Demolition of Sports Haven & its 100-foot horse mural begins, with the artist looking on

Mark Zaretsky

NEW HAVEN — Of the estimated 140,000 vehicles that whizzed by the giant horses and jockeys painted on the former Sports Haven video off-track-betting facility in the city’s Long Wharf section Tuesday, few if any stopped to witness the start of its demolition.

But Tony Falcone was there, joined by Robert Greenberg

They didn’t come to mourn the demise of Sports Haven (originally called Teletrack) and its 100-foot-tall very public art mural installation, but to celebrate the fact that it was there as long as it was, as well as to document it and hopefully preserve some small part of it for posterity. 

But you can understand if they might get a little misty-eyed.

Falcone is the guy that painted those giant horses on the building at 600 Long Wharf Drive beginning in 1995 and finishing in 1996. Since then, they’ve been seen by millions and millions of people passing by on one of Connecticut’s busiest stretches of highway.

Greenberg is the guy who a few years ago founded the Lost in New Haven Museum at 80 Hamilton St., which works to preserve classic, lost icons of New Haven just like this. 

They came out of their visit with a promise from Johnny Carabetta, a member of the family that owns demolition contractor J & J Demolition — and the one operating the excavator that was working around the edges of the building Tuesday before things ratchet up further on Wednesday — to try to keep some good-sized chunks intact to go in the museum.

“Even a fragment will tell a massive story,” said Greenberg.

“I’ve run every emotion,” said Falcone, who lives these days in Cheshire and has a studio in Prospect. He said he has been thinking about the demolition “since it first got announced” and was cheered because “I started to hear how much this means to so many people,' he said.

“Now I’m feeling kind of elated” after talking to Johnny Carabetta and hearing that he didn’t think it would be too much trouble to preserve some large pieces of the mural.

Carabetta said the work on Tuesday was just some “cleanup” to get ready for bigger-scale demolition on Wednesday and beyond. 

Falcone also has done many other pieces of public art in New Haven — including whimsical murals of the Greater New Haven shoreline that used to decorate the cafeteria walls of the old New Haven Register building at 40 Sargent Drive, where Jordan’s Furniture now does business.

He painted the east wall of Sports Haven in 1995 and the north wall in 1996, he said. It took him about 3 ½ weeks on location, with about the same length of time in preparation before he got there, he said.

“We’re celebrating the mural. We’re not not mourning,” said Greenberg. “We’ll celebrate the fact that the mural has existed — and now the fragments will live on in the museum. ‘I’m here to salvage some of the fragments of the mural,’ he said.

City officials, including Robert Dillon, New Haven’s building official, have been very understanding and accommodating, Greenberg said.

“We’re very excited to be here,” Greenberg said. “We’re here to tell their story… We’re hoping to get a piece of the eye, a piece of the head.”

In fact, they’re already telling the story of the Sports Haven mural in a new exhibit that opened last week in the museum, which features a number of Falcone’s sketches and studies for the murals — their actually are two of them, although they originally were meant to link up and stretch all the way around the museum.

The exhibit also has a table-sized 3-D model of Sports Haven depicting the murals as they originally were conceived. 

“The goal in my mind was to make an exhibit,” Greenberg said, pointing out that the site that Sports Haven and Teletrack before it have long stood on once was Sargent Manufacturing — and before that it was underwater.

As he spoke just after noon, a big Carabetta excavator started up and rolled over to a spot just beneath the Sports Haven sign, with Johnny Carabetta at the controls. 

His brother Joe Carabetta also was on hand — and at one point their mother, Anna Carabetta, stopped by with some cold water and fresh-baked peach muffins to help them along.

The muffins, or at least fresh-baked sweets, aren’t entirely a sidelight to the story.

Ever the artist, Falcone looks at the oil tanks just across the road in the 85 East Street Tank Farm and sees an opportunity. 

“The next thing I want to paint are those tanks,” Falcone said. “I want to paint them to look like cupcakes and birthday cakes.”

Demolition began Tuesday after city Building Official Dillon signed off on the permit. Demolition is coming about a month later than the previous estimate by city officials

Earlier this summer, the building underwent an environmental assessment, Dillon has said. Part of that assessment was to determine whether the building had any asbestos-laden tiles, he said. 

The process leading up to demolition began in February when a limited liability company affiliated with Queens, N.Y.-based Criterion Development submitted an application to the city.  Demolition plans were approved, with demolition to begin after a cooling-off period that ended on May 27.

Criterion hasn’t specified what it plans to do with the property. Sports Haven closed at the end of November 2025 after being purchased by Criterion in March 2021

The Long Wharf Responsible Growth Plan for the Long Wharf section calls for a mixed use of residential and large format commercial uses, city Economic Development Administrator Michael Piscitelli has said.

One example of large format commercial use might be a grocery store or other large format retail store, Piscitelli has said.

But as recently as 2019, environmental studies identified Long Wharf as facing a significant flooding threat over the next several decades as result of climate change and storm surges from New Haven Harbor.

Piscitelli said Criterion officials have not indicated to city officials what their plans for the property are. But Piscitelli said a responsible growth plan released in 2019 for the city’s Long Wharf section calls for a mixed of residential and large commercial uses.

An example of large format commercial use, according to Piscitelli, could include a grocery store or other type of large retail store.


Proposed Killingly warehouses continue to roll through review

Sara Bedigian

Killingly — The traffic engineer for a proposed development at 90 Putnam Pike told the Planning and Zoning Commission Monday night that the project is not a mega warehouse that would generate large amounts of truck traffic.

The comments by Kevin Solli came as the commission continued its public hearing Monday night on a proposal By Killingly 1 LLC for warehouses of 178,750 square feet and 297,500 square feet, respectively.

He said a traffic study calculated the warehouses will generate 87 trips — 14 of those being trucks, during the peak hour in the morning, and 91 trips — 14 of those being trucks, during the peak hour in the evening.

“That is one vehicle a minute, this is not a mega warehouse as people have been alluding to, this does not represent a large trip generation, and our analysis is that, as we have indicated, will not have adverse impacts on the traffic operating conditions of the area,” Solli said.

It is still unknown what businesses would occupy the warehouses. Because of this, residents have expressed concern the traffic numbers could increase from the numbers cited by Solli.

Solli said if there are additional trips, a new traffic study and addition approval from the commission along with the state Department of Transportation and Office of State Traffic Administration would be needed.

Solli also explained changes made to the traffic plan that included truck turning, parking, and signage. He said trucks would not be allowed to turn right out of the facility's driveway to avoid crossing the center line. A left turn will allow trucks to easily access Interstate 395.

He said the plan also added additional driveway safety measures and lighting that reduces glare.

The changes were in response to a review by engineering firm Tighe and Bond, which was hired by the town. Solli said while Killingly 1 replied to most of the Tighe and Bond comments, his team is still waiting to complete a noise study and refine its stormwater analysis. He said Killingly 1 will have that information in time for the commission's next meeting on Sept. 21.

“We honestly believe that projects improve with this level of review and comment as we make changes and tweaks to our plan and design,” Solli said.

He also said the project would have no adverse impacts on water quality and would meet all stormwater requirements. The town’s Inland Wetlands and Watercourses Commission has approved the plan.

“We feel that ultimately the project today is better than it was when it was initially first submitted,” Solli said. “We are confident we are going to be able to address every one of their concerns and at the end of this process we will have the best project for the town of Killingly.”

This development has been in discussion for months at Planning and Zoning Commission meetings since the initial application was received at the end of last year but then withdrawn. A new application was filed this spring, and the commission has held several nights of public hearings since then.

While Solli said the facility “will not have an adverse impact on the community,” several residents continued to voice their concerns about traffic, stormwater management and water quality during Monday’s public hearing.

Opponents said they don’t believe truck drivers will follow the signs to not take a right turn out of the facility.

“They are on a timeline, they aren't going to take the extra time to go the routes you want them to go,” said Lina Wagner of Putnam, who is the Democratic candidate for state representative from the 51st District.

Others were concern about not knowing what businesses will come to the facility before the project is approved.

Resident Russ Daniels said it “raises a red flag. ... If they aren’t willing to identify themselves, let's throw them out of Killingly.”

The commission voted to extend the public hearing to its next meeting on Sept. 21.

The commission also voted to receive the new application for the nearly 1.3 million-square-foot Amazon distribution center “Project Husky” on Westcott Road and hold a public hearing for the commission’s Sept. 21 meeting. This comes after the developer Ryan Companies withdrew and resubmitted its application last month.

The commission also decided to have Tighe and Bond review the project.


Developer seeks approval for 420,000 cubic yards of fill to redevelop former Berlin brickyard

Andrew Larson

A Utah developer is seeking approval to bring 420,000 cubic yards of fill to a long-abandoned Berlin brickyard as part of a plan to redevelop the 57-acre property.

The project, slated for 303 New Britain Road, would create a pad site for two commercial buildings totaling 44,000 square feet on about 16.7 acres, along with 90 parking spaces, stormwater basins and a new permanent railroad crossing.

Berlin Industrial Redevelopment LLC, an affiliate of Farr West, Utah-based Industrial Development Advantage LLC, is seeking site plan approval for the project, which would be located on a 56.9-acre property owned by Connecticut Sand & Stone Corp.

Braxton Buckway, the company’s chief financial officer, is listed as the applicant.

The property has been vacant since the early 1980s. From about 1900 into the 1960s, it operated as the Donnelly Brick Co., which mined clay to depths exceeding 30 feet. The resulting pits were filled during the 1970s, including with material generated during construction of Route 9, but the fill was never engineered or compacted.

That uncontrolled fill left the site geotechnically unstable and environmentally contaminated. The developer says the site cannot be redeveloped without massive amounts of fill to stabilize the ground and raise the grade.

Berlin Industrial Redevelopment, or BIR, proposes using up to 420,000 cubic yards of fill to do that.

The project depends on Connecticut’s Large-Scale Beneficial Filling Pilot Program, created under Public Act 21-88. The program allows the state Department of Energy and Environmental Protection to authorize up to four sites for large-scale placement of qualifying lightly contaminated fill material when needed for redevelopment. Sites must require at least 100,000 cubic yards.

The program was created to provide a lower-cost alternative to purchasing conventional clean fill for projects where large quantities are needed.

BIR says conventional clean fill would make redevelopment at this scale financially impractical. Its principals have worked on the property since 2017 and have spent more than $1 million on environmental investigations, engineering, taxes and interest, according to the project summary.

Under the plan, buildings, pavement and clean cover would form an engineered cap over the property, while groundwater monitoring would continue for up to 30 years.

The volume of truck traffic has emerged as a major concern in the town’s review.

Public Works Director and Town Engineer Michael S. Ahern wrote in a May 28 memo that importing the fill would require about 26,250 truckloads over roughly 250 days, or about 105 trucks entering and exiting the property each day. Peak-hour traffic could reach 17 trucks, he wrote.

The applicant’s traffic study found no significant operational impact on local roads, but Ahern said activity at the site entrance would be significant and noticeable to nearby property owners.

Acting Sgt. Thomas Bobok of the Berlin Police Department’s traffic bureau estimated in a June 14 memo that a truck could arrive every 3.5 to 4 minutes through an unsignalized driveway shared with Prentiss Place, a residential complex of about 90 units. He recommended an engineering review of turning radii and said the volume could frustrate residents and other drivers.

The Conservation Commission has separately raised concerns about fill placement and groundwater protection. Ahern also asked the applicant to show that its stormwater system can handle a 25-year design storm.

The Planning and Zoning Commission opened a public hearing July 23. The applicant has since sought additional time under state extension provisions, and no decision date has been set.

Town approval is required before BIR can apply to DEEP. The developer is targeting state approval by mid-2027, with construction extending into 2030.