August 5, 2026

CT Construction Digest Wednesday August 5, 2026

Meriden nearing final stages of $22M bridge reconstruction project in 100-year floodplain

Cassandra Day

MERIDEN — One of three bridges under reconstruction as part of the Harbor Brook master plan to eliminate serious flooding in the downtown area opened Monday, while another is close to completion.

The one that opened is one of the two bridges at the Hanover Towers complex on Butler Street. According to Meriden City Engineer Brian Ennis, the parking lots around the towers flood frequently. Part of the reconstruction of the bridges involves raising the structures above base flood level elevation, according to an environmental assessment from the Federal Emergency Management Agency.

The goal is to dry out Hanover Street by the police station and Banana Brazil restaurant, Ennis said.

Prep work on the Grove Street bridge on the property began Monday. Ennis expects it will be blocked off to traffic Friday or early next week.

“We couldn't demolish them both at the same time because people still have got to get in and out. We filtered all the traffic down Grove Street while we did the Butler Street bridge. Now we're going to move all the traffic over to Butler while we do the Grove Street bridge,” he explained.

That phase of the project costs $14.9 million, Ennis said. The city received a FEMA grant for $11.3 million for 75% of the project, and the city is responsible for the remaining 25%, or $3.6 million, he added. 

The entire project is approximately $22 million, Ennis said

In addition to the bridges at Hanover Towers, the project includes work on the Center Street bridge.

That bridge is expected to reopen over the next couple weeks, Ennis said. The two-year project was delayed some three months due to utility issues involving electric, gas and water service, he added. 

That part of the project, estimated at $7 million, the city engineer said, is being funded by the city through a flood control bond.

With rain Monday and possibly more at the end of the week, work on the bridge is weather-dependent, Ennis said.

“If we get the paving done Thursday and Friday as we're scheduled to, we will be opening by the end of next week,” he said. 

Worst-case scenario, he added, it will reopen the week of Aug. 17.

Up next is Harbor Brook channel work from Cooper Street to the Amtrak railroad bridge, part of the overall Harbor Brook master plan, which can only be started when the bridgework is completed, Ennis said. 

That portion is in the final design stage, he added. The city will need to secure grant funding, which the city manager and grant administrators are working on, Ennis said.

The hope is all work will be done by the completion of the construction season in 2027, he added.


Amazon builder wages legal battle against Killingly over rejection of advanced-robotics warehouse

Steven Goode

PUTNAM—Ryan Companies US Inc., which builds warehouses for Amazon, and more than a dozen Killingly property owners have filed an appeal  of the Killingly Inland, Wetlands and Watercourses Commission's denial of a proposed 1.3 million square-foot robotics warehouse.

The appeal, filed in superior court in Putnam, seeks to reverse the commission's 3-2 vote in July that prevents the $200 million project from moving forward. The appeal also asks the court to direct the commission to approve the application.

Simultaneously, Ryan Companies has filed new applications with the inland, wetlands and watercourses commission and the town's planning and zoning commission. The wetlands application was received by the commission at its Monday meeting and a date for a public hearing was set for Sept. 14. Evan Seeman, an attorney with Robinson & Cole, told the commission that the applicants will be prepared to make a presentation on the project at that hearing.

In the complaint, the plaintiffs argue that the commission's decision to deny the application was made because Ryan Companies did not seek reasonable and prudent alternatives to reduce the square footage of the building and reduce the size of impervious area caused by the parking lot.

However, the complaint claims that the company did reduce the building size by 87,000 square feet during the months-long public hearing and also investigated a suggestion that the company consider a parking structure but determined that it would not result in any meaningful benefit in terms of reduced impact to wetlands.

The complaint also claims that during the commission's deliberations in July some of its members stated that they never asked the applicant to further consider reducing building size or a parking structure even after the town's third-party peer reviewer had examined the alternatives analysis and it was satisfied that Ryan Companies had satisfactorily addressed the issues.

The appeal also alleges members of the commission were biased and illegally predetermined an intent to deny the application; the commission was illegally constituted with some members who had undisclosed and improper conflicts of interest; the commission was illegally constituted with some members who engaged in undisclosed and illegal ex-parte communications; the commission improperly applied Section 10.3 of its regulations (relating to feasible and prudent alternatives) when voting to deny the application; and that section 10.3 was not applicable because the commission did not vote to conduct a public hearing on the ground that there may be a significant impact to inland wetlands or watercourses but instead due to public interest.

Killingly Town Manager Brian Palaia did not immediately respond to a request for comment.

Amazon has said the advanced-robotics "first-mile" facility would employ more than 500 people full-time and the building project would create 200 construction jobs.

The company also plans to construct its own on-site sewage treatment system in response to the town's moratorium on new customers for its own system that could last a decade or more.

Details of the initial project include: 60 loading docks; 430 trailer parking spaces; 930 vehicle parking spaces; and two driveways on Westcott Road, also known as Route 607, one for cars and one for trucks.


Amazon warehouse proposal moves forward after July denial | Exclusive

Connor Linskey

A new application for a proposed Amazon warehouse in Killingly is now moving forward after the previous application for the project was denied on July 6. 

The Killingly Inland Wetlands and Watercourses Commission unanimously accepted Ryan Companies US, Inc.'s new application for the project at their meeting on Aug. 3. A public hearing on the proposed warehouse will take place at the commission's next meeting on Sept. 14. 

"As you recall, the motion to deny last month was without prejudice on the grounds that the applicant examine additional alternatives," Robinson+Cole Attorney Evan Seeman, who was representing Ryan Companies, told the commission. "As part of the application materials that have been submitted, there's additional information and commentary on the alternatives. In addition to that, the applicant is considering some potential design modifications and looks forward to the opportunity to address the commission next month with a full presentation." 

Ryan Companies' new application entails construction of a warehousing and distribution center totaling approximately 1,288,220 square feet on about 556 acres of land. Located between I-395, Westcott Road and Mashentuck Road, the project includes associated landscaping, stormwater drainage improvements, parking, loading spaces and wetland crossings. 

Differences between the new application and old application 

At their meeting on July 6, the Killingly Inland Wetlands and Watercourses Commission denied Ryan Companies' application for construction of a warehouse located between I-395, Westcott Road and Mashentuck Road by a 3-2 vote without prejudice. 

The denied project proposed a 1.38 million-square-foot warehouse and distribution center on 556 acres, about 87,000 square feet smaller than the current proposal. Both plans include landscaping, stormwater improvements, parking, loading areas and wetland crossings. The new application also includes about 44,369 square feet of wetland mitigation, up from roughly 16,921 square feet in the project denied July 6.

The inland wetlands and watercourses commission denied the project on July 6, believing that it would cause the irretrievable loss of wetland resources. Since the vote was without prejudice, Ryan Companies was able to submit a new application to the commission that addressed their concerns about the project. 

Another reason the commission denied the project on July 6 is because its reviewer Tighe & Bond suggested that the size of the warehouse would cause wetland impacts. Tighe & Bond also noted that other large, successful distribution facilities in Killingly operate with much smaller footprints, such as the UNFI warehouse (approximately 447,270 square feet) and the Frito Lay facility (approximately 467,520 square feet). The commission suggested that Ryan Companies reduce the size of the warehouse in their next application. The company's compliance led the commission to accept the application at their meeting on Aug. 3.

How can this project move forward if there is a moratorium on warehouses? 

At its meeting on June 15, the Killingly Planning and Zoning Commission approved a moratorium on new applications for warehouses and distribution centers. The moratorium is in effect from July 20, 2026 - June 30, 2027. 

While the moratorium is in effect, no new applications for the approval of a warehouse or distribution center may be filed, processed or approved. This includes new distribution centers, fulfillment centers as well as truck and freight terminals. 

The purpose of the moratorium is to provide the commission with time to consider and implement revisions to the town's current zoning regulations concerning large commercial warehouses and distribution centers and related uses. The moratorium was submitted to the planning and zoning commission by former Killingly Town Councilwoman Michelle Murphy and Killingly resident Lisa Danburg following the public's opposition to two distribution centers with an unnamed tenant proposed at 90 Putnam Pike and the proposed Amazon warehouse. 

The new application for the Amazon warehouse was filed on July 16, before the moratorium took effect, which is why the project can move forward in the approval process despite the moratorium being in effect.