CONNECTICUT'S CONSTRUCTION INDUSTRY NEWS & INFORMATION
July 21, 2020
CT Construction Digest Tuesday July 21, 2020
Stamford reps appeal court ruling that would allow a bigger high-rise on a BLT lot
Angela Carella
STAMFORD - For the second time in four months, members of the Board of Representatives have voted to appeal a developer’s case that so far has gone against them in court.
This time it involves Building & Land Technology, which earlier this year won a ruling in state Superior Court. A judge said the board does not have the authority to validate a protest petition from residents seeking to stop BLT from building a bigger high-rise in their South End neighborhood.
Representatives this week voted 20-12 for their attorney, Patricia Sullivan of Cohen & Wolf, to file a petition for certification with the Appellate Court. If the court accepts the petition, Sullivan may appeal. If not, the case is over.
If the case ends, BLT may act on a zoning change and build a high-rise with 476 apartments on a South End parcel , instead of the 128 allowed under an existing regulation.
The board’s vote to pursue an appeal followed a nearly two-hour discussion behind closed doors, which elected officials are allowed to do when deciding matters involving pending legal cases.
It was similar to what happened in March, when the board voted for Sullivan to file a petition for certification in a case involving developer George Comfort & Sons, which is seeking to build a large LifeTime Fitness complex in High Ridge Office Park.
Sullivan said representatives, in pursuing the appeals, are acting on authority given them by the city Charter to review decisions by the Planning Board - in the BLT case - and the Zoning Board - in the High Ridge case.
“That is part of the board’s obligation under the Charter,” Sullivan said.
The developer, which is remaking a large swath of the South End in a project called Harbor Point, has “complete confidence” in its case, said Ted Ferrarone, co-president of BLT.
“It is discouraging that the Board of Representatives would choose to continue to fight both the Planning Board and the clear and decisive ruling by the Superior Court,” Ferrarone said in a statement.
The BLT case began after
representatives last year rejected a Planning Board decision
that would allow BLT to build denser housing on a 4.4-acre parcel it owns at Woodland Avenue and Walter Wheeler Drive, once home to trash hauler B&S Carting.
Representatives and BLT have said the change would allow BLT to build 108 units per acre instead of the 29 units per acre allowed under the original density allotment.
South End residents filed a protest petition with the Board of Representatives, opposing the Planning Board change and
what they called BLT’s march into their neighborhood
, which includes 177 acres listed on the National Register of Historic Places.
A few weeks after representatives rejected the Planning Board changes and
supported the residents’ protest
, BLT sued the board, saying it did not have the authority to accept the petition, and that it was invalid.
In March, Judge Marshall Berger, who handles land-use cases in Hartford and also ruled in the High Ridge case, agreed.
“The judge said he did not believe the petition was valid,” Sullivan said. “In both cases he said the board doesn’t have jurisdiction to determine whether a petition is valid or not.”
Berger blamed it on the city Charter, which he said doesn’t explain who has that authority, according to his decision.
“My response to that is, ‘OK, if the board can’t determine it, who can? And if you don’t know, how can you eliminate the board?’” Sullivan said.
If the judge thinks representatives have no jurisdiction, then their vote on the petition was irrelevant, Sullivan said. It should not affect their subsequent vote to overturn the Planning Board decision to allow denser development on the South End parcel, she said.
In the other case representatives are seeking to appeal, developer George Comfort & Sons plans to build a large LifeTime Fitness complex in High Ridge Office Park, which is surrounded by single-family homes and condominiums. That developer also claims representatives accepted an invalid protest petition from residents.
Representatives in that case decided
that a Zoning Board change to allow construction of the fitness complex would have opened the door to development that could harm the character of neighborhoods surrounding High Ridge and half a dozen other office parks in the city. They also fought for the right of condominium owners to be counted as property owners.
But
in February, Berger ruled
that, not only do representatives have no authority over the validity of such petitions, but also that condo owners aren’t landowners under the city Charter and so have no right to protest.
A month later representatives voted to appeal Berger’s decision.
Sullivan filed the petition for certification
in the LifeTime case on July 1, after delays caused by the coronavirus pandemic.
Newington's new town hall, community center project completed on time, on budget
Erica Drzewiecki
NEWINGTON – The Town Hall and Community Center Project has been completed on budget, on schedule and in conformance with plans and specifications.
Town staff began moving into the newly-built facility July 15, after the certificate of occupancy was signed and remaining code compliance issues were cleared.
Now Newington is in the final stages of the $28.8 million project, designed by QA+M Architecture and built by Downes Construction, with oversight by the Town Hall Project Building Committee. The state-of-the-art 72,000 sq. ft. facility stands adjacent to the town’s 105,000 sq. ft. former headquarters, to be demolished in Phase II of the project.
“This is going to be a fantastic resource for the community of Newington,” Principal Architect Tom Arcari told the Herald during a tour of the building Monday morning.
In spite of unforeseen setbacks in the past year, like the Metropolitan District Commission requiring the town to relocate its water main, the project remained on schedule and within budget, Arcari said.
“Many people have come together to make a wonderful product,” he said, later adding, “I think we should be crossing the finish line and cheering.”
The Board of Education offices were among the first completed. Superintendent of Schools Dr. Maureen Brummett was working inside her new office Monday, with a view of the Lucy Robbins Welles Library.
“I’m very happy with it,” Brummett said. “We have large conference rooms and I think we’ll be in much better shape technologically.”
There are multiple ways to enter the building, with designated entrances for Human Services, the Community Center and Parks and Recreation, as well as the main entrance, which brings visitors into the “grand hall.”
Here, the town’s essential services are centrally located, so residents can conduct regular business in a convenient fashion.
In terms of energy efficiency, a highly-sophisticated heating and cooling system is expected to garner the town approximately $100,000 in energy cost savings per year.
“As a committee we worked on the scope of this project,” said Joe Harpie, chairman of the building committee. “I have to say, quite honestly, that Quisenberry-Arcari Malik and Downes Construction met our specifications and even embellished them in many ways. We’re very lucky to have had them. I’m extremely proud of the new Town Hall and I think every member of the community will be proud of it.”
The construction team functioned under a comprehensive covid-19 plan, with workers’ temperatures tested daily and all required to wear masks. If the pandemic had any impact on the project, it has delayed the arrival of some gym equipment. The dual-gymnasium inside the Community Center contains 14 basketball hoops and will have the ability to host multiple sporting events at the same time and seat up to 1,100 spectators once completed.
“Because of the covid situation some gym equipment was delayed. We’re looking at completion of the gym by the middle of September,” Senior Project Manager Frank Tomcak said.
Parks and Recreation Superintendent Bill DeMaio is thrilled with his department’s new headquarters and impressed with the facility as a whole.
“I think it’s absolutely gorgeous, beautiful and functional,” DeMaio said. “It’s going to put Newington on the map for having one of the nicest indoor sports facilities in the state.”
There is much opportunity to earn revenue through facility rental to outside groups and concession sales, putting the department in great financial standing, he added.
Town Council was expected to tour the facility Tuesday evening. Town Manager Keith Chapman could not be reached for comment Monday.
Apartments proposed for Campbell Grain site in downtown Pawcatuck
Joe Wojtas
Stonington — A Boston-based developer has unveiled plans for 82 mixed income apartments on the site of the
former Campbell Grain Building site
.
Redevelopment of the site has long been considered a critical piece of the ongoing effort to revitalize downtown Pawcatuck.
Winn Companies
, which builds and manages similar projects across the country, outlined the $30 million project at the end of Coggswell Street to the Economic Development Commission during a virtual meeting Monday night. A virtual public presentation is slated for July 29 at 5:30 p.m.
“Great project guys. This is going to make a big difference in downtown Pawcatuck,” commission member Jim Lathrop told Winn officials after listening to the presentation.
Commission member Kevin Bowdler agreed calling the project a “great opportunity."
"What’s great about this is that we’re creating a (residential) community where a community doesn’t exist,” he said, adding that it will bring more residents closer to the downtown commercial area.
The commission then voted to write a letter of support for the project.
“We couldn’t ask for a more above board investor/developer to be interested in our community,” commission Chairman Dave Hammond said.
Adam Stein, Winn’s senior vice president of development, told the commission, “We’re not in the business of building and then selling projects. We’re in the business of long time ownership or properties and being part of the community.”
Plans call for a four-story building over a garage with open space along the Pawcatuck River. The building would include a mix of studio, one-, two- and three-bedroom units. Rents will range from market rate such as $1,800 a month for a two-bedroom unit to lesser monthly rents for tenants earning 30, 50 and 80% of the area household median income. Winn envisions renters coming from the Pawcatuck area.
Winn’s attorney for the project, Bill Sweeney of New London, said the project would require the town to grant about a half dozen variances and waivers of requirements such as those governing height, density and a project with all multi-family residential use. He also indicated Winn would be taking advantage of state affordable housing law that allows such projects to be built without meeting all zoning requirements.
Winn’s plan is to seek local zoning approval this summer and fall; in November apply for financing from the Connecticut Housing Finance Authority and Department of Housing, and begin construction in the November of 2021. The project would be complete in April of 2023.
Bond Commission to consider $650M for transportation, state office, minority biz relief projects
Joe Cooper
he State Bond Commission is scheduled to vote Tuesday on $650 million in borrowed funds for transportation improvements, relocating state offices, capital projects, a mixed-use development in Hartford, a minority small business program and setting up the state’s paid family and medical leave insurance program, among other items.
Tuesday’s virtual meeting
will be the second held in 2020, and the first since a special meeting in April, when the 10-member commission chaired by Gov. Ned Lamont
approved more than $700 million in financing
for various transportation projects across the state.
The commission, considering projects already approved by the Democrat-controlled legislature, on Tuesday will consider more than $111.6 million in funding for various transportation-related improvements, including bridge repairs and other highway and environmental projects. It will also vote on $46 million in requested funding for town aid road grants and highway/bridge equipment renewals.
The state Department of Administrative Services (DAS) is requesting almost $206 million to finance the newly renovated State Office Building on Capitol Avenue. Funding will be used to cover construction and relocation costs, and the demolition of an existing parking garage and development of a new 1,000 vehicle parking structure and related site improvements.
A request for $200 million was also requested by DAS for the state’s share of the cost of school expansion, renovation and improvement projects.
The state Department of Economic and Community Development is requesting more than $15.3 million to finance various business expansion and retention projects for several manufacturers and CTNext programs.
Another $5 million is being requested to provide additional funding for minority business initiatives underwritten by Hartford nonprofit HEDCO Inc.
The quasi-public Capital Region Development Authority (CRDA) is requesting $5.5 million to provide a loan or equity investment to a Hartford developer proposing to build a $21.5-million mixed-use development in a key corner of the Upper Albany neighborhood.
As reported in May
, the city council approved a 50-year deal for developer Rohan Freeman, of 7 Summits Realty LLC, to lease the vacant city-owned property for the development of apartments and office and retail space.
The Paid Family and Medical League Insurance Authority
is also requesting nearly $7 million to finance development of an employee contribution platform, and software and licensing for the launch of the program, which employees will pay for through a 0.5% payroll tax that starts Jan. 1, 2021.
In addition, $7 million in grant funding is being requested for capital improvements in distressed towns and cities; $4 million is requested for an ongoing statewide asbestos abatement program; and $7 million is requested for the town of Preston to finance additional environmental remediation of the former Norwich State Hospital.
Other funding requests include
:
$36 million to fund environmental compliance, soil and groundwater remediation, demolition, and other work at or in the vicinity of state-owned properties or related to state Department of Transportation operations;
$20 million to provide fiscal year 2021 funding for the Crumbling Foundations Assistance Fund program;
$7.1 million to finance Local Transportation Capital Improvement Program grant and oversight;
$5.6 million to finance equipment and facilities improvements and support advanced manufacturing and emerging technology programs at Connecticut state colleges and universities;
$5 million for urban bikeway, pedestrian connectivity, trails and mobility programs;
$3 million for community engagement training for law enforcement units in certain towns;
$2.3 million for construction projects at libraries in New Britain, Glastonbury, Meriden and Warren;
$2 million for telecommunications infrastructure at Connecticut state colleges and universities;
$800,000 for dredging and replacement of the floating dock system at the Marine District headquarters in Old Lyme;
$725,000 for repairs at Rentschler Field at Pratt & Whitney Stadium in East Hartford;
$500,000 for water pollution control projects at state facilities; and
$450,000 to finance improvements at
the Connecticut Regional Market in Hartford
.
Last week
, one Republican legislative leader slammed the potential approval of these funds because of new reports that Connecticut may need to dramatically cut its bonding program.
The administration’s budget director, Office of Policy and Management Secretary Melissa McCaw, recently said Lamont has reduced spending on borrowed dollars by 60% since taking office in Jan. 2019.
Newer Post
Older Post
Home