, responsibility for and authority over how the grid achieves resource adequacy. There’s no reason why responsibility for resource adequacy has to be centralized with ISO New England,” he said.

Casey Roberts, a senior attorney with the Sierra Club, said her organization is advocating for the states to be the primary decision makers. “The ISO and FERC would play sort of a backstop role,” she said. “That’s kind of how it was initially before the capacity market came in.”

But Caitlin Marquis, a director at Advanced Energy Economy, a trade association for the clean energy industry, worried. “Are you getting six different tiny markets?” she asked. “It’s a big responsibility for the states to take back what they did used to have, but it’s not something they’ve been responsible for, for a while.”

Some have broached the thorny issue of reforming the concept of cost when comparing generation types — particularly clean versus fossil fuel energy. The ISO’s marching orders are to provide technology and fuel-neutral power that’s reliable, at least cost.

One idea for re-defining cost might be something akin to a social cost of carbon calculation the federal government uses. Instead of the basic view of cost that exists now, a new definition of cost would also monetize attributes such as health benefits of energy sources and contributions towards addressing climate change, as well as considering fuel availability. Natural gas has struggled with availability in the winter when gas is sometimes diverted for heating. It was also one of the issues in the Texas crisis.

“That’s a big question,” said Dykes about changing the definition of “cost,” and left it at that.

“That’s a good question,” said Ellen Foley, another spokesperson at the ISO, who defined the question but offered no answer. She said the federal, state and environmental objectives are not quite aligned. “How do we get to a wholesale market that will price those attributes in?” she asked.

Ho at NRDC said it’s not that the ISO should get rid of the goal of getting reliable power at the lowest cost. “I think the problem is the perspective they have on ‘least cost’ is too narrow. It’s not counting enough things. They’re missing some costs and benefits in the electricity system that haven’t historically been within their calculations,” Ho said — namely, climate change and its nexus with electricity generation. “What’s needed is a new paradigm in thinking. How do we provide not energy markets that procure how the market used to work in the past, but more markets that look at how do we provide the service of affordable, reliable electricity that’s also clean?” he said.

An ISO effort a few years ago to get more clean energy into the system by essentially replacing a retiring resource with equivalent clean energy is largely described as a failure. Out of 800 megawatts of offshore wind Massachusetts has planned for its Vineyard Wind project, only 54 megawatts cleared the capacity auction through substitution. The rest has not.

As frustrating as the capacity market problems have been, it’s not the only grid issue that prompted Dykes to take action.

Millstone and more

The Millstone Nuclear Power Station issue involves a payment negotiated with Connecticut in 2019 that secured a 10-year guarantee that the plant — which provides about 20% of the region’s power, all of it carbon-free — would continue to operate. Connecticut has had to pick up the entire cost of that. No help from the ISO; no help from other states.

But when the Mystic Generating Station near Boston threatened to close, the ISO stepped in and got a deal to keep the plant open until 2022, now pushed to 2024. But instead of Massachusetts footing the bill, each state in the grid had to pick up part of that cost. In Connecticut’s case, it was about 25%.

“We’re now paying an outsized share here in Connecticut for the failures of that capacity market to produce investment in resources needed to keep the grid reliable,” said Dykes, indicating she repeatedly asked the ISO to apply the Mystic solution to Millstone.

There are also concerns over the ISO’s closed-door governance practices — no press and little state representation at most meetings. And there are concerns about transmission capabilities, the ISO’s original and core mission.

A recommendation from Energy Vision is to look longer term at transmission systems — 10 years into the future, instead of five, as it is now. The ISO has proposed what it calls a 2050 transmission study. “One of first things we need is for states to identify what resources they want us to build into the system 2030 to 2050 — so mainly offshore wind,” said the ISO’s Johnson.

And then they have to figure out how to pay for it. But according to Johnson, climate change will not be an explicit variable in the study, though he said it informs planning broadly.

Transmission planning also raises questions such as: What kind of flexibility will a 2050 or even a 2030 grid need so that variable power like offshore wind or intermittent power like solar can become primary sources? How would the grid of the future handle electric vehicle charging needs or the power those vehicles can put back in the grid? How would it accommodate storage, energy efficiency and other non-centralized sources like rooftop solar and move them around as needed? How will it handle the challenges of climate change?

“What is changing is that it’s no longer enough to just pile up a certain number of megawatts of capacity,” said RAP’s Hogan. “It matters what kind of megawatts they are.”

About 95% of resources currently proposed for the region are grid-scale wind, solar, and battery projects. As of January 2020, about 20,100 MW have been proposed in the ISO Generator Interconnection Queue.

And even those critical of how the ISO has handled some things acknowledge an ISO may be more important than ever as technologies and needs grow more complex.

“The grid itself is one of the most miraculous inventions of mankind from an engineering perspective,” Dykes said. “The ISO has the best engineers, system planners who manage this complex and delicate system.”

But she said: “Reliability is in the same breath as decarbonization. They have to be prioritized together.”

She’s not as totally sold as others on how reliable the grid has been, and there have been some hair-raising near-misses in recent years.

The ISO’s own Operational Fuel-Security Analysis in 2018 depicted multiple dire scenarios requiring rolling blackouts due to insufficient natural gas supplies in winter. All the more reason Dykes and others say the ISO should end a system that favors natural gas. They also point out that the price for gas tends to be highly variable, while renewable prices are more stable.

Winter cold snaps in 2013, 2014 and 2015 severely tested grid reliability as gas supplies were diverted for heat and in 2014 pushed gas prices to 10 times their normal levels.

Wildfires in Canada in July 2013 shut down transmission lines from Hydro-Quebec to both the New England and New York grids, cutting off that source of power. Lucky timing due to the July 4th weekend spared both grids catastrophic problems. Peak demand on the grid still occurs in summer — the 10 highest demand days on record are all in summer. While efficiency and things like rooftop solar have kept energy use flat, summers are getting warmer due to climate change.

On a 90+ degree day in August 2016 — the hottest summer in 122 years — a lightning strike took one Millstone plant offline at a time several other plants were not available. Power that normally cost $40 per megawatt hour spiked near $2,700 per megawatt hour on the spot market the ISO was forced to use.


Maine contractors fear labor agreement will shut them out of offshore wind work

Tux Turkel

Maine’s largest construction contractors say they fear being shut out of work in the state’s nascent offshore wind industry because of a pending labor agreement between the lead project developer and trade unions.

At issue is an agreement being negotiated between New England Aqua Ventus and the Maine Building and Construction Trades Council on the role of skilled labor in building a demonstration floating offshore wind turbine near Monhegan Island. That arrangement, called a project labor agreement, would set terms and conditions for employing workers from trade unions on the project. But more broadly, it could set a precedent for work and hiring rules for hundreds of future jobs that clean-energy advocates hope will emerge in offshore wind.

The union collaboration was announced earlier this month at a news conference, and it caught leaders of some of the state’s top construction firms off guard. One of them was Peter Vigue, chairman of The Cianbro Companies.

Cianbro is an employee-owned firm and Maine’s largest contractor, with 4,000 workers. Like an estimated 90 percent of the general contracting companies in Maine, Cianbro’s workers aren’t members of organized labor unions. They work in a so-called “open shop.”

“The pending labor agreement will preclude all open-shop contractors from involvement with the project,” Vigue said. “That would be very unfortunate.”

Cianbro has been at the vanguard of Maine’s offshore wind aspirations. It built a one-eighth-scale prototype of the Monhegan turbine platform, a University of Maine-patented design that was tested off Castine in 2013. The company has been positioning itself to be a major player – and employer – in the evolving ocean wind power industry.

“I’ve invested over 10 years in this project, but that’s irrelevant,” Vigue said. “It’s not about me. It has everything to do with our state.”

But Vigue’s concerns may be overblown, according to Chris Wissemann, the chief executive of New England Aqua Ventus. Wissemann said project labor agreements, or PLAs, are individually negotiated and can be tailored to accommodate a range of work considerations. The final language of the PLA in question is still several months away, he said.

“We’re frankly just finding our way to figure out the best way to build it,” Wissemann said about the project. “And that helps us figure out who can build it. Our intention is to have a really well-thought-out PLA. It’s not an all-or-nothing thing.”

CLIMATE VS. LABOR CONDITIONS

Confusion over the impact of PLAs isn’t limited to offshore wind. A bill meant to elevate the pay and benefits of workers on big renewable energy projects is currently being debated in the Legislature. It contains language that seeks to reward developers that enter into such labor agreements.

Vigue and other construction interests, including the Associated General Contractors of Maine, testified against the bill at a recent public hearing. The bill’s lead sponsor, however, said an amended version should ease their concerns.

The bigger issue, said Rep. Scott Cuddy, D-Winterport, is how to fulfill the dual promise of a clean-energy economy: fighting climate change impacts while creating well-paying jobs.

Project labor agreements aren’t uncommon on large construction projects, notably in places where organized labor is influential. They are widely used in Europe and are familiar to the global wind power firms now setting up shop in the United States. They have become a cornerstone of the emerging ocean wind industry on the East Coast and are being negotiated from Virginia to Massachusetts.

Policymakers and politicians see them as a tool to encourage diversity and minority hiring in a growing sector. For unions, they create long-term demand for their members. Developers count on partnerships with unions to set up training programs that can provide a reliable supply of skilled workers. That helps close the so-called labor gap, Wissemann said, on big infrastructure projects that take years to complete.

“We reached out to the trades,” Wissemann said about seeking a PLA. “We didn’t expect anything other than that.”

Wissemann was the former managing director of Deepwater Wind, which built the 30-megawatt Block Island wind farm off Rhode Island in 2016. The project, now owned by Danish wind developer Orsted, was built largely with organized labor through a PLA. Wissemann said he expects the Block Island agreement to serve as a template for the Monhegan project.

Aqua Ventus is a joint venture between a subsidiary of Mitsubishi Corp., Diamond Offshore Wind, and German energy giant RWE Renewables. It’s currently developing the $100 million project 14 miles off the coast. The Monhegan project will consist of a single, semi-submersible concrete platform supporting a full-scale, 11-megawatt wind turbine. It would send power to the electric grid via an undersea cable, enough to meet the annual needs of more than 5,000 homes.

The demonstration project is expected to kick off more than $125 million in total economic activity, according to the developer, along with hundreds of Maine-based jobs. Construction is slated for 2022 and 2023.

Beyond that, the administration of Gov. Janet Mills is seeking to create the nation’s first floating offshore wind farm dedicated to research. The project could include as many as a dozen turbines floating 20 to 40 miles offshore in the Gulf of Maine.

Taken together, the two projects could employ several hundred workers for at least a couple of years, Wissemann said. The floating concrete base of each turbine platform will weigh roughly 10,000 tons and be fabricated on land. They will require teams of carpenters to build the forms, iron workers to install thousands of reinforcing bars, engineers to operate massive cranes and electricians to handle the power cables.

Union wages for those trades range from $50,000 to $80,000 a year, Wissemann estimated.

REQUIREMENTS VS. INCENTIVES

But how that work gets done and by whom is still being decided, Wissemann said. A PLA could be developed that creates a division of labor for various elements of the project, he suggested, and leaves room for open-shop companies to participate.

That doesn’t make sense to Jackson Parker, chief executive and chairman of Reed & Reed, a nonunion general contractor in Woolwich that specializes in wind energy. The employee-owned company has a wind power services division that helped build most of Maine’s land-based wind farms.

But Parker said he doesn’t understand how some workers could agree to rules, pay and benefits that are different from those at their own company. In his view, a PLA would force the company’s employee owners to join unions in order to participate in offshore wind projects.

The broader application of PLAs on large renewable energy projects is now under scrutiny in the Legislature.

A union electrician, Cuddy said he sponsored L.D. 1231 so the men and women who will be building the surging number of solar and other renewable projects can benefit appropriately. The bill  specifically mentions “disadvantaged communities” and Mainers not well represented in construction, such as people of color.

Cuddy’s bill calls for using registered apprenticeship programs to build a workforce in the trades. The recently amended version drops a requirement for PLAs on big projects. Instead, it specifies that a developer who signs one will receive “a beneficial consideration” by the Maine Public Utilities Commission during a procurement process in which the agency ranks and selects new projects for power contracts.

In testimony at the public hearing, Cuddy stressed that any contractor could bid on a PLA.

“Every contractor who bids knows the terms before the bid and has to agree to live up to them,” Cuddy said. “But PLAs do not limit participation to union contractors or unionized employees.”

Despite that intention, the bill was widely panned by Maine contractors. Besides Vigue and Parker, opponents included representatives from the Associated Builders and Contractors of Maine, Sargent Corp. and Maine Drilling & Blasting.

Cuddy said he was “blown away” by the claims those critics made around the PLA provision.

“It’s the same opposition you hear any time you try to improve the lives of people who actually perform the work,” he said.

The bill has yet to have a work session scheduled before the committee that handles labor issues.

Whatever happens with the Aqua Ventus labor agreement and L.D. 1231, a third document may influence who works on offshore wind.

In 2019, the PUC approved a long-term contract for the Aqua Ventus project to sell power to Central Maine Power Co. The 45-page contract has many specific provisions that must be met, including those contained in a section titled “Economic Benefits to Maine.”

Throughout this section, the power seller commits to using “Maine-based entities” during various stages of the project, including development, construction, operations and maintenance. During construction, for instance, the seller must use “commercially reasonable efforts to ensure that all or substantially all, but in no event less than 50 percent of contract expenditures for the project’s construction period activities, be performed by Maine-based entities that create and/or retain jobs in Maine.”

Wissemann said Aqua Ventus intends to honor the economic benefits provisions in the power contract, but that details need to be worked out.

“The core issue for me, regardless of what the power purchase agreement says, is we need to build this with labor from Maine,” he said. “It can’t be labor brought in from other states. It has to create local jobs, or we won’t go on to project No. 2.”



Will Biden fund a high speed train from Boston to NYC? Northeast lawmakers are lobbying














Emilie Munson

WASHINGTON — On Thursday, U.S. Reps. Rosa DeLauro, Richard Neal, and other New England lawmakers had a call with an urban planner who’s pitching a high-speed train to carry people from Boston to New York City in 100 minutes or less.

The call is one of many conversations happening now among members of the Northeast Congressional delegation about securing high-speed rail for the New England region through President Joe Biden’s $2.3 trillion infrastructure bill and a transportation funding package that is also expected to pass this year.

“We’re going to fight for it,” said U.S. Sen. Richard Blumenthal, D-Conn. “We’re going to be fighting first for the American Jobs Plan and second for the investment in the Northeast that is necessary for high speed rail.”

DeLauro, D-3, said her staff was actively working with groups that advocate for more rail investment for the Northeast Corridor “to ensure these federal dollars make it to Connecticut and fund high-speed rail projects across New England.”

“Together, we can build the architecture for our nation’s future while at the same time creating millions of good-paying jobs that cannot be outsourced,” she said.

Asked whether Biden intends for his infrastructure package to fund high-speed rail projects like the one proposed for New England, Press Secretary Jen Psaki said the White House and Transportation Department are considering how it could be done.

“Certainly high-speed rail is part of an option of investment,” Psaki said Friday. “The president is a big fan of Amtrak and railways himself. But we have to work through with Congress what the different mechanisms are for funding. Where would we fund the projects? Are they through states? Are they through different grants? So that’s part of the discussion and the nitty-gritty negotiation happening in the coming weeks.”

In the eyes of New England’s rail champions, Biden’s huge infrastructure spending plans are an unrivaled opportunity to fund a massive train project that would transform the region.

“We can put a ton of money into 1950s highways, and maybe we'll get some electric vehicles so you can be traveling around in a brand spanking new electric car with an added lane to Route 93 and you'll still be stuck in traffic. Or you could be zipping across Massachusetts and zipping across the entire region at 250 mph in a high speed train,” said Rep. Seth Moulton, D-Mass., who sits on the House Transportation Committee, in a recent WBUR interview. “That's what we're really gunning for in this proposal."

But lawmakers from every region are lining up lobbying efforts to snag cash for their preferred projects — including pitches for other high speed rail projects.

Prodding the conversation in the Northeast is a group of urban and transportation design experts, civic and business leaders that has coalesced around one vision they’re calling the North Atlantic Rail initiative.

Their plan is for a high-speed rail line carrying trains moving 200 mph from New York City up Long Island, through a tunnel under the Sound to New Haven and then north to Hartford before tacking east to Providence and then Boston. Travel from Boston to New York City on this train would be two hours faster than the quickest train Amtrak now operates, they say.

They also propose a host of other rail improvements — like upgrades to the existing New Haven line to New York — and new rail expansions — like service from Boston to Springfield, Mass. and Pittsfield, Mass. to Danbury.

The whole thing would take 20 years and $105 billion to accomplish, the project’s advocates say. And they’re seeking authorization for a new federal-state partnership to run it all: the North Atlantic Rail Corporation.

“We are putting our economy and our cities at a competitive disadvantage by not having a network like we propose,” said Robert Yaro, an emeritus professor at the University of Pennsylvania and former leader of the Regional Plan Association in Manhattan. Yaro is a big name in infrastructure: he assisted President Barack Obama with rail initiatives tied to the 2009 stimulus, worked on the Tappan Zee bridge and helped lay the vision for Hudson Yards.

Since Biden took office, Yaro’s North Atlantic Rail initiative has been presented to the U.S. Department of Transportation and many lawmakers and their staffs.

“Our work right now is focused on building as strong and united a coalition as possible in these seven states — New York and the six New England states — to push this vision forward,” said Hartford Mayor Luke Bronin, who co-chairs the initiative. “This region has more than 10 percent of the country’s population, 14 percent of GDP, the highest train ridership in the country and an enormous opportunity to connect dozens of mid-size cities that have been left behind economically over the past 50 years to two of the biggest metro-areas in the country.”

Biden — or “Amtrak Joe” as he’s been nicknamed for his own frequent train ridership — already has at least some awareness of the proposal. Yaro, who has been working on this effort since 2007, described discussing his rail vision with Biden on at least two previous occasions.

In Sept. 2010, Yaro and his Penn students presented their high-speed rail plan to Biden in the White House Roosevelt Room. Biden pounded his fist on the table and said “Damn it. I’ve been waiting 30 years for this,” by Yaro’s retelling.

But some New England lawmakers are not embracing the full North Atlantic Rail vision, although they love the idea of high speed rail.

“I am not saying we are adopting hook, line and sinker what is the North Atlantic Rail Initiative, but they’ve got a lot of really good ideas that a lot of members care about,” said Rep. Jim Himes, D-4. “So we are pushing that both with the White House and obviously at the end of the day — this is a bill that gets written in Congress — so with each other.”

Some hold objections to North Atlantic Rail’s boldest idea: a 16-mile tunnel under Long Island Sound that would carry a high-speed train from New Haven to Long Island.

“I spent a lot of years and time as attorney general opposing projects that threaten the environmental integrity of Long Island Sound and this one seems to raise a lot of questions,” Blumenthal said. “I approach it with initial skeptcism, but I’ve heard very few details.”

Multiple lawmakers said they’d prefer to make improvements of expansions to the New Haven Line so that a high-speed train might run there. Yaro and Bronin said that is simply not possible because that corridor is “highly constrained,” “narrow” and “winding” and one high-speed train would yank two to three Metro-North trains out of the schedule. They set newest tunnel digging technology would allow the tunnel to be located deep underground where it would not impact the ocean floor or the wildlife of Long Island Sound.

Blumenthal also raised objections to creating a new rail corporation to do the work.

Yaro said that was needed because Amtrak “has got their hands full.” Amtrak announced it would make numerous improvements and service expansions — some in New England and some to new markets across the country — with the $80 billion Biden allocated for it in the American Jobs Plan.

DeLauro, D-3, called recent meetings with Yaro “informative” and said she appreciated North Atlantic Rail’s desire to “go big.”

U.S. Rep. John Larson, D-1, said he shares “the goals of North Atlantic Rail,” but the congressman is not committing to the details of the plan yet.

“This is an exciting vision for our region’s future,” he said. “I’m committed to improving rail connection between New Haven and Springfield, finishing the Hartford line and connecting it to Worcester, and connecting western Massachusetts to Boston with Hartford as a hub.”

Numerous other countries from Japan to Kazakhstan have high-speed trains under construction or already operating. In the U.S. there is only one such project underway: a bullet train from San Francisco to Los Angeles. That project is facing funding woes and backers are almost certain to be reaching to Biden’s infrastructure bill for aid.

Proponents of high speed rail in New England will have to compete with this and other projects proposed in Texas, Las Vegas and elsewhere for the major investment needed to kick start it. At least down payment for New England high speed rail and the necessary authorization could come from the American Jobs Plans, lawmakers and advocates hope.

Republicans have opposed Biden’s $2.3 trillion proposal as too costly and too expansive in its definition of infrastructure. They say it’s a terrible idea to fund the work through a corporate tax increase. They countered with their own smaller proposal of $568 billion to invest in roads, bridges, rail, ports, water systems and broadband.

When Biden announces part two of plan — big expansions of the social safety net, likely paid for by more tax increases on the wealthy — as soon as next week, Republican opposition is likely to grow.

Although Biden has reached out a hand to work together with Republicans, it means Democrats are likely to again use a legislative procedure that allows them to pass their vision without Republican votes.

People like Yaro are confident Amtrak Joe will get the legislation over the finish line, so they’re sprinting to ensure their project will too.

“I’ve been in this business for 50 years and this is the best opportunity we’ve had for 50 years,” Yaro said. “We’re running to catch this one if we can.”


Hamden deal includes construction jobs for residents and tax break for developer

Meghan Friedmann

HAMDEN — A vacant plot near Lake Whitney soon could be home to an apartment building with retail space in a deal that gives the developer a tax break while also setting workforce requirements aimed to promote diversity and ensure Hamden residents get construction jobs.

The proposed building would sit on Mather Street near Dixwell Avenue, behind Autozone Auto Parts. A $5.3 million investment, it would offer 30 upper-level apartments and four first-floor retail spaces, a letter from Mayor Curt Balzano Leng to the council indicates.

Stamford-based construction company USHS President Chris Downey said he hopes the project will be completed in a year-and-a-half.

Under the agreement, Curtis Eatman, the town’s director of economic development, said, Hamden would phase in the site’s post-development tax increase over six years. USHS is expected to save roughly $255,000 in tax payments overall, according to a memo from Eatman’s department that was attached to a meeting agenda.

Afterward, development could bring in roughly $142,000 in additional taxes, per the memo. Eatman stressed all numbers were preliminary and based on the town’s current tax rate.

The Legislative Council recently approved the agreement, and USHS LLC, was to sign off Friday, according to Eatman, .

As a result of a proposal from Councilwoman Dominique Baez, the town also is requiring the developer “provide evidence of best efforts” to give at least 10 percent of its on-site construction hours to Hamden residents, 6.9 percent to women and 17 percent to men of color, according to the contract language.

USHS also should draw 10 percent of its construction services from Hamden businesses, and 6.25 percent from Minority or Women-owned Business Enterprises, the contract says.

The goals are similar to those the state Commission on Human Rights and Opportunities uses for public projects, according to Baez.

“I believe that giving back these dollars to Hamden residents directly in their pockets helps the economic development of our town,” she said. “This is something I feel very passionate about … so I’m glad that we’re able to write it in this agreement here.”

While the diversity goals were included in the contract that went to the Legislative Council, Baez said she got an added provision passed that will help the town enforce those standards by requiring the site owner to provide evidence to the Economic Development Commission on a monthly basis.

“Said evidence shall include but not be limited to certified payroll records and other such information as the Commission deems necessary,” the language, provided by Baez, says. “Should Proposed Owner fail to abide by the provisions of this section, tDowney, the USHS president, said he also hopes to bring in Hamden residents to work in the retail spaces after the construction is complete. Rather than rent out the space, the company is considering using it to open its own businesses, he said.

Six of the apartments, which the economic development memo indicates will include 18 one-bedroom and 12 two-bedroom units, will meet state affordable housing requirements, according to Downey.

The plan has cleared the Planning & Zoning Commission, Downey said, noting that it previously was proposed by a developer who gave up the project.

Downey said his firm’s offer was contingent on the tax abatement. A bank currently owns the land, according to Eatman, who said the transfer would be worked out privately.

USHS still would have to obtain a series of permits before moving forward, he said.

Eatman, whose appointment as economic development director was approved officially by the council last week, expressed excitement about the project, which he said will turn a vacant spot currently collecting trash into a space with job, living and shopping opportunities.

“Projects like this bring ... vibrancy to the community, excitement to the community,” he said. “We love mixed-use developments, particularly (in) the southern part of the town.”

his Agreement shall be declared null and void.”


Cromwell officials delay vote on $1.8 million on capital projects, including Town Hall roof

Jeff Mill

CROMWELL - The Board of Finance has put off action on a $1.8 million request for a range of capital projects, including a new roof for much of Town Hall.

It did so as it awaits clarification of the ways in which impending federal stimulus funds can be used, as well as the level of tax payments, and the outcome of the vote on the proposed town budget, board Chairman Julius C. Neto said Friday.

Even as it delayed action on the other requests, however, the board approved a $130,000 allocation for a new backhoe for the Highway Department.

The board acted after Director of Public Works Louis J. Spina said the existing 1989 backhoe is no longer usable.

The town has rented a backhoe, at a weekly cost of $1,500, Spina said.

Now that he has been permission to replace the backhoe, Spina said it could be 60-90 days before the new piece of equipment arrives.

The finance department has to cut a purchase order before he can place the order, Spina said, adding that he expects the purchase order “to be ready after the weekend.”

If the capital projects list is proved next month, Spina said he is “confident the roof repair project can be completed in this construction season.”

The finance board postponed action until its May 27 meeting.

The remaining items include $1.005 million for replacement of the roof that covers the Town Hall atrium and gymnasium, the Senior Center, and the Cromwell Belden Public Library.

Also included on the list is a $332,000 allocation to replace a retaining wall on Main Street, $260,000 for the replacement of the family and consumer science kitchen at the high school, and $50,00 for a mason dump truck.

Officials are particularly intent about installing a new roof over the library, which reopened last year following a $3.2 million renovation.

Board member Edwin Maley Jr. led the effort to postpone action on the list.

Maley has long been a critic of the process that has been used to fund the capital non-recurring account.

“Why don’t we wait until we have more information” about using the American Relief Package funds, he asked.

For his part, Neto said, “I feel very comfortable with the explanation that was presented to us by (Director of Finance Marianne Sylvester),” adding “The Fund Balance is in good shape.”

Sylvester said any additional delays could upset the timeframe for several of the projects, pointing out that a roof repair project is not something that can be carried out in winter.

Town Manager Anthony J. Salvatore said Friday, “We’re pretty confident of several areas in which we can use the APP funds.”

He said he was not put off by the delay called for by the finance board, acknowledging, “It could provide us with a better financial picture of the town.”

But if delays were to stretch out beyond 30 days, “that would cut into the construction season,” Salvatore said.


Brookfield’s new senior living facility expected to open this fall

Currie Engel

BROOKFIELD — Construction on the town’s newest senior living facility is expected to be completed by Oct. 1.

The new 51,170-square-foot, three-story facility, located at 291 Federal Road, will be the town’s second senior living facility and is expected to have 136 beds. Of those, 26 beds will be in a memory care unit for residents with Alzheimer’s and dementia. There will also be 69 parking spaces on site, called Brookfield Senior Living.

The Village at Brookfield Common, the town’s other assisted living facility, is located a half mile down the road.

“There is need for additional senior housing where people who want to move out of houses— don’t want to do lawns and gutters and things like that— and still want to stay in their community,” First Selectman Steve Dunn said.

Sales offices will be open a few months prior to the opening of the new facility, he said.

Building plans show project costs estimated around $21.1 million. Developer Columbia Pacific Advisors, based out of Washington state, is building the new facility.

The first floor of the facility will include a lobby, large dining room, private dining area, living room, craft/exercise area, and a “wellness” room, according to architectural plans filed. The second floor will have its own living room, salon, cafe, card and activities rooms, lounge and media room, as well as a separate dining area.

sample menu from another Columbia Pacific Advisors facility in Lake Worth, Fla., filed with other town document suggests residents might be able to enjoy dishes like: croissant club, chilled shrimp, fresh salmon and “The Chef’s Daily Special.” Site plans show capacity to serve 136 meals— enough for all the beds— three times a day.

During a Board of Finance meeting Wednesday, officials discussed the impact of the new facility on the town’s emergency medical services, with Dunn noting that it’s arrival could result in about 3.4 EMS calls per week, increasing the town’s total calls by about 180 a year. Dunn said those numbers were just estimates for now.

But senior living centers have been known to have an impact on the town’s emergency medical services in the past.

Fire Chief Andrew Ellis said that when The Village at Brookfield Common arrived, calls increased significantly, causing the town to pivot from a fully volunteer ambulance corp to the blended career and volunteer paramedic team they now have.

“It was just way too busy for us,” Ellis said.

Ellis also expects an increase of about 200 calls annually once Brookfield Senior Living is up and running.

A proposal for the new facility was first raised in 2018 and approved in 2019. The increase in calls to fire and police were also a concern at that time.

Still, Dunn feels confident the town will be able to handle the increase in calls.

Since beginning construction in the fall of 2020, the site has faced problems with the state related to contractor misclassifications of out-of-state workers as independent contractors who were then not paid overtime. Construction has since continued and the stop work order did not delay the projected Oct. 1 completion date, said Fran Lollie, a Brookfield zoning enforcement officer.

“I think they’re prepared and ready to help people wherever they are in that process of aging,” Dunn said. “And that’s a good thing because people don’t like moving.”


Costco breaks ground for South Windsor store

Olivia Regen JI

Construction has begun on a new 163,404 square-foot Costco wholesale retail store in South Windsor's Buckland Road Gateway development area.

State Sen. M. Saud Anwar (D-South Windsor) said Costco would become an anchor store for the entire region.

Anwar added that Costco is already known for its $16 per hour salaries, which is well above the $12 minimum wage.

The store will be located at 1220 Tamarack Ave., neighboring a group of medical buildings and offices, west of LA Fitness and Evergreen Way and north of a senior living facility. The Costco store was first proposed for the Evergreen Walk area, also known as the Buckland Road Gateway development zone, in 2017.

Mayor Andrew Paterna praised the project.

“It has taken a lot of work and effort by the people, the Town Council, the Planning and Zoning Commission, and the Inland Wetlands Commission,” he said. “This has been such a team effort.”

Paterna said that Costco treats its employees fairly, and that he was excited to welcome them to South Windsor.

The PZC approved the site plan for the store on Nov. 10, 2020.